- Open Access
- Total Downloads : 577
- Authors : Mrs. Rani Mate, Dr. G. A. Hinge
- Paper ID : IJERTV4IS060239
- Volume & Issue : Volume 04, Issue 06 (June 2015)
- DOI : http://dx.doi.org/10.17577/IJERTV4IS060239
- Published (First Online): 10-06-2015
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Delay Mitigation in the Construction Industry
Mrs. Rani M. Mate
Civil Engineering Department BSCOER, Narhe, Pune
Pune, India
Dr. G. A. Hinge
Civil Engineering Department BSCOER, Narhe, Pune
Pune, India
Abstract Project management is a process of planning, organizing, managing activities and resources to accomplish a defined objective within constraints on duration, resources or cost. Monitoring involves watching the progress of the project against time, resources and performance schedule during execution of the project. Whereas project controlling uses data from monitoring activities to bring actual to planned performance. As project become larger and complex, the ability to exchange information on timely basis is shrinking. The construction projects have become so vast and complex that the application of information technology has become inevitable. Companies started developing software for project management such as Primavera, Microsoft project, etc. This study involves monitoring and controlling the project using Primavera-P6. There is tremendous amount of information on project that is always changing. So there comes need of Primavera to overcome the failure due to lack of management.
The main objective of this paper is to identify the management tool that are practiced in the construction industry for mitigating delay. This paper comprises of three phases. Phase-I comprises of data collection, estimation, planning and scheduling. Data is gathered in form of responses from questionnaire survey and interviews with those involved in construction project. In second phase primavera tool is used. With usage of Primavera, comparison of planned and actual efforts are done which provides delay occurrence. Delay causes are found with analyzing delay time. Third phase includes study, analysis and mitigation of delay causes. Stakeholder management is done in accordance to causes of delay. Now once delay causes are found, it needs to be countered by providing mitigation plan so as to complete project on schedule or with minimal delay.
Keywords Primavera software; Delay causes; Delay mitigation
INTRODUCTION
Project management is a process of planning, organizing and managing activities and resources to accomplish a defined objective within constraints on duration, resources or cost. The purpose of project management is prediction and prevention, NOT recognition and reaction. It is very common to see project failing to achieve its mission within specified time and cost. The factors contributing to overrun are inadequate project formation, poor planning for implementation and lack project management during project execution but the main cause of failure can be attributed to cost estimation and management failure. Construction delays are the rule, not the exception. Most construction work is performed out-of-doors. Weather, alone, can play havoc with schedules. Then, there are change orders, site problems, labor
disputes, shipping delays, supply backlogs, subcontractor problems, and accidents.
Always have a contingency plan for delays. As project become larger and complex, the ability to exchange information on timely basis is shrinking. There is a tremendous amount of information on a project that is always changing. The traditional project management system cannot meet the demands of todays projects. The construction projects have become so vast and complex that the application of information technology has become inevitable. Companies started developing software for project management such as Primavera, Microsoft project, etc.
Objectives of work:-
-
To study causes of delay.
-
Develop comparative study of planned and actual duration of project.
-
Mitigation plan for the same
-
LITERATURE REVIEW
Pethe Sarang & Pramila Adavi published the paper in ASCE 2012 Project management concepts are no longer theoretical but have got converted to technology driven means.
Matthew J. Liberatore, Bruce Pollack-Johnson, and Colleen A. Smith. Published paper in ASCE 2001 Decision of using PM software depends on complexity of project. Construction professionals using more analytical techniques tends to choose the full featured software packages primavera over other packages while those who use fewer techniques to use Microsoft Project Plan MPP.
Andrew Fernans Tom, Sachin Paul Lecturer published paper in IJIRSET 2013. The main objective of this study was to understand the role of monitoring and control in the progress and timely completion of a construction project. This objective was achieved through revision of literatures and methodologies involved in monitoring and control. The case study proved to be a guideline in understanding the progress of construction work and also to identify the specific problems arising during the process. Results of this study show the drawbacks of the present project management system in construction project and the importance efficient planning, monitoring and controlling, as well as the need and effectiveness of project management software like Primavera P6 in a construction project.
H. Abdul-Rahman1; M.A.Berawi2; A.R.Berawi3; O. Mohamed4; M. Othman5; and I. A. Yahya6 published paper in ASCE 2006 This research purpose is to identify causes for project delays and suggest mitigation to overcome effects of problem. Data for study have been gathered in form of questionnaire survey & interview of those involved in construction management like project manager of company. Study results implies delay incidents occur mainly during the construction phase of a project and one or more parties usually contribute to delay. Paper emphasis on having capable construction manager as well as skilled labourers to enable the industry to develop at a faster rate either nationally or internationally.
Tarek Hegazy, M.ASCE1; and Wail Menesi, S.M.ASCE2 published paper in ASCE 2008 This research introduces enhancements to a computerized schedule analysis model so as to yield accurate and repeatable results. Theoretical base for this method is traditional window analysis which presents improvements to the daily window analysis method. The resultant modified daily window analysis considers the multiple baseline and resource allocation effects on daily analysis. The model uses a daily window size in order to consider all fluctuation in the critical path and uses a legible representation of progress information to accurately a portion delays and acceleration along project parties. This research is useful for repeatable analysis of construction project in order to enable corrective actions and claim analysis.
Desai Megha1, Dr Bhatt Rajiv2 published paper in IJETAE 2013 The paper presents the framework of causes of delays in residential construction projects. Total 59 causes were identified under 9 major groups. An approach is suggested to carry out ranking of these causes by two different techniques: Relative importance index and Importance index based on degree of severity and degree of frequency.
-
METHODOLOGY ADOPTED
The research methodology contains three phases. The first phase included a literature search from different journal papers, interviews, case study, estimation, planning and scheduling. The literature review was conducted through books, internet and international project management journals. Data is gathered in form of responses from questionnaire survey and interviews with those involved in construction project. For planning, estimation needs to be completed by taking residential building case study and estimating it folloed by planning and scheduling. In second phase primavera tool is used. With usage of Primavera, comparison of planned and actual efforts are done which provides delay occurrence. Delay causes are found with analyzing delay time. Delay causes are considered from literature and site experiences. As the outcome of this phase, causes of delays for residential construction project were identified. Third phase includes study, analysis and mitigation of delay causes. Stakeholder management is done in accordance to causes of delay. These causes are categorized in nine main groups as: Project related, Owner, Contractor related, Consultant related, Design-related,
Material related, Labor related, Equipment related and External factors depending on their nature and mode of occurrence. Framework of the causes are given in appendix I. Now once delay causes are found, it needs to be countered by providing mitigation plan so as to complete project on schedule or with minimal delay. Mitigation plan is given in appendix I.
-
PHASE I
The first phase includes a literature search from different journal papers, interviews, case study, estimation, planning and scheduling.
-
PHASE II
In second phase primavera tool is used. With usage of Primavera, comparison of planned and actual efforts are done which provides delay occurrence. Delay causes are found by analyzing delay time. Delay causes are considered from literature and site experiences. As the outcome of this phase, causes of delays for residential construction project have been identified.
-
Role of Computer Technology in Civil Engineering
The computer can play a useful and important role in the teaching and learning of civil engineering concepts and applications. Depending on the type of software used, the professor can design the course such that the computer can be used advantageously to increase the understanding of engineering concepts and to develop sound judgment in students. Since the development of faster and more affordable computers will be the trend, it is necessary that civil engineering schools should increase the awareness in students on the significant role computers play in education and in the industry.
-
Primavera
Project Management software (P6) is a powerful, interlinked software system designed to create and analyze the CPM schedules used in managing construction projects; which allows to link multiple schedules together. Primavera is the industry leading project and program management solution for projects of any size. Primavera helps to 1) Obtain early warning of project risks 2) Improve visibility into project performance. 3) Collaborate with the project team. 4) Reduction in manual efforts for planning. 5) Reduction in possibility of manual errors. 6) Effectively listing the dependent activities for next activity. 7) Effectively tracking of execution of activities. 8) Proposing solution to minimize the cost variance and schedule delay.
-
Delays in Project
Delay analysis is focus on a comparison of planned versus actual schedule performance. Delays give rise to disruption of work and loss of productivity, late completion of project, increased time related costs, and third party claims and termination of contract. It is important that general management keep track of project progress to reduce the possibility of delay occurrence or identify it at early stages.
-
Effects of Delay
Overtime: Suppose work is of 25 person days and it needs to be completed in 5 days so for its labor required would be 5 but labor arranged are only 4 then each labor would work extra for 2 hrs./day considering normal working hrs. Are 8 hrs. /day.
Over cost: while planning cost of cement is x rupees but during construction cost of cement increases by 10 % so this 10% increase in cement cost would increase overall cost of project.
Abandonment: We have planned for project but the required approvals from government authorities like environmental, non-agricultural, etc. have been rejected in such cases the project would be abandonment.
Litigation: If the land is in disputes then we have to clear land ownership in the legal manner.
Lawsuits: If the land is in disputes then we have to clear land ownership in the legal manner.
Negotiations: There are some demands of a labor union which management have to negotiate with them in such a manner that work should not impacted with issues such as strike.
Disputes: Disputes in between Owner and Consultancies like Contractors.
-
Monitoring
Construction monitoring is a service which provides the client with independent verification (to the extent of the consultant's engagement) that the works have been completed in accordance with specified requirements. Most construction projects are unique, but unlike manufactured products which are often thoroughly tested and evaluated during construction and prior to being brought into service, the completed project is rarely tested against all design requirements. Factors influencing the level of construction monitoring for a project are: 1) The size of the project 2) The importance of the project 3) The complexity of the construction works 4) The experience and demonstrated skill in quality management of the constructor
-
Case study analysis
From studying and analyzing the project Actual vs. Planned duration/schedule in Primavera, it was found that there is variation in project actual duration with respect to project planned duration. Variation in duration/schedule can be seen in Fig. A given below. Reasons of such delay are found by Questionnaire survey with site Engineers and from journal papers. Causes of delay are as mentioned with their groups in terms of project, owner, contractor, consultant, design, material, equipment, labor and external in Appendix I.
-
Figures and Tables
Fig A – Snapshot of primavera for showing the project is behind schedule
-
-
PHASE III
Third phase includes stakeholder management is calculated in accordance to causes of delay. These causes are categorized in nine main groups as: Project related, Owner, Contractor related, Consultant related, Design-related, Material related, Labor related and External factors depending on their nature and mode of occurrence. Framework of the causes are given in annexure I. Now once delay causes are found, it needs to be countered by providing mitigation plan so as to complete project on schedule or with minimal delay. Mitigation plan is given in annexure I.
A. Mitigation plan for Delay
An analysis is needed to identify the impact of delay on time and cost followed by taking the appropriate action to mitigate delay and minimize the cost required. Mitigation efforts are necessary to minimize losses and this can be achieved by many procedures such as protection of uncompleted work, timely and reasonable reprocurement, and timely changing or cancellation of purchase orders. It is important to predict and identify the problems in the early stages of construction and diagnose the cause to and implement the most appropriate and economical solutions. This factor increases the probability of delay occurrences in construction projects and makes effective management important to reduce the diversions from the original program.
-
CONCLUSION
Delays are known to cause losses to the developers. Identifying projects life cycles and when delay usually occurs will help to identify the cause of a delay in a construction project. With help of primavera tool the delay in schedule can be found by comparing planned schedule and actual schedule of project. Analyzing delay in schedule it was observed that major cause of delay was decision making by management for number of building floors. All parties involved in the project also agreed that delay occurs mostly during the construction phase. From questionnaire survey it was found that there are many other causes of delay during construction phse. Therefore, in order to solve these several causes of delay, the mitigation plan was suggested.
Sr.
No.
Causes of delay
Group
Mitigation plan
implemented by contractor
work progress.
16
Delay in site mobilization
Contractor
Consultant should monitor site mobilization and ensure that it should be within time
limit.
17
Delay in performing inspection and testing by
consultant
Consultant
Consultant should timely inspect the site
18
Delay in approving major changes in the scope of work by consultant
Consultant
Scope of Work should be finalized by taking meetings so as to avoid any delay in approval process. Work schedule should be planned
in accordance to that.
19
Inflexibility (rigidity) of consultant
Consultant
Before project execution, owner should ensure that consultant is aware of his responsibilities & expectations set by owner. A signed legal agreement should be in place for the
same.
20
Late in reviewing and approving design documents by consultant
Consultant
Design document schedule must be strictly adhered by consultant and design engineer. In case of any delay made by consultant and design engineer, owner should schedule meeting and make the project expectations
clear to them.
21
Conflicts between consultant and design engineer
Consultant
Design documents walkthrough should be arranged prior to project execution so as to have
common understanding of project design.
22
Mistakes and
discrepancies in design documents
Design
Design documents should be reviewed by consultant.
23
Delays in producing design documents
Design
Design document schedule must be strictly adhered by consultant and design engineer. In case of any delay made by consultant and design engineer, owner should schedule meeting and make the project expectations
clear to them.
24
Unclear and inadequate details in drawings
Design
Drawing should be clear and self-explanatory. Drawing
should be reviewed and approved by consultant.
25
Complexity of project design
Design
Provide additional details and try to reduce complexity of design. Consultant should have walkthrough from Design Engineers so as to understand the design and reduce complexity in it by
redesigning.
26
Insufficient data collection and survey before
design
Design
Consultant should provide complete data needed for designing to Design
Engineers.
27
Misunderstanding of owners
requirements by design engineer
Design
Requirement gathering should be properly done by
having repeated meetings and reviews with Owner/Client.
TABLE I. APPENDIX I
Sr.
No.
Causes of delay
Group
Mitigation plan
1
Legal disputes b/w various parts
Project
Amicable solution should be provided between parts.
Appoint arbitrator to take final decision.
2
Ineffective delay penalties
Project
Monetary penalties should be effective on consultant/contractor for any delay in project and it should
be in signed agreement.
3
Delay in progress payments by
owner
Owner
It should be compensated by making advance payment to
vendors/contractors.
4
Delay to furnish and deliver the site to the contractor by the owner
Owner
Motivate contractor by paying bonus so as to complete work as per rescheduled activities. Labors can be paid extra for extra work done to complete work
on schedule.
5
Change orders by owner during construction
Owner
Owner should stick upon their orders. If orders needs to be changed then owner should plan it ahead so as not
to impact on schedule.
6
Late in revising and approving design documents
by owner
Owner
Prior execution of project, owner must have finalized drawings and documents.
7
Delay in approving sample materials
Owner
Prior to execution of project, material sample should be finalized as per its availability and need of
project.
8
Poor communication and coordination by owner and
other parties
Owner
Weekly review meetings should followed religiously by owner to track project progress.
9
Slowness in
decision making process by owner
Owner
Decision process should be simpler and faster.
10
Rework due to errors during construction
Contractor
Work should progress as per plan. Engineer/Architect should monitor ongoing work so as to avoid any errors during execution of work.
Timely monitoring work will reduce the need of rework.
11
Conflicts b/w contractor and other parties
(consultant and owner)
Contractor
Owner should conduct weekly/monthly meetings so that alarming issues between
contractors and other parties can be addressed.
12
Poor site management and
supervision by contractor
Contractor
Qualified and experienced staff should be hired for site management and supervision.
13
Poor communication and coordination by contractor with other parties.
Contractor
Contractor should co-ordinate with subcontractor and other parties on weekly basis.
Contractors should publish
work schedule on regular basis.
14
Ineffective planning and scheduling of project by
contractor
Contractor
Planning/Scheduling should be practical and achievable. Planning and schedule should be reviewed by experienced
staff and owner.
15
Improper construction
methods
Contractor
Consultant should provide timely guidance on work
methodology to accelerate the
Sr.
No.
Causes of delay
Group
Mitigation plan
28
Changes in material types and specifications during construction
Materials
It's part and parcel of project but can be avoided by taking
fast decisions and having backup plan. Backup plan (like vendors list) would avoid any delay in delivery of
material.
29
Delay in material delivery
Materials
Delivery schedule should be adhered with proper planning like having material in place before execution and making advance payments for booking material in case of scarcity. Backup plan like material vendors list should
be handy.
30
Damage of sorted material while they are needed
urgently
Materials
Sufficient material should be in store, considering the material damage.
31
Delay in manufacturing special building
materials
Materials
Material specification should be provided early.
32
Late procurement of materials
Materials
Material should be procured as per the need of project and availability in market. If there is scarcity of material in market then it should be
booked in advance by making partial payments.
33
Late in selection of finishing materials due to availability of many types in market
Materials
Consultant should technically evaluate the material by having pros and cons. Owner and consultant should then take decision on material as per project need, its cost and technically feasibility. This process should be completed
before start of project execution.
34
Shortage of equipment
Equipment
Equipment's should be made
available by contractor as per schedule and project status.
35
Low level of
equipment- operators skill
Equipment
Skilled labors should be hired
by contractor for usage of equipment's
36
Low productivity and efficiency of equipment
Equipment
Equipment selection should be done as per its productivity and need of project. Skilled labors should
be hired for using equipment.
37
Shortage of labors
Labor
Equipment's should be used to maximum so as to reduce
dependency on labors.
38
Unqualified workforce
Labor
Skilled labors should be hired for work. Trainings should be
provided to unskilled labors.
39
Low productivity level of labors
Labor
Contractor should sort out difficulties faced by labors during work and motivate them by providing incentives
for good work.
40
Personal conflicts among labors
Labor
Contractor should handle conflicts by having proper
communication.
41
Delay in obtaining permits from municipality
External
Documents should be complete. Process of approvals should be started
early
42
Rain effect on construction
External
Activities should be planned and prioritized by considering
Sr.
No.
Causes of delay
Group
Mitigation plan
activities
the impact of weather conditions due to seasonal
change.
43
Unavailability of utilities in site (such as, water, electricity,
telephone, etc.)
External
Basic utilities on site should be considered during planning and arranged before start of project execution.
44
Effect of social
and cultural factors
External
While planning consideration
of labors social & cultural factors should be done.
45
Accident during construction
External
Safety precautions should be strictly followed on site. First aid kit should be available on site. Labors insurance should
be done.
46
Differing site (ground) conditions
External
Soil investigation should be properly done prior to start of planning. This also helps
structural Engineer as well.
47
Changes in government regulations and
laws
External
Consultant should timely check the changes in government regulations/laws
and act in accordance to that.
48
Delay in performing final inspection and certification by a
third party
External
Inspection should be done on time by third party and certificate should be provided.
ACKNOWLEDGMENT
The satisfaction that accompanies the successful completion of any task would be incomplete without the mention of people whose ceaseless co-operation made it possible, whose constant guidance and encouragement crown all efforts with success.
I am grateful to my Project guide under Prof. Dr. G. A. Hinge and external guide Prof. Baliram Ade sir for the guidance, inspiration and constructive suggestions that are helpful for me in the implementation of this Paper
REFERENCES
-
Issaka Ndekugri1; Nuhu Braimap; and Rod Gameson3 (2008) Delay Analysis within Construction Contracting Organizations Journal Construction eng. Manage. ASCE 134: (692-700).
-
Abdulaziz A. Bubshait1; Michael J. Cunningham2 (1998) Comparison of Delay Analysis Methodologies Journal Construction eng. Manage. ASCE 124: (315-322)
-
Tarek Hegazy, M.ASCE1; and Wail Menesi, S.M.ASCE2 Delay Analysis under Multiple Baseline Updates Journal of Construction engg. & Manage. ASCE August (2008).134 (575-582)
-
H.Abdul-Rahman1; M.A.Berawi2; A.R.Berawi3; O. Mohamed4; M. Othman5; and I. A. Yahya6 Delay Mitigation in the Malaysian Construction Industry Journal of Construction engg. & Manage. ASCE February (2006).132 (125-133)
-
Andrew Fernans Tom1; Sachin Paul2 (2013) Project Monitoring and control using Primavera IJIRSET VOL. 2 ISSUE 3 (762-771)
-
Miss A. A. LAKADE; Prof. A. K. Gupta; Prof. D. B. Desai (2013) A Project Management Approach Using Erp and Primavera in Construction Industry IOSR Journal of Mechanical and Civil engg. ISSN: 2278-1684, PP: (21-24)
-
Desai Megha1, Dr Bhatt Rajiv2 (2013) A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context IJETAE (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 3, Issue 3 (396-404)
-
E. William East I and Simon Kim (1993) Standardizing scheduling data exchange J. Constr. Eng. Manage. ASCE (119:215)-22
-
-