Planning a Small Scale Industry for Automatic Sliding Doors Manufacturing
1D. I. G. Chomo
Department of Mechanical Engineering Plateau State Polytechnic Barkin Ladi, Jos, Nigeria
line 3-City, Country
2 D. S. Yawas 3 S. Y Aku Department of Mechanical Engineering
Ahmadu Bello University, Zaria Nigeria
Abstract Automatic sliding doors ease movements through buildings and gating systems and though highly patronized and marketed in Nigeria it suffers lack of an indigenous manufacturing company. Plant layout which is a perquisite to establishing a manufacturing company is hereby designed. The process through which the door is manufactured is analysed, departments are designed from the type of machines used and materials processed, the number of movements of materials through the designed departments is analysed, the number of movements is used to design all the possible layouts, the layout with no backtracking, low cross movements and low cost is then selected. To help conserve foreign exchange and the attainment of national self reliance, the establishment of a small scale industry to manufacture automatic sliding doors is highly recommended
Keywords Cross movement, Backtracking, Material flow, Cost matrix , Automatic
1.0 INTRODUCTION
As the Nigerian economy expands, it is pertinent to diversify it by designing industries that not only provide employment at the micro level, but help propel other sectors of the economy. It is observed that, there is no known automatic door manufacturing company in Nigeria. The aim of this work is to design a plant layout for a small scale industry to manufacture the door. This will help entrepreneurs to, not only take interest in establishing companies to address the issue of automatic sliding door manufacturing in Nigeria, but make the establishment of the company easier. The design takes into consideration components that are manufactured in this country such as products from aluminium foundries, sheet metal manufacturing companies, etc. This will make the product cost effective. Expectedly, the successful outcome of this work will help conserve foreign exchange by reducing importation of the product, and help the attainment of national objectives of self reliance.
your paper.
2.0 PLANT LAYOUT
Kumar [1], states that a small business requires a smaller area or space and can be located in any kind of building as long as the space is available and it is convenient. He went on to add that plant layout for small scale business is closely linked with the factory building and built up area. He also states that plant layouts are mainly of four types: product or line layout, process or functional layout, fixed position or location
layout, and combined or group layout. The most commonly used layouts are the product and process layout. A comparison between the two types of layouts tabled by Yawas [2] is given in table 1 below.
Table1: Comparison between product layout and process layout
Product layout |
Process layout |
||
i ii iii |
Employed when there is a continuous production of items. Equipment of special design are used Will be involved in producing relatively large quantities of each product. |
I ii Iii |
Employed when there is an intermittent production of items General purpose equipment are used Will be involved in producing relatively small quantities of each product |
Source: Yawas [2].
-
Materials and Methods
-
Layout Design Considerations
Small business owners need to consider many operational factors when building or renovating a facility for maximum layout effectiveness. These criteria include the following:
-
Ease of future expansion or change.
Facilities should be designed so that they can be easily expanded or adjusted to meet changing production needs. "Although redesigning a facility is a major, expensive undertaking not to be done lightly, there is always the possibility that a redesign will be necessary," [3].
-
Flow of movement.
The facility design should reflect recognition of the importance of smooth process flow. In the case of factory facilities, J.K. Lasser Institute [4] state that "ideally, the plan will show the raw materials entering your plant at one end and the finished product emerging at the other. The flow need not be a straight line. Parallel flows, U-shaped patterns, or even a zig-zag that ends up with the finished product back at the shipping and receiving bays can be functional. However,
backtracking is to be avoided in whatever pattern is chosen. When parts and materials move against or across the overall flow, personnel and paperwork become confused, parts become lost, and the attainment of coordination becomes complicated."
-
Materials handling
Small business owners should make certain that the facility layout makes it possible to handle materials (products, equipment, containers, etc.) in an orderly, efficient and preferably simple manner.
-
Output needs
The facility should be laid out in a way that is conducive to helping the business meet its production needs [5].
-
Space utilization
This aspect of facility design includes everything from making sure that traffic lanes are wide enough to making certain that inventory storage warehouses or rooms utilize as much vertical space as possible [5].
-
Shipping and receiving
The J.K. Lasser Institute [4] counselled small business owners to leave ample room for this aspect of operations.
-
Ease of communication and support
Facilities should be laid out so that communication within various areas of the business and interactions with vendors and customers can be done in an easy and effective manner [5].
-
Impact on employee morale and job satisfaction Since countless studies have indicated that employee morale has a major impact on productivity, Weiss and Gershon [3] counsel owners and managers to heed this factor.
-
Promotional value
The small business owner may want to make sure that the facility layout is an attractive one that further burnishes the company's reputation.
-
Safety
The facility layout should enable the business to effectively operate in accordance with Occupational Safety and Health Association guidelines and other legal restrictions [5]
-
-
Layout Design Methodology
The following culled from Sharma [6] are the major stages in planning a plant layout:
-
Analyse Manufacturing Requirements.
The basic-data needed to design a layout include: a complete list of parts to be manufactured and assembled; their drawings; operation sequence and method of manufacture of each part and estimated process time for each operation.
-
Determination of space Requirements
The space for production departments is determined by generating the following data. (i) Activities to be carried out in each department. (ii) What operations to be performed on which machines and in which department. (iii) Standard times for each individual operation are calculated and listed in operation planning sheets. The required number of machines of each type is calculated. The space needed for each machine and the requirements of other equipment needed are determined. Space for Utilities, Production Related-Activities, Administration Offices and Personal Servces is finally determined.
-
Choice of Plant Layout
A choice has to be between a product or line layout, process or functional layout, group technology or combined layout and fixed position or location layout.
-
Determination of Flow of Materials.
The smooth flow of work into, through and out of the factory depends, to a large extent, on the type of production and on the success of the layout chosen. In flow production (product layout), the work movement will be predetermined with the equipment arranged in operation sequence and the components and subassemblies flowing into the main assembly line at the correct position. For process layout, it is possible to establish only a general direction of work movement, due to the difference in operation sequence of different parts of the product. A better way is to take the help of Travel Charts.
-
Synthesis of Alternate Department Layout
By analysing travel charts for different arrangement of departments, sketches or drawings are made of the possible relative arrangement of the various departments. In this manner, we get a number of rough layouts of departments considering the shape and size of each department.
-
Planning Stores and Service Areas.
The size and position of the various store areas are determined. Normally raw materials stores are located at one end of the company and finished products warehoused at the other, with a component store between the manufacturing and assembly areas.
-
Choice of the Best Overall Layout.
To select the best layout, Materials Handling Costs of the layouts is compared. The alternative which results in the minimum total materials handling cost is selected.
-
Detailed Factory Layout Planning.
-
The next step is to plan the detailed layout of each department. This is done by considering each department separately and determining the best arrangement for machines, equipment and facilities within the department.
-
LAYOUT DEVELOPMENT
-
Operations Process Chart
The manufacturing, assembly and installation procedure is summarized in an operation process chart (figure 1). The total
No of door units manu factured /day =
= 8 units/day
main components are sixteen.
In this chart, the materials entering are indicated by horizontal lines and the processing of these materials is shown vertically. Only two symbols arc used to prepare this chart: for operation and for inspection.
4.4 Automatic Sliding Door Part List and Machine
Requirement
To manufacture a product a comprehensive part list is needed. The parts that make up the automatic sliding door are enumerated in Appendix A. The Appendix also provide information on the raw materials for manufacturing the parts, the number of components in an assembled door and the total
Operator
Rail
Door
Door
Double Double
Bottom Top
number needed to produce eight components which is the
Rollers Bracket Hanger Hook Pulleys Cover Gauge Head
frame Jamb Track Interlock Lockstyle Rail
Rail Glass
daily output of the company.
Turn
Drill
Drill Drill Drill
Cut
Turn
Cutt
Cut Cut Cut
Cut Cut Cut Cut Cut Cut Cut
The machine required for the plant and their
Bore
Press Fit Bearings
Cut
Bend
Cut
Bend
Cut
Bend
Drill Bore
Drill
Bend
Bend
Drill Weld
Bend Drill
Weld
Bend
Drill
Drill
Drill
Miillll
Drill Drill
Drill Drill
capacities are summarized in table 2 (Appendix A). The table also shows the calculated floor space occupied by each
Press Fit
Bearings
Assembly Inspection
Inspection Inspection
Assembly
Assembly
Inspection
Assembly
Inspection
machine.
Inspection
Figure 1 Operations process chart for automatic sliding door
4.2 Number of Machines Required.
Assembly
Inspection
Assembly
Inspection
4.5 Material Flow in Plant
Departments are developed from the manufacturing activities taking place on the product from the raw materials required to the finished product. The departments developed are: stores, machining, sheet metal fabrication, aluminium sections fabrication mechanism assembly and final assembly.
The movements from stores to the various production
The number of machines required can be calculated from the time taken for a particular operation, number of components to be produced per day and the total working time per day [7]. Machine requirement is calculated using equation 3 provided by Harold, Amrine and Hulley [7].
Number of machines required =
…………………………………………………………….. 1
From the calculation, the machines required are: power saw, 1; lathe, 2; hydraulic press, 1; drilling machine, 1; welding
machine, 1; guillotine, 2; bending machine, 1; aluminium milling machine, 1; aluminium cutting machine, 1; and aluminium punching machine, 1. This makes a total of 12 machines.
4.3 Daily Door Units Manufactured.
From proportional principle, the number of door units to be manufactured /day
= …………………… 2
Critical time is the longest time spent on any one of the machines in the plant. From table 2 below the longest time is spent on power saw i.e. 60 minutes.
Critical time = 60 min Working time per day(8 hours day)
= 480 min/day
departments and the movements from one production department to the other are developed and the movements summarised in the travel chart of figure 2 below.
Figure 2: Material flow travel chart
-
Layout Development
The factory floor layout is designed using the travel chart of figure 2. The cost of movement is calculated from the product of the number of movements and the cost per movement. To get the best floor arrangement, the departments are arranged so that the cost of movements is a minimum. Since the total departments designed are six, there are then 6! or 720 ways to arrange them
The cost matrices calculate the cost implication of using the layouts. The best layout must have no backtracking, must have very low cross movements and should have low cost in that order.
-
Work Flow Diagram
The work flow diagram according to Sharma [6] is the plan view of the work place under study to a certain scale. A line diagram indicates the path-followed by the object under study. In the case of work/material movement, it represents sequence of operations. A work flow diagram is developed from the selected layout and shown in figure 3 below.
Figure 3: Work-flow diagram of manufacturing plant
-
Company Layout
The final layout of the small scale company, as shown in figure 4, is located on a 30m x 45m land (i.e. 3 plots). There is enough space for an administration block in front of the company and the production plant at the rear as suggested by Sharma [6].
Figure 5:Store
-
Planning Machine Tools Department
This department has power saw, lathe, and hydraulc press installed. Using equation 3 one power saw is required to manufacture eight sliding doors. Provision is made for four lathes as indicated figure 6 below. The six machines are arranged close to the wall to provide access to power and give enough room close to the gangway for materials.
Securi Post
Commercial
Water Supply
ty
PARKING LOT
Cafetaria Juniour
Admin
Offices
Kitchen
SHEET METAL FABRICAT
MACHINE SHOP
ION
Reception
General Manager
Secreta
STORES
Cafetaria Senior
ry Finance
Figure 6: Machining Department
Finished Products Store
Quality Control
-
Planning Sheet Metal Fabrication Department
This department is made up of drilling machine, welding machine, bending machine and guillotine. This shop floor is arranged so that the welding machine is well screened and
GANGWAY
MECHANISM ASSEMBLY
FINAL ASSEMBLY
Office
ALUMINIUM SECTIONS
FABRICATION
Toilet
Locker Room
MAINTENANCE DEPARTMENT
Office |
Service Pit |
Service Pit |
Service Pit |
Service Pit |
Generator
located between walls to shield off harmful rays. Provision for three guillotines, one drilling machine and one bending machine is provided. The machines are so located that
Figure 4: Layout Plan of a Small Scale Company
4.9 Planning Stores
The plan view of a store room is shown in Figure 5 indicating various spaces required. The various spaces, on which store keeping operations take place, as suggested by Kanna [9], are Incoming material receiving gate, Place for dumping raw material, Place for sorting and checking of raw materials, Place for raw material inspection, Place for temporarily storing the materials before putting them on racks, etc Proper place for storing each type of material, Main aisles, Side aisles, Service window, Boxes containing materials to be issued, and Counters for keeping materials, to be issued.
enough room is provided for finished work and inventory as
shown in Figure 7
-
Planning Aluminium Sections Fabrication Department
This department has the Aluminium Milling Machine, Aluminium Cutting Machine, and Aluminium Punching Machine. The aluminium sections fabricated are long (about three meters long), therefore, enough space is allocated to handle them. Room is also provided for movement to the assembly departments without re-entering the gangway. Fabrications of aluminium sections start with cutting, punching and then milling, therefore, the machines are arranged in that order as shown in Figure 7.
-
Planning Assembly Departments
Since both mechanisms assembly and final assembly have similar operations and procedure, merging them offer mutual advantage. The first is the use of long assembly tables which offers the opportunity of having more assembly on the assembly table. One technician can assemble more than one assembly concurrently and also the ease of supply of similar components to each station. The second advantage of merging the two departments is the sharing of tools, work rack and space. The third advantage is the great reduction in cost. The reduction in cost is achieved is this case about by removing movement 4 6. Movement 1 5 can be replaced by movement 1 6, the double movement being reduced to a single movement. The layout is shown in figure 8.
The saving in cost is 4000.00 + 5500.00 = 9500.00 Cost of using layout 4 is now
98600.00 – 9500.00 = 89100.00 (Justifying rejection of matrix 3 and 8. Also see table 4)
Figure 8: Assembly Departments.
5.0 CONCLUSION AND RECOMMENDATION
A small scale industry planned for the manufacture of automatic sliding door was successfully designed. The design took details of layout needed for the complete manufacturing of the door. A process chart, a travel chart and a work flow diagram was designed. Design was also made of each production department. It is recommended that:
-
A multiproduct layout to manufacture automatic sliding door and other products should be an area in further research.
-
Research into devising the number of movements for different categories of standard engineering materials and if possible, values tabulated.
-
Write software to design and choose the best layout from a given set of data prompted and fed into the software.
REFERENCES
-
Kumar, A. (2011). Plant location and layout. Retrieved October, 30 2012 from docsfile.com/pdf
-
Yawas, D.S. (2001). Design of an automatic tyre remover and planning of a small scale industry for its manufacture. Unpublished MSc thesis. Ahmadu Bello University. Zaria,
Nigeria
-
Weiss, H. J., and M. E. Gershon (1989). Production and Operations Management. Boston: Allyn and Bacon
-
J. K. Lasser institute, (1994). How to Run a Small Business. (7th ed). New York: McGraw-Hill.
-
Gale Encyclopedia of Small Business (2011). Retrieved from http:///www.answeres.com/library/small business Encyclopedia
-
Sharma, P. C. (2005); A textbook of production engineering.
New Delhi: S. Chand & Company Ltd
-
Harold, T., Amrine, R.J.A., and Hulley,V.S. (1985). Manufacturing organization and management (Eastern economy edition). New Delhi: Jay Print Pack Private Ltd. Prentice Hall.
-
Ikpe, L. (1999). A guide to Small Business Investments. Lagos: Impressed Publishers.
-
Osoba, A. M. (1987). Small scale enterprises in the developing process. Ibadan: Niser/Rosprint Industrial Press
Appendix A
Table 2:Machine Requirement Summary and Manufacturing Area Space Requirement.
Machine no |
Machine name |
No of machines |
Time spent |
Floor space By Machine (m2) |
Floor space by department (m2) |
|
Per machine |
Total |
|||||
1 |
Power saw |
1 |
60 |
1 |
1 |
14 |
2 |
Lathe |
2 |
97 (48.5) |
6 |
12 |
|
3 |
Hydraulic press |
1 |
14 |
1 |
1 |
|
4 |
Drilling machine |
1 |
18 |
5 |
5 |
10 |
5 |
Welding machine |
1 |
45 |
1 |
1 |
|
6 |
Guillotine |
2 |
65 (32.5) |
1 |
2 |
|
7 |
Bending machine |
1 |
30 |
2 |
2 |
|
8 |
Milling machine |
1 |
9 |
5 |
5 |
15 |
9 |
Cutting machine |
1 |
12 |
5 |
5 |
|
10 |
Punching machine |
1 |
13 |
5 |
5 |