Assessment of Reliability Indices of Abuja Distribution Network

DOI : 10.17577/IJERTV3IS20570

Download Full-Text PDF Cite this Publication

Text Only Version

Assessment of Reliability Indices of Abuja Distribution Network

P. U. Okorie , D. M. Ezekiel

Department of Electrical Engineering, Ahmadu Bello University, Zaria.

Abstract Assessment of customer power supply reliability is an important part of distribution system operation and planning. Analysis of outage data from a practical distribution system is performed in order to assess the reliability indices. The aim of this paper is to assess the reliability and analysis customer power supply of Abuja metropolis, evaluating with SAIDI, SAIFI and CAIDI. The report consists of measuring past performance, including reliability indices; sources of data; and existing methods for reliability analysis. The main conclusion of the report is that, Abuja municipal city reliability network measured failed below the average industrial city: SAIDI, 392.88 hrs of duration in 2007, CAIDI, 1.82 hrs while SAIFI records 215.47.

Keywords Reliability, Distribution system reliability, Availability, Failure and Reliability indices.

  1. INTRODUCTION (Heading 1)

    Reliability concerns are often split into three categories: Adequacy, Security and Quality. Adequacy is the capacity and energy to meet demand; Security is the ability to withstand disturbances; and Quality is the acceptable frequency, voltage and harmonic characteristics. There are more than forty reliability indices, the most common one include SAIDI, SAIFI, CAIDI, MAIFI, ASAI etc, other common indices that measure unavailability include ASUI which is complement of ASAI, EENS, and AENS. The indices used in this report are SAIDI, SAIFI and CAIDI [1]. These indices are generallyyearly average of interruption of frequency and duration. They attempt to capture the magnitude of disturbances by load lost during each interruption. We used these indices; CAIDI, SAIFI and SAIDI method because there were best suited to the subject discussed. These reliability indices are among the following.

    1. Customer Average Interruption Duration Index (CAIDI) is an indicator of average interruption duration, or the time to restore service to interrupted customers.

    2. System Average Interruption Frequency Index (SAIFI) is an indicator of average service interruption frequency experienced by customers on a system.

    3. System Average Interruption Duration Index (SAIDI) is a composite indicator of outage frequency and duration and is calculated by dividing the customer minutes of interruptions by the number of customers served on a system. Mathematically, SAIDI is the product of SAIFI and CAIDI. Thus, a SAIDI of 100 may be achieved by a SAIFI of 1 and a CAIDI of 100, or by a SAIFI of 1.25 and a CAIDI of 80

  2. RELIABILITY STUDIES OF ABUJA DISTRIBUTION NETWORK

    The power system is vulnerable [2] to system abnormalities such as control failures, protection or communication system failures, and disturbances, such as lightning, and human operational errors. Therefore, maintaining a reliable power supply is a very important issue for power systems design, operation and planning [3]. The results of reliability assessment of distribution systems supplying electricity of various consumers in Abuja Federal Capital Territory are presented and discussed. The various reliability indices computed for the distribution systems in all the districts of Abuja Federal Capital Territory are based on the methodology described. The major causes of power supply problems in Abuja have been identified and also summarized in Tables 1 to 4. There are a number of problems associated with transmission, distribution and consumption of electricity in a rural area. A study into the problems of power supply shows that disturbance on the commercial mains power supply can be categorized into the following: (i) Weather problem, (ii) Human problem and (iii) Planned problem. The computed annual outages and their durations between 2002 and 2007 according to fault type are given in Table 1.

    Table1: outage and duration of faults types for the Abuja distribution network, 2002 2007 (Okorie, 2009)

    S/N

    Nature & causes of fault due to bad joint

    2002

    2003

    2004

    2005

    2006

    2007

    Avg. outage & duration /year

    Freq.

    Duration

    Freq.

    Duration

    Freq.

    Duration

    Freq.

    Duration

    Freq.

    Duration

    Freq.

    Duration

    Freq.

    Duration

    1

    UG cable

    120

    158.74

    87

    224.38

    142

    280.46

    56

    305.79

    176

    545

    98

    381.16

    113.2

    315.92

    2

    Cable sparked by diggers

    5

    45.61

    5

    38.12

    5

    38.34

    4

    55.45

    6

    51.37

    2

    14.35

    4.5

    40.54

    3

    Pole and equipment damaged by vehicles

    28

    176.82

    35

    130.23

    31

    234.34

    27

    237.6

    79

    379.3

    17

    241.23

    36.2

    233.25

    4

    Failure of line due to jumper or cross arm

    1079

    558.1

    286

    476.6

    472

    331.04

    349

    454.81

    551

    720.3

    422

    804.82

    526.5

    557.6

    5

    Tree falling on line

    171

    218.91

    21

    105.28

    56

    262.13

    78

    218.5

    52

    295.5

    55

    338.99

    72.2

    239.88

    6

    Faulty transformer

    32

    374.6

    11

    253.37

    26

    435.32

    33

    261.13

    30

    426.6

    9

    590.36

    23.5

    390.23

    7

    Faulty switchgear/panel

    10

    69.54

    19

    54.02

    20

    86.12

    29

    116.41

    37

    98.74

    16

    105.97

    21.8

    88.47

    8

    Faulty tripping unit

    151

    138.06

    54

    124.79

    165

    110.43

    30

    53.72

    95

    269.6

    6

    15.73

    83.5

    118.72

    9

    Earth fault

    938

    231.53

    441

    209.08

    <>1689

    756.4

    2235

    822.86

    805

    1467

    1178

    1478.3

    1241.

    3

    827.57

    10

    Over current

    846

    226.36

    342

    254.04

    1328

    498.93

    1750

    702.7

    785

    573.8

    1197

    1070.9

    1041.

    3

    554.48

    11

    Other causes

    219

    274.02

    40

    168.96

    80

    382.53

    156

    364.13

    119

    336.6

    232

    851.38

    141

    396.26

    12

    Yearly total

    3599

    2472.3

    1341

    2038.87

    4014

    3416

    4747

    3593.1

    2735

    5164

    3232

    5893.2

    3278

    3762.91

  3. RELIABILITY INDICATORS FOR MEASURING SERVICE QUALITY PERFORMANCE MODELING

    These are the five key reliability indicators recently introduced for the purpose of assessing distribution reliability performance. These are the reliability indices used by the Floridas Investor owned electric utilities (IOU) for assessing and auditing their performance in electricity distribution system [5]. Such reliability indicators are listed below:

    1. Customer Average Interruption Duration Index (CAIDI);

    2. System Average Interruption Frequency Index (SAIFI);

    3. System Average Interruption Duration Index (SAIDI);

    4. Momentary Average Interruption Event Frequency Index/Indicator (MAIFI);

    5. Customers Experience More than Five Interruptions (CEMI5).

    The mathematical computation is as follows:

    CAIDIik =

    SAIFI =

    Sumof all customers min utes int errupted (CMIik ) 1

    Total number of customersint erruptions (CIik )

    Total number of customer' s int erruption (CIik ) 2

    ik

    SAIDIik MAIFIE

    =

    ik=

    Total number of customers served (Cik )

    Sumof all customers min utes int errupted (CMIik ) 3

    Total number of customers served (Cik )

    Sumof all customers momentaryint erruption events (CMEik ) 4

    Total number of customers served (Cik )

    CEMI5ik = 5

    Customers exp erienced morethan 5int erruptions (CEM 5ik ) x Total number of customers served (Cik )

    100%

    i = 1, 2, 3 m

    k = 1, 2, 3 n wherei denotes year and

    k denotes kth district

    These five performance indices express interruption statistics in terms of system customers. A customer here can be either feeder, or an individual, firm, or organization who purchases electric services at one location under one rate classification, contract or schedule. If service is supplied to a customer at more than one location, each location shall be counted as a separate customer.

    Furthermore, the well known basic reliability indices are defined in equations ( 6 ) to ( 12 ).

    1

    Mean Time To Failure (MTTF) =

    Mean Time To Repair (MTTR) =

    6

    Failure Rate

    Fault Duration

    7

    No. of Outage

    Mean Time Between Failure (MTBF)= MTTF + MTTR 8

    1

    Failure Rate () = Repair Rate () = Availability =

    Unavailability =

    9

    MTTF

    1

    10

    MTTR

    11

    12

    The computations of the above basic reliability indices required acquisition of fields data on distribution component failure statistics over the desired time frame.

  4. ANALYSIS OF DATA COLLECTED USING RELIABILITY INDICES

    Tables 2 to 4, and Figure 2 summarize the results of several reliability analysis carried out in respect of electricity

    supplied to the customers in Abuja municipal city and satellite towns from 2002 -2007. Herein, service reliability indices (Failure rate, MTTR, MTTF, MTBF, CAIDI, SAIDI and SAIFI) were computed for all the five districts and for each year of the study period using equations (1) to (12).

    Table 2: Reliability indices of Abuja distribution network for the specified study period *[4]

    S/No

    Parameters

    Wuse District

    Garki

    District

    Kubwa

    District

    Karu District

    G/Lada

    District

    Abuja

    Metropolis

    1

    Total no. of

    failure/outages

    5558

    3676

    552

    1151

    1091

    19681

    2

    Total outages

    duration

    4208.49

    5003.99

    1404.28

    1890.71

    2480.15

    21496.88

    3

    Average duration of outage (hrs/yr)

    (MTTR)

    1062.35

    1252.21

    703.34

    945.36

    1240.08

    3582.81

    4

    Failure rate

    158.618 x 10-3

    104.908 x 10-3

    31.507 x 10-3

    65.696 x 10-3

    62.215 x 10-3

    374.448 x 10-3

    5

    Mean Time To

    Failure (MTTF)

    6.322

    9.532

    31.739

    15.222

    16.073

    2.671

    6

    Mean Time

    Between Failure

    1068.85

    1261.74

    735.08

    960.58

    1256.15

    3585.481

    7

    Repair Time

    9.412 x 10-4

    7.986 x 10-4

    1.422 x 10-4

    1.058 x 10-4

    8.064 x 10-4

    2.791 x 10-4

    *study period for Wuse and Garki : 2004-2007; Study period for Kubwa, Karu and G/Lada: 2006-2007; Study period for Abuja Territorial District: 2002-2007.

    450

    400

    350

    300

    250

    200

    150

    100

    50

    0

    SAIDI CAIDI

    SAIFI

    2002

    2003

    2004

    2005

    2006

    2007

    Figure 2: Abuja Municipal Network.Table3: Service reliability indices data year 2007

    Utility Name ADC [4]

    District

    Registered Customers Served (C)

    Interruptions (N)

    Total feeder hour of interruption (FHI)

    Feeder Interrupted (FI)

    SAIDI

    CAIDI

    SAIFI

    Garki

    28,858

    1164

    2908886

    2239381

    100.80

    1.30

    77.60

    Wuse

    26,344

    617

    1494583

    1083617

    56.73

    1.38

    41.13

    Kubwa

    35,013

    200

    1489220

    466840

    42.53

    3.19

    13.33

    Karu

    41,104

    802

    3510623

    2197908

    85.41

    1.60

    53.47

    G/Lada

    31,023

    466

    941031

    963781

    30.33

    0.98

    31.00

    Table 4: Summary of service reliability for Abuja 2002 2007 [4]

    Year

    Registered Customers Served (c)

    Interrupted (N)

    Total feeder hour of interruption

    (FHI)

    Feeder Interrupted (FI)

    SAIDI

    CAIDI

    SAIFI

    2002

    145,989

    3599

    24061907

    35027627

    164.82

    0.69

    239.9

    2003

    146,349

    1341

    19892439

    13083601

    135.92

    1.52

    89.4

    2004

    148,750

    4014

    33875333

    39805500

    227.73

    0.85

    267.6

    2005

    150,394

    4747

    36025379

    47594688

    239.54

    0.76

    316.47

    2006

    158,446

    2735

    54547676

    28889987

    344.27

    1.89

    182.33

    2007

    162,342

    3232

    63780925

    34979290

    392.88

    1.82

    215.47

    450

    400

    350

    SAIDI CAIDI

    SAIFI

    300

    250

    200

    150

    100

    50

    0

    2001 2002 2003 2004 2005 2006 2007 2008

    Figure 3: Abuja Municipal City Reliability Network Measured.

  5. RESULTS AND DISCUSSION

    From Table 1 through 4 and Figures 2and 3, it can be seen that outages per feeder per year for all districts variedbetween (1341 to 4747). The Wuse feeders recorded the highest outage rates per feeder per year while the least is Kubwa feeder. However, Garki had the highest duration of outage account for 5003.99 hours. This records a total of about 209 days continuous `blackout`. This is followed by Wuse, which had 4208.49 hours duration of outage. This means a total of about 176 days continuous blackout. The least is also Kubwa with 1404.28 hours, 59 days blackout. These values are far too high when compared to the typical 2% value for industrialized nations and accounts for much of the national operational problems in the supply of electric power. There is need to analyze problem in the supply of electrical power. There is further need to analyze the fault to identify reasons for the high level of unavailability of the feeders.

    According to Table 1, several factors have been identified to be responsible for these outages. The major cause of outages is earth fault (earth leakage). The average

    outage frequency per year recorded is 1214.3 and accounted for 37.04% of the total failure. The time duration was

    adequately maintained, increases operational cost might be incurred even if there was no frequent system failure.

    The year by year assessment showed that the performance of the station was best in 2003. However, this value fell below expectation. The outage frequency recorded in 2003 was 1341 failures with 2038.77 hours of no electricity. The worst year was 2005 which accounted for about 4,747 failures which resulted to 3594.10 hours.

  6. CONCLUSION.

Reliability evaluations are an important and integral feature of the planning, designs and operation of all engineering systems. Engineers must not only appreciate the benefits obtained from reliability assessments, but also how much such assessments can be made. The study has presented a statistical method of determining the power system components` failure rates and the associated durations. The method adopted was found to be satisfactory and comparable with other standard methods. The reliability parameters obtained gave a true reliability picture of the network.

REFERENCES

[1] Reliability of Electric Utility Distribution Systems: EPRI White

827.57 hours. The next major cause was over current due to surge which contributed about 31.77%. The duration of the outage association with this was 1041.3 hours. Other

[2]

Paper ECOSYNC; EPRI 1000424. Dec, 6 (2006), pp 5.1-5.4.

C.C. Liu, G.T. Heydt, A.G. Phadkeetal, The Strategic Power Infrastructure Defense (SPID) System IEEE control system Magazine, vol.20, Issue 4, August 2000, pp 40-52.

significant outages were due to jumper or cross arm 16.06%; other causes 4.3%, under ground cable fault 3% etc. The basic under line factor responsible for the poor performance, however, was poor maintenance and attitude

to duty. The total number of forced and scheduled outages

  1. Rao J.M. et al Assessment of Reliability indices in Electric Power

    Distribution Systems, International Journal of Engineering Research &Indu. Appls. (IJERIA) ISSN O974-1518, vol.2, No.vii (2009) , pp 447-459.

  2. P.U. Okorie, Reliability Evaluation of Electricity Distribution System, using Abuja Metropolis as a case study, January, 2009. M. Eng. Theses, School of Engineering, Electrical/Electronics Program

    were recorded with other causes which accounted for only 4.3%. Maintenance which is the back bone of successful performance had not been properly carried out for the Abuja 33kV and 11kV distribution network. If the feeders were not

me. AbubakarTafawaBalewa University, Bauchi.

James D.B. (2006) , Review of Floridas Investor Owned Electric Utilities (IOU) Service. Reliability in (2005) Florida Public Service Commission.

Leave a Reply