Cost Comparison and Parametrical Investigation of the R/C Shear Wall Core of a Tall Building
Theodoros Chrysanidis, Ioannis Tegos
Department of Civil Engineering Aristotle University of Thessaloniki Thessaloniki, Greece
Vassilis Panoskaltsis Department of Civil Engineering Democritus University of Thrace Xanthi, Greece
AbstractThis work analyzes a tall building using two different design methods. One is the preliminary design and the other is the final design. The structural system used for supporting the building is a widely used worldwide system of the type of a brace shear wall core system. The preliminary analysis takes place using hand calculations while the final analysis takes place using computer software suitable for static and dynamic analysis and design. After analysis and design have taken place for both methods (preliminary and detailed method), the calculation of the cost for the reinforced concrete part of the structural system takes place. The reinforced concrete part has to do basically with the shear wall core placed at the center of the tall building in question. A parametrical comparison of the cost of the reinforced concrete part of the structural system leads to useful conclusions.
Keywordsparametrical; cost; comparison; tall; reinforced concrete
-
INTRODUCTION
Most of the flat buildings constructed around the world are buildings which have an average height of 4-5 storeys. However, there are special occasions that really tall buildings need to be constructed, e.g. in the case of office buildings for multinational companies, multi-storey flat buildings, etc.. In these cases, a typical structural system which is widely used along the world is the type of a braced shear wall core system. This system is chosen by many consultant engineers because of the great advantages which possesses. One of the most important advantages of this kind of system is its inherent ability to resist horizontal loads due to seismic action or wind pressure loads. This inherent ability of the structural system in question is owed to the fact that this system has increased stiffness and rigidity compared to other typical systems like outrigger-megacolumn system. The high level of stiffness and rigidity leading to an almost excellent behavior against lateral forces is owed basically to the placement of a shear wall core usually at the center of such a structural system. Reinforced concrete shear walls and shear wall cores are well-known for their aforementioned abilities and their large capacities against both horizontal and vertical loads [1-14]. Preliminary design is very useful in these cases because it can quickly estimate a first number for the cost of such a system. Final and detailed design gives a more accurate approach to the final construction cost of the shear wall core but it requires more analysis and design time.
The work herein analyzes the tall building in question for
material of this core is reinforced concrete, the construction cost calculation takes place for the reinforced concrete material. This calculation has basically to do for the concrete part which is more expensive compared to the reinforcement bars, not essentially because of the net prices of these two materials but because of the quantities used in the construction of the central core. Needless to say, that the quantity used for the concrete is much higher than the steel reinforcement bars themselves. Finally, a comparison for the construction cost of the shear wall for both design methods takes place. It becomes obvious from the present research that the quantity of concrete is one crucial cost parameter influencing the total building construction cost. Useful conclusions derive given in the final part of this work.
-
GENERAL CHARACTERISTICS OF THE STRUCTURAL SYSTEM
-
Specifications
General specifications of the building in question are the following:
-
200 m Height 220 m
Volume 400,000 m3
-
Increased storey height only for the ground floor
-
Equal storey height for the rest of the floors
-
-
Elevation Geometrical Characteristics
Two more specifications are chosen for the storey height:
-
Increased ground floor height
-
Equal typical floor height
Thus, the chosen storey heights are:
-
6m (Ground floor)
-
4.45m (Typical floor)
Thus, the total building height is:
Building height = 6 + 48×4.45 = 219.60 m
-
-
Plan Geometrical Characteristics
The building area is:
both design methods; preliminary and final method.
Volume 400, 000m3
Afterwards, it estimates the final construction cost for the main member of this type of system, which is the central shear wall core. As it is obvious, because of the fact that the construction
Volume Height Area
Area 1821 m2
219.6 Area 400000
A plan area of 42×42 m is chosen:
A = 42×42 = 1764 m2 1821 m2 OK
-
Dimensions for the Shear Wall Core
The plan dimensions of the central shear wall core are chosen in such way in order to occupy 20% of the total plan area of the building. Thus, the plan dimensions of the shear wall core are:
Acore = 18×18 m = 324 m2 20%×A = 0.20(4242) = 352.8
m2
-
-
DESCRIPTION OF THE BRACED SHEAR WALL CORE SYSTEM
-
General
The braced shear wall core system is constituted basically by: (a) The shear wall core at its center, (b) The columns at the perimeter and (c) The beams (primary or secondary). The materials for its type of member are given in Table 1.
TABLE I. IIITYPE AND MATERIAL OF STRUCTURAL SYSTEMS MEMBERS
TYPE AND MATERIALS OF STRUCTURAL SYSTEM MEMBERS
Shear wall core
Columns
Beams
Type
Reinforced concrete
Composite
Composite
Material
High-strength concrete
(C90/105)
Normal weight concrete
(C50/60)
Lightweight concrete
(C40/50)
-
Load path
As it has been previously stated, the braced shear wall core system is based mainly on the shear wall core to carry the horizontal loads due to wind or seismic actions. The contribution of other members, like the perimetrical columns, to the resistance of the lateral loads is minimal. Vertical loads are carried typically by the composite beams (primary or secondary) and brought down to the foundation and eventually to the ground through the composite columns and the shear wall core.
-
-
STRUCTURAL SYSTEM ANALYSIS AND DESIGN
A. General
Preliminary design is done using hand calculations [15]. Final design of the structural system takes place using personal computer static and dynamic analysis software (SAP 2000). Eurocodes [16-20] and other codes [21-22] are used for the design of the building.
Fig. 1. 3D Model of the building. Fig. 2. Side view of the building.
-
COST CALCULATION AND COMPARISON
It has to be noted the fact that cost calculations are given in terms of weight. This is done because any price given or used would be definitely indicative. It is well-known that prices change from place to place depending on the time of construction. Weights are something objective world-wide and
-
Concrete Construction Cost ofShear Wall Core
-
Model
The three dimensional model of the building used for the detailed design is shown in Figures 1 and 2.
they definitely do not change based on place or time. Table 2 shows the construction cost calculation which, as it has been previously stated and for the reasons given, it takes place for the concrete material of the shear wall core. Cost comparisons between the two design methods (preliminary and detailed) are given in the same Table. Section members have resulted from the design of the building either preliminary or final.
TABLE II. CONCRETE VCOST OF SHEAR WALL CORE
CONCRETE COST CALCULATION OF SHEAR WALL
Design type
Type
Volume (m3)
Preliminary
High-strength concrete C90/105
10046.70
Final
High-strength concrete C90/105
7434.96
Thus, the difference of the shear wall concrete cost for the two design methods (preliminary and final) is:
-
As far as the concrete cost of the shear wall is concerned, preliminary results overestimate it.
Difference= WFinal -WPreliminary =
WFinal
Difference=-35.13%
7434.96-10046.70
7434.96
-
Nevertheless, the usefulness of preliminary design remains in terms of a quick estimation of cost or member sections without the need for a time-consuming modelization or computer analysis of a building.
-
Certainly, concrete cost is not a negligible or trivial cost
-
-
ANALYSIS OF RESULTS
Analysis of the cost comparison results and investigation of their parameters gives the following:
-
Preliminary design of the braced shear wall core system overestimates the concrete construction cost of the shear wall core by almost 35%.
-
It can be easily understood that a difference of such size is a considerable difference since it is a difference higher than 10%. In other words, it cannot be considered an acceptable, even in terms of preliminary design.
-
Investigating the cost influential parameters, someone can notice that the concrete cost is a significant cost. Especially, if someone considers the whole concrete cost of the whole building (meaning concrete cost of composite beams, composite columns and composite slabs).
-
Of course, it is considered necessary the continuation of the present research to other parameters, too.
-
-
CONCLUSIONS
Parametrical comparison of the concrete construction cost for the shear wall core and analysis results result to the following conclusions:
in buildings of such size even if they possess steel elements, too.
-
Tall constructions demand high costs and preliminary design can be very helpful for consultant engineers in order to be able to reduce them.
-
More research is needed and more parameters in other cases need to be studied in order for final and more concise conclusions to be stated.
REFERENCES
-
Taranath B., "Steel, Concrete & Composite Design of Tall Buildings", 2nd edition, McGraw-Hill, USA, 1998.
-
Jayachandran P., "Tall buildings: Design and Behaviour", Proceedings of the 7th International Conference on Computational Structures Technology, Civil-Comp Press, Stirlingshire, UK, Paper 218, 2004.
-
Penelis G., Stylianidis K., Kappos A., Ignatakis C., "Reinforced Concrete Structures", A.U.Th. Press, Thessaloniki, 1995. (In Greek).
-
Penelis G., Kappos A., "Earthquake-resistant Concrete Structures", E & F N SPON (Chapman & Hall), London, December 1996.
-
Chai Y.H., Elayer D.T., "Lateral stability of reinforced concrete columns under axial reversed cyclic tension and compression", ACI Structural Journal, Vol. 96, No. 5, 1999, pp. 780-789.
-
Paulay T., Priestley M.J.N., "Stability of ductile structural walls", ACI Structural Journal, Vol. 90, No. 4, 1993, pp. 385-392.
-
Chai Y.H., Kunnath S.K., "Minimum thickness for ductile RC structural walls", Engineering Structures, Vol. 27, No. 7, 2005, pp. 1052-1063.
-
Paulay T., "The design of ductile reinforced concrete structural walls for earthquake resistance", Earthquake Spectra, Vol. 2, No. 4, 1986, pp. 783-913.
-
Chrysanidis T., Tegos I., Pallogos G., Christodoulou S., "Lateral instability of alternating tensile and compressive flanges of RC shear walls due to intense seismic flexure", Proceedings of 3rd Panhellenic Conference on Earthquake Engineering, Athens, Greece, 2008, ID 1818. (In Greek).
-
Chrysanidis T., Tegos I., Gkagkousis V., "The influence of longitudinal reinforcement ratio of boundary edges of R/C shear walls in their lateral stability", Proceedings of 16th Greek Concrete Conference, Pafos, Cyprus, 2009, ID 131005. (In Greek).
-
Chrysanidis T., Tegos I., "The influence of the degree of elongation to the ultimate strength and mode of failure of RC walls reinforced with the maximum code-prescribed longitudinal reinforcement ratio", Proceedings of the 2013 International Van Earthquake Symposium, Van, Turkey, 2013, ID 92.
-
Chrysanidis T., "The influence of the degree of tensile strain to the ultimate strength and mode of failure of seismic walls with low- reinforced end-sections", Proceedings of the 2014 International Conference On Innovative Trends in Management, Information, Technologies, Computing and Engineering to tackle a Competitive Global Environment (ITMITCE 2014), Istanbul, Turkey, 2014, ID 2014155.
-
Chrysanidis T., Tegos I., "The influence of the diameter of the longitudinal reinforcement of RC walls to their displacements against lateral instability", Proceedings of the 2014 International Conference On Innovative Trends in Management, Information, Technologies, Computing and Engineering to tackle a Competitive Global Environment (ITMITCE 2014), Istanbul, Turkey, 2014, ID 2014158.
-
White K. C., Institution of Structural Engineers, "Stability of Buildings", The Institution, London, Great Britain, 1988.
-
Chrysanidis T., Panoskaltsis V., Tegos I., "Preliminary Design and Analysis of Cost Parameters of a High-Rise Building: Braced Shear Wall Core System", International Journal of Civil Engineering and Technology (IJCIET), Vol. 7, No. 5, 2016, pp.137-152.
-
European Committee for Standardization, "EN 1998-1:2004, Eurocode 8: Design of structures for earthquake resistance – Part 1: General rules, seismic actions and rules for buildings", Brussels, Belgium, 2004.
-
Standards New Zealand, "NZS 3101:2006, Concrete structures standard: Part 1 The design of concrete structures", Wellington, New Zealand, 2006.
-
European Committee for Standardization, "EN 1992-1-1:2004, Eurocode 2: Design of concrete structures – Part 1.1: General rules and rules for buildings", Brussels, Belgium, 2004.
-
European Committee for Standardization, "EN 1993-1-1:1992, Eurocode 3: Design of steel structures – Part 1.1: General rules and rules for buildings", Brussels, Belgium, 1992.
-
European Committee for Standardization, "EN 1994-1-1:1992, Eurocode 4: Design of composite steel and concrete structures – Part 1.1: General rules and rules for buildings", Brussels, Belgium, 1992.
-
British Standards Institute, "BS 6399-2:1997, Loading for buildings – Part 2: Code of practice for wind loads", London, UK, 2002.
-
British Standards Institute, "BS 6399-3:1988, Loading for buildings – Part 3: Code of practice for imposed rof loads", London, UK, 1997.