Productivity Improvement in Assembly Line of Automobile Industry by Reducing Cycle time of Operations


Productivity Improvement in Assembly Line of Automobile Industry by Reducing Cycle time of Operations
Authors : Ashish Kalra, Sachin Marwah, Sandeep Srivastava, Rajesh Bhatia
Publication Date: 03-05-2016

Authors

Author(s):  Ashish Kalra, Sachin Marwah, Sandeep Srivastava, Rajesh Bhatia

Published in:   International Journal of Engineering Research & Technology

License:  This work is licensed under a Creative Commons Attribution 4.0 International License.

Website: www.ijert.org

Volume/Issue:   Volume. 5 - Issue. 05 , May - 2016

e-ISSN:   2278-0181

 DOI:  http://dx.doi.org/10.17577/IJERTV5IS050185

Abstract

The present study has been done at one of the famous automobile industry, a leader manufacturer of tractors. The aim of study is to identify various problems on the assembly line which are causing assembly line to stop. There are two assembly lines rear assembly line and front assembly line and the work has been done on the front assembly line. The bottle neck problem is found in front assembly line and is solved by reducing the cycle time of the operations by utilizing the work study techniques and material handling techniques and it was found that cycle time of the bottle neck operation was reduced by 14.66 % per trolley.

Citations

Number of Citations for this article:  Data not Available

Keywords

Key Word(s):    

Downloads

Number of Downloads:     393
Similar-Paper

Call for Papers - May - 2017

        

 

                 Call for Thesis - 2017 

     Publish your Ph.D/Master's Thesis Online

              Publish Ph.D Master Thesis Online as Book