Contractor Selection in Construction Industry using Fuzzy-Logic System

DOI : 10.17577/IJERTV3IS111008

Download Full-Text PDF Cite this Publication

Text Only Version

Contractor Selection in Construction Industry using Fuzzy-Logic System

Kolekar P. B.

Department of Civil Engineering TKIET

Warananagar, India

Kanade G. N.

Department of Civil Engineering TKIET

Warananagar, India

Abstract Selection of the most appropriate & potential contractor to deliver a project in time is most significant decision making process to ensure the successful completion of construction projects. The construction industry has witnessed the failure of many contractors due to different reasons like labour problems, financial problems, poor performance, social and political problems, lack of safety considerations at worksite etc. All these incidents have led to the impression that the current scenario of awarding the contracts is inefficient in selecting the contractor capable of meeting the demands and challenges of present times and hence needs to be reviewed accordingly. This work presents contractor selection using Analytic Hierarchy Process & Fuzzy Group Decision making Method and results are evaluated by using an actual case study in infrastructure development.

Keywords- Bids, Contractors, Parameters, Decision, Analytical

Hierarchy Process (AHP), Fuzzy Group Decision Making.

  1. INTRODUCTION

    Selection of the contractor for the job has been primarily based on bid price alone. The selection of the lowest bidder is one of the major reason for project delivery problem, when contractor faced with a shortage of work, desperately quoted a low bid price simply to remain in business with the expectation to be offset through claims. So, selection of the contractor for construction project should be based on a set of multiple decision criteria both price and non-price related.

    In practice, a contractor selection problem can be divided into two stages,

    1. A large number of potential contractors are invited and investigated based on a set of predetermined criteria and then a short list of contractors is drawn by the project owner called Prequalification stage.

    2. An appropriate contractor is selected from the short list to execute the construction project called Bid evaluation stage.

      Decision making in construction projects is a complicated process and in most cases the value for each criterion is determined roughly by decision makers. In many cases, criteria are examined by linguistic variables such as, very low, low, medium, high and very high. Quantifications of these linguistic variables using fuzzy logic will provide a more realistic approach for evaluation of a construction project. These ambiguities necessitate the use of fuzzy logic in the selection process. Use of fuzzy logic opens the possibility for straight forward translation of the statements in

      natural language into a fuzzy set, which is very essential for decision making under uncertainties. Fuzzy set theory provide with a respectable inventory of theoretical tools for dealing with concepts expressed in natural language. By fuzzy set of various types we manipulate them in a great variety of ways for various purposes. They enable us to express and deal with various relations, functions and equations.

  2. METHODOLOGY Following methods are described in this work,

      1. Analytic Hierarchy Process (AHP)

        1. Introduction

          Analytic Hierarchy Process (AHP) is an effective decision making technique based on multi-criteria decision making methodology (MCDM). AHP is a method that can be successfully used as it incorporates all the attributes pertaining to contractor selection and then prioritizes each attribute resulting in easy judgment of best contractor. The AHP works on three primary functions namely structuring, measurement and synthesis.

        2. How the AHP works

          The AHP consider a set of evaluation criteria and a set of alternative options among which the best decision is to be made. It is important to note that, since some of the criteria could be contrasting, it is not true in general that the best option is the one which optimizes each single criterion, rather the one which achieves the most suitable trade-off among the different criteria.

          The AHP generates a weight for each evaluation criterion according to the decision makers pairwise comparison of the criteria, higher the weight, the more important the corresponding criterion. Next, for a fixed criterion, the AHP assigns a score to each option according to the decision makers pairwise comparison of the options based on that criterion, higher the score, the better the performance of the option with respect to the considered criterion.

          Finally, the AHP combines the criteria weights and the option scores, thus determining a global score for each option, and a consequent ranking. The global score for a given option is a weighted sum of the scores it obtained with respect to all the criteria.

        3. Steps for contractor selection using AHP

          Step 1) Identify the criteria attributing to contractor selection. Step 2) Structure the decision hierarchy from the top with the goal of the decision, then the criteria on which this goal depends to the lowest level which is a set of the alternatives. Step 3) Construct a set of pair wise comparison matrices. Each element in the upper level is used to compare the elements in the level immediately below with respect to it.

          Priorities can be obtained of each criterion and of alternatives with respect to each criterion using these comparison matrices by normalization. The scale used for these comparisons is given in Table No.1

          Step 4) Final priorities of the alternatives can be obtained using priorities derived from step 3. Priority of criteria and priority of contractors are then multiplied and added for each of the contractor to obtain the final scores.

          TABLE 1 THE FUNDAMENTAL SCALE

          Intensity of importance on an absolute scale

          Definition

          Explanation

          1

          Equal importance

          Two activities contribute equally to the objective

          3

          Moderate importance of one over another

          Experience and judgment strongly favour one activity over another

          5

          Essential or Strong importance

          Experience and judgment strongly favour one activity over another

          7

          Very Strong importance

          An activity is strongly favoured and its dominance demonstrated in practice

          9

          Extreme importance

          The evidence favouring one activity over another is of the highest possible order of affirmation

          2,4,6,8

          Intermediate values between the two

          adjacent judgments

          When compromise is needed

          Reciprocals

          If activity i has one of the above numbers assigned to it when compared with activity j then j has the reciprocal value when compared with i

          Rationales

          Ratios arising from the scale

          If consistency were to be forced by obtaining n numerical values to span the matrix

      2. Fuzzy Group Decision-Making Method (FGDM)

        1. Introduction

          Conflict always occurs in group decision making since members in a group generally do not reach the same decision. Resolving conflicts becomes an important issue in group decision making. For group decision making, the main approch is collective individual decision making. A Fuzzy Delphi method is used to adjust the fuzzy rating of every expert to achieve the consensus and to tackle this type of problems.

        2. The basic concepts of fuzzy numbers

          A fuzzy number is a fuzzy set on R which possesses as the following three properties:

          1. is a normal fuzzy set, i.e. Ht.=1

          2. The -cut of is a closed interval for every (0, 1],

            i.e. lower limit is 0& upper limit is 1

          3. The support of is bounded. i.e. all values have upper bound to the value 1

          Special cases of fuzzy numbers include crisp real number and intervals of real numbers. Although there are many shapes of fuzzy numbers, the triangular and trapezoidal shapes are used most often for representing fuzzy numbers. The following describes and definitions show that membership function of triangular and trapezoidal fuzzy number and its operations.

          Definition A: fuzzy number is convex, if

          1 + 1 2 min 1 , 2 ,

          2 , 2 , 0,1 .

          Alternatively, a fuzzy set is convex if all -level sets are convex.

          Definition B: A fuzzy set in the universe of discourse X is normal, if

          1

          sup = 1. x

          A nonempty fuzzy set can always be normalized by,

          / sup . x

          Definition C: A fuzzy number is a fuzzy subset in the

          universe of discourse X that is both convex and normal.

          One of the most important concepts of fuzzy sets is the concept of an -cut and its variant. It is a bridge from well- defined structure to fuzzy environment.

          Definition D: For a fuzzy set defined on X and for any number a (0, 1]; the cut, , and the strong cut, + are defined as:

          = ,

          + = > .

          That is, the -cut (or the strong -cut) of a fuzzy set is the crisp set (or the crisp set +) that contains all the elements of the universal set X whose membership grades in

          are greater than or equal to (or only greater than) the specified value of .

          Definition E: A triangular fuzzy number can define as a triplet (a1, a2, a3). Its membership function is defined as,

          0, < 1 ,

          = 1 /2 1, 1 2 ,

          3 /3 2 , 2 3 ,

          0, < 3.

          Let and be two fuzzy numbers parameterized by

          b i , b i , b i , b i . If it still necessary new trapezoidal fuzzy

          1 2 3 4

          the triplet (a1, a2, a3) and ( b1, b2, b3 ), respectively. Then the operations of triangular fuzzy numbers are expressed as,

          (+) = (a1, a2, a3) (+) (b1, b2, b3) = (a1 + b1, a2 + b2, a3 + b3)

          (-) = (a1, a2, a3) (-) (b1, b2, b3) = (a1 – b3, a2 – b2, a3 – b1)

          numbers C (i) = c i , c i , c i , c i are presented, and their

          1 2 3 4

          average Cm is calculated. The process could be repeated again and again until to successive means A m , B m ,C m , become reasonably close (we can define the distance of two fuzzy

          numbers, d 0.2 )

          (x) = (a1, a2, a3) (x) (b1, b2, b3) = (a1b1, a2b2, a3b3) i

          (÷) = (a1, a2, a3) (÷) (b1, b2, b3) = (a1/b3, a2/b2, a3/b1)

          Definition F: A trapezoidal fuzzy number = (a1, a2, a3, a4),

          1 2 3 4, ( if a2 = a3, is a triangular fuzzy number) its membership function is defined by,

          0, < 1

          1 /(2 1 ), 1 2

          = 1 2 3

          4 /(3 4), 3 4

          0, > 4

        3. A Fuzzy Group Decision-Making Method

          In this section, we will summarily introduce Fuzzy Delphi method ranking fuzzy numbers procedure, and the defuzzification value of the trapezoidal fuzzy number.

          Fuzzy Delphi Method –

          The fuzzy Delphi method consists of the following steps.

          Step 4) At a later time, the same process may re-examine the ratings, if there is important information available due to new discoveries.

        4. Ranking fuzzy numbers procedure

          1. Intuition ranking method. From membership function curves of fuzzy numbers, many fuzzy numbers can easily rank its orderings by intuition ranking method. Human intuition would favor a fuzzy number with the following characteristics: higher mean value and at the same time lower spread.

          2. If its ordering cannot rank by intuition ranking method. We can rank fuzzy numbers by -cut method, fuzzy mean and spread, or other methods. We use the defuzzification value of the trapezoidal fuzzy number to do the necessary rank orderings. We take trapezoidal fuzzy number to represent experts opinion.

        5. The defuzzification value of the trapezoidal fuzzy

    Step 1) Experts Ei , i=1,,n provide the possible realization time (or rating) of a certain event: the earliest time (or the

    pessimistic rating) a i , the most plausible time (or rating)

    number

    Definition: For a trapezoidal fuzzy number,

    A = , , , , its defuzzification value is defined

    1 1 2 3 4

    (a i , a i ), and the latest time (or the optimistic rating) a i . to be, C = ( a1 + a2 + a3 + a4 ) / 4

    2 3 4

    The time given by each expert Ei are presented in the form of a trapezoidal fuzzy number

    A (i) = a i , a i , a i , a i , i = 1, n

    of the trapezoidal fuzzy number to do the necessary rank orderings. We take trapezoidal fuzzy number to represent experts opinion.

    1 2 3 4

    Step 2) First, the average (mean) A m of all A (i) is computed. This requires computation of the average of all

    a i , a i , a i , and a i , i=1,, n. Hence

    1 2 3 4

    A m = am 1, am 1, am 1, am 1

    n n n n

    = 1 a(i) , 1 a(i) , 1 a(i) , 1 a(i) .

    n 1

    i=1

    n 2

    i=1

    n 3

    i=1

    n 4

    i=1

    3

    4

    m 3

    m 4

    Then for each expert Ei the differences

    Fig. 1 The defuzzification value of the Trapezoidal fuzzy number

    i i

    1

    2

    m 2

    am 1 a , a a , a

    a i , a

    a i

    n

    = 1 a(i) a(i), 1

    n

    a(i)

    From above Fig.1 we can see that if the left area a1pa2 +

    a2pqc is equal to the right area cqra3 + a3ra4 then,

    n 1

    i=1

    1 n 2

    i=1

    (1) (a2

    – a1)/2 + (c – a2

    )(1) = (a3- c) (1) + (1) (a4

    a3)/2

    a(i), 1

    n

    a(i) a(i), 1

    n

    a(i) a(i)

    => c = ( a1 + a2 + a3 + a4 )/4

    Therefore, we obtain the defuzzification value of the

    2 n 3

    i=1

    3 n 4 4

    i=1

    trapezoidal fuzzy number is,

    are found and sent back to the expert Ei for re-examination.

    Step 3) Each expert Ei presents a revised trapezoidal fuzzy number

    1 2 3 4

    B (i) = b i , b i , b i , b i , i = 1, n

    This process starting with Step 2 is repeated. The average Bm

    is calculated by above formula (9) with the differences that

    now a i , a i , a i , a i are substituted correspondingly by

    c = (a1 + a2 + a3 + a4) / 4

  3. DATA COLLECTION

    For evaluation process, a case study of a Tender work of Establishment of Ground Control Points, Carrying out Engineering survey and Preparation of Master Plan with necessary Detailed Project Report of Infrastructure for

    1 2 3 4

    Urun-Islampur Municipal Council, Tal – Walawa, Dist Sangali, Maharashtra, India has been propose.

    TABLE 2 DATA FROM CASE STUDY

    Parameter

    Notation

    Unit

    Bidder A

    Bidder B

    Bidder C

    Bid Value

    C1

    Rs.

    3875500

    4185540

    4456825

    Financial

    Stability

    C1

    %

    100

    31

    41

    Technical capability

    C3

    %/p>

    85

    90

    80

    Management

    Skill

    C4

    %

    80

    90

    85

    Reputations & Safety

    C5

    %

    90

    90

    90

    Quality

    C6

    %

    90

    70

    80

  4. EVALUATIONS

    1. Using AHP

      Fig.2 Hierarchy structure for Contractor Selection

      The criteria used for contractor selection and hierarchy structure are obtained for the Analytic Hierarchy Process given in Table 2 and Figure 2 respectively. Carry out pair- wise comparison matrix is obtained by comparing all criteria attributing to contractor selections according to the importance of one criterion over the other criterion. The following matrices (Table 3 and 4) show pair-wise comparison. The Fundamental scale used is given in Table 1.

      C1

      C2

      C3

      C4

      C5

      C6

      C1

      1

      5

      7

      9

      9

      9

      C2

      0.2

      1

      5

      5

      7

      7

      C3

      0.14

      0.2

      1

      3

      7

      7

      C4

      0.11

      0.2

      0.33

      1

      5

      5

      C5

      0.11

      0.14

      0.14

      0.2

      1

      0.33

      C6

      0.11

      0.14

      0.14

      0.2

      3

      1

      Sum

      1.67

      6.68

      13.61

      18.4

      32

      29.14

      TABLE 3 PAIRWISE COMPARISON MATRIX

      TABLE 4 SUMMARIES OF CRITERIA PRIORITIES

      C1

      C2

      C3

      C4

      C5

      C6

      Priority

      C1

      0.599

      0.749

      0.514

      0.489

      0.281

      0.309

      0.490

      C2

      0.120

      0.150

      0.367

      0.272

      0.219

      0.240

      0.228

      C3

      0.084

      0.030

      0.073

      0.163

      0.219

      0.240

      0.135

      C4

      0.066

      0.030

      0.024

      0.054

      0.156

      0.172

      0.084

      C5

      0.066

      0.021

      0.010

      0.011

      0.031

      0.011

      0.025

      C6

      0.066

      0.021

      0.010

      0.011

      0.094

      0.034

      0.039

      Now, Pair wise comparison matrices are obtained by comparing contractors with respect to each criterion (Table 5 to 10)

      TABLE 5 PAIR WISE COMPARISON W.R.T. C1

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      2

      3

      0.546

      0.571

      0.500

      0.539

      B

      1/2

      1

      2

      0.273

      0.286

      0.333

      0.297

      C

      1/3

      1/2

      1

      0.182

      0.143

      0.167

      0.164

      Sum

      1.83

      3.5

      6

      TABLE 6 PAIR WISE COMPARISON W.R.T. C2

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      5

      3

      0.652

      0.556

      0.693

      0.634

      B

      1/5

      1

      1/3

      0.13

      0.111

      0.077

      0.106

      C

      1/3

      3

      1

      0.217

      0.333

      0.231

      0.260

      Sum

      1.53

      9

      4.33

      TABLE 7 PAIR WISE COMPARISON W.R.T. C3

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      1

      1/2

      0.25

      0.25

      0.25

      0.25

      B

      1

      1

      1/2

      0.25

      0.25

      0.25

      0.25

      C

      2

      2

      1

      0.5

      0.5

      0.5

      0.5

      Sum

      4

      4

      2

      TABLE 8 PAIR WISE COMPARISON W.R.T. C4

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      1/3

      1/3

      0.143

      0.143

      0.143

      0.143

      B

      3

      1

      1

      0.429

      0.429

      0.429

      0.429

      C

      3

      1

      1

      0.429

      0.429

      0.429

      0.429

      Sum

      7

      2.33

      2.33

      TABLE 9 PAIR WISE COMPARISON W.R.T. C5

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      1

      1

      0.333

      0.333

      0.333

      0.333

      B

      1

      1

      1

      0.333

      0.333

      0.333

      0.333

      C

      1

      1

      1

      0.333

      0.333

      0.333

      0.333

      Sum

      3

      3

      3

      TABLE 10 PAIR WISE COMPARISON W.R.T. C6

      Criteria

      A

      B

      C

      A

      B

      C

      Priority

      A

      1

      3

      3

      0.6

      0.6

      0.6

      0.6

      B

      1/3

      1

      1

      0.2

      0.2

      0.2

      0.2

      C

      1/3

      1

      1

      0.2

      0.2

      0.2

      0.2

      Sum

      1.667

      5

      5

      Final ranking is obtained by multiplying priority of criteria and priority of contractors followed by addition to obtain the final scores and presented in Table 11

      TABLE 11 FINAL RANKING FOR CONTRACTORS

      Criteria

      C1

      C2

      C3

      C4

      C5

      C6

      Priority

      0.490

      0.228

      0.135

      0.084

      0.025

      0.039

      Rank

      A

      0.539

      0.634

      0.250

      0.143

      0.333

      0.600

      0.497

      B

      0.297

      0.106

      0.500

      0.429

      0.333

      0.200

      0.256

      C

      0.164

      0.260

      0.500

      0.429

      0.333

      0.200

      0.259

      0.259

      0.256

      Contractor's Score

      0.497

      0.497

      0.6

      0.4

      0.2

      0

      The Final scores obtained in Table 11 lead us to the conclusion that Contractor A has better final score than Contract C and B.

      A B C

      Contractor Score

      Fig. 3 Ranking of Bidders by AHP

    2. Using Fuzzy Group Decision making Method

      TABLE 12 LINGUISTIC VARIABLES OF THE IMPORTANCE WEIGHT

      Very low (VL)

      (0, 0, 0.1, 0.2)

      Low(L)

      (0.1,0.2,0.2,0.3)

      Medium low (ML)

      (0.2,0.3,0.4,0.5)

      Medium (M)

      (0.4,0.5,0.5,0.6)

      Medium high(MH)

      (0.5,0.6,0.7,0.8)

      High(H)

      (0.7,0.8,0.8,0.9)

      Very high(VH)

      (0.8,0.9,1,1)

      TABLE13 LINGUISTIC VARIABLES FOR THE RATINGS

      Very poor (VP)

      (0, 0, 1,2)

      Poor(P)

      (1,2,2,3)

      Medium poor (MP)

      (2,3,4,5)

      Fair(F)

      (4,5,5,6)

      Medium good(MG)

      (5,6,7,8)

      Good(G)

      (7,8,8,9)

      Very good(VG)

      (8,9,10,10)

      TABLE 14 THE IMPORTANCE WEIGHT OF THE LINGUISTIC CRITERIA AND ITS MEAN

      Parameters

      Weight of

      criteria

      Fuzzy value

      Bid Value

      M

      (0.4,0.5,0.5,0.6)

      Financial Stability

      M

      (0.4,0.5,0.5,0.6)

      Technical Capability

      H

      (0.7,0.8,0.8,0.9)

      Management Skill

      H

      (0.7,0.8,0.8,0.9)

      Reputation and

      Safety Records

      M

      (0.4,0.5,0.5,0.6)

      Quality of Work

      VH

      (0.8,0.9,1,1)

      Parameters

      A

      B

      C

      Bid Value

      G

      MG

      F

      Financial Stability

      VG

      MG

      G

      Technical Capability

      G

      G

      G

      Management Skill

      MG

      G

      G

      Reputation and Safety

      Records

      G

      G

      G

      Quality of Work

      VG

      MG

      G

      TABLE 15 THE RATINGS OF ATTRIBUTE PERFORMANCE FOR THREE TYPES OF BIDDERS

      `

      Bid Value

      Financial Stability

      Technical

      Capability

      Management Skill

      Reputation and Safety

      Records

      Quality

      A

      0.7,0.8,0.8,0.9

      0.8,0.9,1,1

      0.7,0.8,0.8,0.9

      0.5,0.6,0.7,0.8

      0.7,0.8,0.8,0.9

      0.8,0.9,1,1

      B

      0.5,0.6,0.7,0.8

      0.5,0.6,0.7,0.8

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.5,0.6,0.7,0.8

      C

      0.4,0.5,0.5,0.6

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      TABLE 16 NORMALIZING THE RATINGS OF ATTRIBUTE PERFORMANCE FOR THREE BIDDERS

      From Tables 12 to 16, we get Fuzzy weight matrix and fuzzy decision matrix respectively, 0.7,0.8,0.8,0.9 0.8,0.9,1,1 0.7,0.8,0.8,0.9 0.5,0.6,0.7,0.8 0.7,0.8,0.8,0.9 0.8,0.9,1,1

      = 0.5,0.6,0.7,0.8 0.5,0.6,0.7,0.8 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0. 0.5,0.6,0.7,0.8

      0.4,0.5,0.5,0.6 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9

      0.4,0.5,0.5,0.6

      0.4,0.5,0.5,0.6

      = 0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.4,0.5,0.5,0.6

      0.8,0.9,1,1

      Aggregate the fuzzy evaluations by ()= [ ] . [ ]t, i= 1,,m, j=1,,n where *denote composition operation of fuzzy numbers.

      A 0.7,0.8,0.8,0.9 0.8,0.9,1,1 0.7,0.8,0.8,0.9 0.5,0.6,0.7,0.8 0.7,0.8,0.8,0.9 0.8,0.9,1,1

      0.4,0.5,0.5,0.6 B = 0.5,0.6,0.7,0.8 0.5,0.6,0.7,0.8 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.5,0.6,0.7,0.8

      0.4,0.5,0.5,0.6

      C 0.4,0.5,0.5,0.6 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 0.7,0.8,0.8,0.9 * 0.7,0.8,0.8,0.9

      0.7,0.8,0.8,0.9

      0.4,0.5,0.5,0.6

      0.8,0.9,1,1

      A

      2.36

      3.18

      3.55

      4.21

      B

      =

      2.06

      2.82

      3.08

      3.92

      C

      2.26

      3.05

      3.13

      3.96

      = (2.36, 3.18, 3.55 And 4.21)

      = (2.06, 2.82, 3.08 And 3.92)

      = (2.26, 3.05, 3.13 And 3.96)

      Ranking aggregate fuzzy number (), i = A, B, C and determining the best alternatives

      1

      0

      0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

      Fig. 4 The defuzzification value of the Trapezoidal fuzzy number A, B, C by Fuzzy methodology

      Hence, we can defuzzify, , and as in the following:

      = (2.36 + 3.18 + 3.55 + 4.21) / 4 = 3.325

      = (2.06 + 2.82 + 3.08 + 3.92) / 4 = 2.970

      = (2.26 + 3.05 + 3.13 + 3.96) / 4 = 3.100

      Fig. 5 Ranking of Bidders by Fuzzy methodology

  5. RESULTS

    Table 17 FINAL RESULTS

    Methodology

    A

    B

    C

    AHP

    0.497

    0.256

    0.259

    FGDM

    3.325

    2.970

    3.100

    Therefore, as per above 2 methods, The Ranking of Bidders is, A> C > B

  6. CONCLUSION

    Analytic Hierarchy Process is an effective decision making technique based on multi-criteria decision making. AHP is a method successfully used as it incorporates all the attributes pertaining to contractor selection and then prioritizes each attribute resulting in easy judgment of best contractor. In this method important parameters regarding procurement procedure are considered & rating is given to the criterion according to the question, How important is one criterion compared to other criterion and ranking procedure to contractor carried out as per given scale. But, in some complex decision problems, it is difficult for the decision maker to compare between alternatives with crisp value, because of the ambiguity in human experience and knowledge. Fuzzy methodology used to tackle this type of problem. Consistency of the outcome regarding the selection of the contractor in the AHP checked in FGDM, the uncertainty involved in rating a contractor overcome using Fuzzy methodology.

    Finally, we can concluded that, the suitability of these

    methods depends on the input regarding various attributes of contractors and attributes of selection criteria obtained from the decision makers.

  7. REFERENCES

    1. Bojadziev G., Bojadziev M., (1995), Fuzzy Sets, Fuzzy Logic, Applications, World Scientific, Singapore.

    2. Chen C.T., (1998), A study of fuzzy group decision-making method, 6th National Conference on Fuzzy Theory and Its Applications.

    3. Chen S.J., Hwang C.L., (1992), Fuzzy Multiple Attribute Decision Making: Methods and Application, Springer, New York.

    4. Ching-Hsue Cheng (1996), Evaluating naval tactical missile systems by fuzzy AHP based on the grade value of membership function, European Journal of Operation Research 96, Page No. 343-350.

    5. Ching-Hsue Cheng, Yin Lin b (2002), Evaluating the best main battle tank using fuzzy decision theory with linguistic criteria evaluation, European Journal of Operational Research 142 Page No. 174186.

    6. Hatush, Zedan and Skitmore, Martin R. (1997), Criteria for Contractor Selection, Construction Management and Economics, 15(1), Page No. 19-38.

    7. James H. Paek, (1992) Yong W. Lee and Thomas R. Napier, Selection of Design/Build Proposal using Fuzzy-Logic System, Journal of Construction Engineering and Management, Vol.118, No.2, Page No.303-317.

    8. Jeffrey S. Russell, (1991) Contractor Failure: Analysis, Journal of Performance of Construction Facilities, Vol.5, No.3, Page No.163-180.

    9. Jeffrey S. Russell and Miroslaw J. Skibniewski, (1988) Decision Criteria in Contractor Prequalification, Journal of Construction Engineering and Management, Vol.4, No.2, Page No.148-164.

    10. Jose Ramon and San Cristobal, (2012) Contractor Selection Using Multicriteria Decision-Making Methods, Journal of Construction Engineering and Management, Vol.138, No.6, Page No.751-758.

    11. Kaur Prabjot, Verma Rakesh, Mahanti N. C., (2009), Selection of vendor using analytical hierarchy process based on fuzzy preference programming, Operational Research Society of India, 47(1), Page No. 1634.

    12. Kaufmann A., M.M. Gupta, (1988), Fuzzy Mathematical Models in Engineering and Management Science, North-Holland, Amsterdam.

    13. Lee E. S. & Li R. J. (1988), Comparision of fuzzy numbers based on the probability measure of fuzzy events Computer and Mathematics with Application, Vol. 15, No. 10, Page No. 887896.

    14. Mounir El Asmar, Wafik Lotfallah, Gary Whited and Awad S. Hanna, (2010) Quantitative Methods for Design-Build Team Selection, Journal of Construction Engineering and Management, Vol.136, No.8, Page No.904-912.

    15. Nguyen Van Uu (1985), Tender Evaluation by Fuzzy Sets, Journal of Construction Engineering and Management, Vol. 111, No. 3 Page No. 231-243.

    16. Randolph Thomas H. and Ralph D. Ellis Jr., (2007) Contractor Prebid Planning Principles, Journal of Construction Engineering and Management, Vol.133, No.8, Page No.542-552.

    17. Saaty Thomas L. (1990), How to make a decision : The Analytic Hierarchy Process, European Journal of Operational Research 48 Page No. 9-26.

    18. Singh D. and Robert L.K. Tiong, (2005) A Fuzzy Decision Framework for Contractor Selection, Journal of Construction Engineering and Management, Vol.131, No.1, Page No. 62-70.

    19. Waara F. and Brochner J., (2006) Price and Nonprice Criteria for Contractor Selection, Journal of Construction Engineering and Management, Vol.132, No.8, Page No.797-804.

    20. Yawei Li, Xiangtian Nie and Shouyu Chen, (2007) Fuzzy Approach to Prequlifying Construction Contractors, Journal of Construction Engineering and Management, Vol.133, No.1, Page No. 40-49.