Rehabilitation of Timber Brdige Case Study -Rehabilitation of Zero Bridge over River Jhelum at Rajbagh, Srinagar-J&K-India

DOI : 10.17577/IJERTV6IS050130

Download Full-Text PDF Cite this Publication

  • Open Access
  • Total Downloads : 205
  • Authors : Amreena Yaqoob Shah, Muqsit Masood Chishti, Mohseen Ul Hassan, Bisma Mehraj
  • Paper ID : IJERTV6IS050130
  • Volume & Issue : Volume 06, Issue 05 (May 2017)
  • DOI : http://dx.doi.org/10.17577/IJERTV6IS050130
  • Published (First Online): 04-05-2017
  • ISSN (Online) : 2278-0181
  • Publisher Name : IJERT
  • License: Creative Commons License This work is licensed under a Creative Commons Attribution 4.0 International License

Text Only Version

Rehabilitation of Timber Brdige Case Study -Rehabilitation of Zero Bridge over River Jhelum at Rajbagh, Srinagar-J&K-India

Amreena Yaqoob Shah

Department of Civil Engineering SSM College of Engineering & Technology

J&K, India

Bisma Mehraj

J&K, India,

AbstractFor thousands of years, timber bridges and other timber structures were built primarily by trial and error and rule of thumb. Designs were based on past experience, and little concern was given to efficient material usage or economy. Timber bridges which still exist in the 21st century are considered a symbol of an age old heritage and as such arises the need to rehabilitate and reconstruct them as per the modern design and accurate engineering methods which have been developed after years of research on wood as a construction material. This case study is aimed at the rehabilitation of one such old age heritage timber bridge, situated at Srinagar, J&K, India, to preserve the historic and the cultural significance it brings to the place, with the application of engineering principles and design philosophies.

Keywords Deterioration; Floor Joists; Piers; Settlement; Symmetrical And Unsymmetrical Members; Continuous And Discontinous Members; Realignment; Load Settlement Test;

  1. INTRODUCTION

    Many recent developments have increased the interest in timber bridges such as materials, improvement in chemical treatment (preservatives) and manufacturing methods. These developments reflect the advancement in the behavior of wood as a structural material. The age of wood spans human history. It has provided a resounding choice of being used as a construction material commonly known as timber. Timber has been widely used in the construction of bridges since middle ages since these bridges do not require any special equipment for installation and can normally be constructed without highly skilled labor. They also present a natural and aesthetically pleasing appearance, particularly in natural surroundings. Many of these bridges which still exist today are termed as heritage because of their history and cultural significance

    During the 1900s, a number of wooden bridges were built in Srinagar, J&K. Many different types and designs made up the once-abundant population of Srinagars covered bridges, of which only a few remain. Some of the remaining structures must be completely replaced, others are being moved to local fairgrounds or parks to be used as pedestrian crossings, and in some cases new bridges are being built alongside the old to

    Mohseen-Ul-Hassan

    J&K, India,

    Muqsit Masood Chishti

    Department of Civil Engineering Islamic University of Science & Technology

    J&K, India

    divert all traffic away from the existing structures. But the ideal preservation practice involves rehabilitation of the existing bridge, leaving it in place with the ability to carry modern loads, to remain a part of the local transportation system. In Rajbagh, Srinagar, located in the central part of the State, one such bridge named as Zero bridge remains, which was once an integral part of the state road system . The J&K Government have recognized the importance of preserving this structure as an important part of preserving the heritage & connectivity it offers. The decision was made to upgrade the bridge by rehabilitating it.

  2. NEED FOR REHABILITATION

    1. Understanding the Problem

      The bridge was chosen based on its symbolic significance, low traffic volume and generally poor condition throughout the bridge. Over the period of year, the zero bridge had become structurally or functionally deficient. Structurally, the deficiency resulted from deterioration, damage, or increased load requirements in excess of the design capacity. Hydraulically, the original waterway opening under the bridge had become inadequate as a result of changing drainage patterns in the watershed or because the hydraulic parameters on which the original design was based were inadequate.. Some members of the superstructure & substructure had a noticeable twist caused primarily by nearly broken 10-13 lower chords at opposite corners of the members. The ends of some diagonals and lower chords were decayed and crushed from years of termite attack and general deterioration. The timber members had not only been damaged because of the deterioration due to decay but they were also subjected to temperature exposures which had caused further damage due to temperature differential, as the part of timber members in the substructure remained below the water level while the other parts were way above it. Two additional piers were placed under the bridge in the 1980s, along with other various supports added in attempts to keep the bridge standing. An accurate analysis of the bridge was nearly impossible because of the unique design, the poor condition of the truss, and all the supports installed over the years. The bridge had a posted load limit of only 3 tons & a

      significant settlement had been observed in the recent years which had also been confirmed by the load settlement tests conducted near the bridge site during the recent years.

    2. Understanding the Possible Solution

      Various design options were considered, many of which would have worked well. Most centered around the concept of reducing the dead load of the bridge by providing symmetrical members instead of the existing unsymmetrical members of the bridge superstructure. This would decrease the pressure & weight on the existing foundation system of the bridge and ensure proper distribution and transmission of load through its members, thereby resulting in zero settlement, if the reduced load to which the foundation system of the bridge is subjected to, is well within the limits which it can bear & conveniently transfer and transmit to the ground below. This concept was especially attractive to us because of the uncertainty of the live-load capabilities of the old bridge system. Armed with this central idea, other more specific design parameters were formulated, including the following:

      1. The waterway adequacy must not be constricted by the improvement.

      2. Bridge capacity must be increased to handle single tandem axle loads without any settlement.

      3. Timber will be used in the improvement for aesthetic compatibility.

      4. The new system will help support the superstructure against further sag and twist, and straighten the members.

      5. Original appearance must be maintained as much as possible.

      6. The project must meet economic criteria.

  3. REHABILITATION/FINAL DESIGN SOLUTION

    A final design solution was selected based on a great deal of discussion, preliminary design calculations and sketches, and help from reputed engineers & designers, who have experience in the works of bridge rehabilitation and construction programs and are known nationwide. The final design solution is tabulated in a comparative manner to understand the rehabilitation much better. Table I shows the comparative design differences between the old design and the new design which is finally adopted in the rehabilitation of the same. The design for loading, in excess of AASHTO (American Association of State Highway and Transportation) H 15-44 loading, was based on the current AASHTO specifications [6]. The floor beam spacing (12 cm on-center) was a result of the AASHTO wheel-load distribution guidelines [7][8][9]. The main aim of all these recommended changes in the design is to decrease the overal dead load of the bridge system by replacing unsymmetrical members with symmetrical ones and realignment of members wherever it is deemed necessary for proper distribution of load stresses and thereby ultimately resulting in bringing the settlement values of the overall structure within permissible limits, which is later confirmed by the load settlement test.

    TABLE I. COMPARATIAVE DESIGN DIFFERENCES BETWEEN THE OLD DESIGN AND THE NEW DESIGN ADOPTED DURING REHABILITATION

    Existing Design

    New Design

    Remarks

    The number of floor joists

    The number of floor

    The total dead load of

    were 28 in each span with a

    joists are 20 in each

    the new design was

    spacing of 8 cm between

    span with a spacing of

    reduced by decreasing

    each joist

    12 cm on centre

    the number of floor

    between each joist

    joists & increasing the

    spacing in between.

    The ends of the main

    The ends of the main

    The extra weight that

    longitudinal beams were

    longitudinal beams are

    the connection, hinges

    connected to each other by

    connected to each other

    and the ends of the

    mild steel strips/bolts (butt

    by fevicol, epoxy and

    beam members were

    to butt joint/fish joint)

    light weight nails.

    subjected to was

    reduced considerably

    The use of beam sections

    Only two distinct sizes

    The use of symmetrical

    was very random &

    & cross sectional

    members at proper

    nonuniform. Varying cross

    beams are used in the

    places enabled to get

    sections of the beam

    bridge system. The use

    rid of a number of extra

    members were used in the

    of beam sections is

    beam members, thereby

    bridge system

    very uniform &

    reducing the overall

    disproportionately

    proportional.

    dead load of the

    (5 cm x 9 cm, 5 cm x 8 cm,

    (3 cm x 6 cm/ 5 cm x 6

    structure & moment of

    5 cm x 7 cm)

    cm)

    inertia of the whole

    beam member system

    The under strut or the

    The under strut is fixed

    The realignment of the

    inclined member of the

    on the middle ledger by

    inclined member of the

    bridge was fixed on the top

    means of groove

    bridge enabled proper

    ledger by means of cleat

    blocks.

    distribution of the

    angles

    overlying load by

    distributing the axial

    forces uniformly in the

    under strut members to

    prevent the load

    settlement

    Double piers were provided

    The use of double piers

    The symmetrical

    at many places without any

    is restricted to only on

    placement & reduction

    proper justification &

    need basis at the proper

    of unnecessary

    reasoning and their placing

    locations where it is

    members, reduced the

    was very nonuniform

    deemed necessary &

    overall load coming on

    they are placed in a

    to the ground[4][3][2]

    very uniform

    arrangement

    Mild steel sections were

    The use of steel

    The homogenous use of

    used at some places in the

    sections has been

    materials not only

    bridge system in 1980s as

    totally avoided. The

    reduced the dead load

    a part of rehabilitation to

    existing steel sections

    of the structure but also

    compliment the timber

    have been reviewed and

    enabled the overall load

    members in relieving the

    replaced again by

    system to avoid

    load stresses coming onto

    timber sections, if

    eccentricity and act as

    them.

    needed necessary

    a monolithic unit in the

    transmission of the

    loads through a well

    defined and

    noneccentric, centre of

    mass[1][7]

    Some of the beam members

    The placement & fixity

    The strength of the

    were discontinuous and did

    of all beam members

    overall bridge system

    not provide a continuous

    was reviewed & many

    was considerably

    load transmission path from

    beams were re aligned

    increased by providing

    the superstructure to the

    with proper

    continuous members &

    underlying sub structure

    connections & fixtures

    their proper

    to provide continuous

    participation in the load

    beam members.

    transmission path

    resulted in reducing the

    pressure on the

    foundation system &

    thus zero settlement

    which was later

    confirmed by the load

    settlement test.

  4. LOAD SETTLEMENT TEST AFTER REHABILITATION

    After making the necessary changes in the design as tabulated, it was necessary to make sure that the overall settlement of the bridge prior to the rehabilitation of the structure was brought under control and that the settlement after the rehabilitation was within the permissible limits, which would label the project as success. To carry out the same, the load settlement test was conducted at the various points on the downstream side, middle side and the upstream side of the bridge. The load settlement test was conducted under a load of 84 metric tons with 2400 bags filled with coarse aggregates and each bag weighing 35 kg approximately [10]. The difference in Reduced levels (RLs) at the locations in consideration before and after the test gives us the total settlement observed. After the test, it was obsrved that the total settlement reported was zero at the selected locations. Ironically, as exclaimed by one of the concerned engineer at the site, zero bridge having zero settlement has been finally achieved. Table II below gives us the observed results of the load settlement test at the selected locations:

    Location

    Initial Reduced Level prior to test (m)

    Final Reduced Level after the test (m)

    Settlement (m)

    Downstream Side

    107.80

    107.80

    zero

    Middle Side

    98.60

    98.60

    zero

    Upstream Side

    115

    115

    zero

    Average of three settlement values

    zero

    TABLE II. LOAD SETTLEMENT TEST RESULTS BEFORE AND AFTER THE TEST

    The tests confirmed and authenticated the acceptability of the measures that were adopted during rehabilitation. The process of rehabilitation was thus successful in bringing down the settlement values of the overall bridge structure and thereby ending a three decade year old growing problem of worrisome settlement which had been seen in the recent years through various tests by different independent & government sponsored studies. Figure 1 below gives us the graphical account of various settlement values as they were seen in the studies which have been conducted at zero bridge in the recent years.

  5. RECOMMENDATIONS

    Since Zero bridge is an age old timber bridge located in Kashmir which experiences a very harsh winter, it is prone to weathering effects like snowfall, rainfall etc. In view of this the use of wood preservative on wooden members is recommended to prevent it from termite attack & subsequent deterioration. Further the use of polycarbonate panel sheets should also be considered to cover the timber members wherever it is deemed necessary as an alternative against the weathering effects due to harsh climate. To strengthen the foundation of timber piles, it is recommended that shelling wires should be fixed & tightened with the group of existing piers, encircling the individual trestle pier. Stones and boulders of specified shape & size should be dumped deep encircling the pier to increase its strength & to withstand the flowing magnitude of water during floods. Use of modern techniques like underpinning and jacketing of columns can also be done to increase the strength of timber columns.

  6. CONLCUSION

In retrospect, the project was a success. An important bridge was saved and left in service. Some historians and bridge purists may argue the methods used, or question the authenticity or aesthetic value that remains, but there is probably no perfect or absolutely correct way to improve these bridge deficiencies and still preserve them. Too many factors are involved to ideally address each problem area of the bridge. It tends to become a give-and-take process.

REFERENCES

  1. Ritter, Michael A. 1990. Timber Bridges: Design, Construction, Inspection, and Maintenance.Washington, DC: 944 p.

  2. Muchmore, F.W. 1986. Designing timber bridges for long life. In: Trans. Res. Rec. 1053. Washington, DC: Transportation Research Board, National Res. Council: 12-17

  3. Muchmore, F.W. 1984. Techniques to bring new life to timber bridges. Journal of Structural Engineering 110(8): 1832-1846.

  4. Muchmore, F.W. 1983. Timber bridge maintenance, rehabilitation, and replacement. GPO 693-015. Missoula, MT:

    U.S. Department of Agriculture, Forest Service, Northern Region. 31 p.

  5. Park, S.H. 1989. Bridge rehabilitation and replacement. Trenton, NJ: S.H.Park. 818 p.

  6. American Association of State Highway and Transportation Officials. 1983.Manual for maintenance inspection of bridges. Washington, DC: American Association of State Highway and Transportation Officials.50p.

  7. American Society of Civil Engineers. 1982. Evaluation, maintenance, and upgrading of wood structures. Freas, A., ed.

    New York: American Society of Civil Engineers. 428 p

  8. American Institute of Timber Construction. 1985. Timber construction manual. 3d ed. New York: John Wiley and Sons,

    Inc. 836 p

  9. American Society of Civil Engineers. 1986. Evaluation and upgrading of wood structures: case studies. New York: American Society of Civil Engineers. 111 p.

American Society of Civil Engineers. 1980. A guide for the field testing of bridges. ASCE Working Committee on Safety of Bridges. New York: American Society of Civil Engineers. 72 p.

Leave a Reply