Cost Overrun Assessment Model in Highway Construction Projects Using Fuzzy Uncertainty Analysis

DOI : 10.17577/IJERTV6IS040490

Download Full-Text PDF Cite this Publication

Text Only Version

Cost Overrun Assessment Model in Highway Construction Projects Using Fuzzy Uncertainty Analysis

Mr. Manoj Thorat1 1 P.G.Student,

Department of Civil Engg, TatyasahebKore Institute of Engineering and Technology,

Warananagar, India

Prof. B.V.Birajdar 2 2 Professor and Head, Dept.of Civil Engg,

TatyasahebKore Institute of Engineering and Technology,

Warananagar,India

Abstract: – The aim of this paper is to propose a model for predicting cost overrun in highway construction projects using fuzzy logic. Model provides a decision support tool for contractors and project managers before bidding stage to quantify the probability of cost overrun. A list containing 52 factors responsible for cost overrun is prepared through vast literature review and negotiating with experts in highway construction industry. Total of 28 experts were asked to rank the identified factors on a five point likert scale. Identified factors are arranged in descending order using relative importance index method (RII). Top five factors are shortlisted for cost overrun assessment model development using fuzzy toolbox of MATLAB program software. Developed model shows graphs of variation of cost overrun for different combination of cost overrun factors. Finally, model validation is done using a case study.

Keywords: – Construction industry, Cost overrun, Fuzzy logic, Relative importance index

  1. INTRODUCTION

    Construction industry is considered as one of the most dynamic and risky industrial sector. Many construction projects do not attain all their desired goals due to the presence of risks and uncertainties intrinsic in the project. One of the main duties of the construction project manager is to ensure that the project does not exceed its allotted cost & time frames despite claims. Due to different uncertainties such as Client characteristics, Consultant and design parameters, Contractor attributes, Project characteristics, Contract procedures and procurement methods, External factors and market conditions etc., the actual cost of project is not certainly known for the managers in advance. Therefore, total cost of project may differ significantly because of these uncertainties. In the construction market, most construction companies are willing to undertake infrastructure projects such as highway in order to maximize their profitability. In order to be awarded a contract in highly competitive construction market, companies should excel in choosing the most attractive markets and prepare winning bids for the selected construction projects in those markets. While preparing bids, the major concern of companies is to offer an optimum price that will enable them to earn enough profits and win the contract at the same time, where profit making

    ability is strongly correlated with proper estimation of a risk premium that is added onto the estimated cost of the project. Therefore a good forecasting approach is needed at the time of planning itself.

  2. LITERATURE REVIEW

Garry D. Creedy, Martin Skitmore and Johnny K.W.Wong (2010) addressed the problem of why highway projects overrun their predicted costs. It identified the owner risk variables that contribute to significant cost overrun and then used factor analysis, expert elicitations, and nominal group technique to establish groups of importance ranked owner risks. Stepwise multivariate regression analysis is also used to investigate any correlation of the percentage of cost overrun with risks, together with attributes such as highway project type, indexed cost, geographic location and project delivery method.

Murat Gunduz, Yasemin Nielsen and Mustafa Ozdemir (2014) propose a decision support tool for contractors before the bidding stage to quantify the probability of delay in construction projects in Turkey by using the relative importance index (RII) method incorporated into fuzzy logic. For this purpose, 83 delay factors were identified, categorized into 9 major groups through a detailed literature review process as well as interviews with experts from the construction industry. The assessment model was developed using a commercial software product. The proposed methodology was tested in a real case study. Finally, some recommendations were made in order to minimize and control delays in construction projects.

YehielRosenfield (2013) examined the cost overrun phenomenon as a worldwide problem, identified its root causes, ranked them (on a local basis), and analysed them. Through expand focus principle, 146 potential causes gathered from the international professional literature as well as from prominent local experts. Through two cycles of expandfocus, they were filtered and merged into merely 15 independent universal root causes.

IIIRESEARCH METHODOLOGY

  • Deciding cost overrun factors through a detailed literature and preparation of questionnaire for rating

    factors by expertise from highway construction field according to their severity level on a suitable scale.

  • Selecting top five cost overrun factors by ranking them

    Where

    RII = W

    AXN

    using Relative Importance Index (RII) method.

  • Applying fuzzy logic technique for the development of cost overrun assessment model using fuzzy toolbox of MATLAB program software.

  • Validation of model by applying it to a case study.

  1. Identification and Ranking of cost overrun Factors

    In this research, 52 factors responsible for cost overrun in highway construction projects are identified through vast literature survey. A Questionnaire form which is consisting of two parts A and B has been developed. In Part A personal Information of the respondents (for e.g. work experience, organization, average cost overrun of a project) was asked. Part B was aimed to obtain information about causes of cost overrun in highway construction industry. It was asked to rate those initially identified 52 factors according to their severity level on the given scale i.e. 1- Very low importance 2-Low importance 3-Medium importance

    4-High importance 5-Very high importance

    The relative importance index (RII) is calculated by using the relation given below:

    W is the weighting given to each factor by the respondent (ranging from1 to 5),

    A is the highest weight and N is the total number of respondent.

    e.g. Considering factor Escalation of material prices,

    RII = 123/528= 0.8785

    Relative importance index for all 52 factors are calculated and tabulated in descending order of RII. Table1 shows the causes rearranged in descending order according to their corresponding RII. Then, the causes are ranked according to their RII such that the cause received the highest RII is assigned rank equal to 1.Though all factors may be responsible for the cost overrun, it is very difficult to handle all the factors simultaneously. So to resolve this problem, we will consider only five top most ranked factors for further analysis. It is beneficial so that handling five factors is possible and as they are most affecting factors to cost overrun, we may predict or assess cost overrun related to highway construction project.

    Table 1: List of identified cost overrun factors with RII and Rank

    Sr. No.

    COST OVERRUN FACTORS

    RII

    RANK

    1.

    Escalation of material prices

    0.8785

    1

    2.

    Right of way acquisition (Land acquisition)

    0.8642

    2

    3.

    Incorrect planning and scheduling by contractor

    0.8500

    3

    4.

    Improper construction methods

    0.8357

    4

    5.

    Contract failure-new contract establishment cost

    0.8285

    5

    6.

    Payments delay

    0.8214

    6

    7.

    Inaccurate investigation of construction site

    0.7928

    7

    8.

    Frequent change of subcontractors

    0.7928

    8

    9.

    Delay in reviewing and approving design documents during construction by consultant

    0.7857

    9

    10.

    Frequent equipment breakdown

    0.7714

    10

    11.

    Specification change

    0.7642

    11

    12.

    Poor communication between construction parties

    0.7642

    12

    13.

    Inadequate labour productivity

    0.7642

    13

    14.

    Encroachment problems

    0.7571

    14

    15.

    Contract tender price higher than the original cost estimate

    0.7500

    15

    16.

    Poor quality of project management

    0.7428

    16

    17.

    Latent conditions such as rock, and soil suitability, terrain conditions, ground conditions etc

    0.7428

    17

    18.

    Constructability under traffic

    0.7357

    18

    19.

    Experience in contracts

    0.7285

    19

    20.

    Frequent design changes

    0.7285

    20

    21.

    Lack of qualified project manager

    0.7000

    21

    22.

    Weather

    0.6928

    22

    23.

    Incomplete Drawings

    0.6928

    23

    24.

    Rework due to error by contractor

    0.6857

    24

    25.

    Lack of skilled labour

    0.6785

    25

    26.

    Rehabilitation of affected people

    0.6642

    26

    27.

    Ineffective delay penalties

    0.6642

    27

    28.

    Low efficiency of equipment

    0.6571

    28

    29.

    Late delivery of material

    0.6500

    29

    30.

    Political situation

    0.6357

    30

    31.

    Slow mobilization of equipment

    0.6285

    31

    32.

    Mistakes in design

    0.6285

    32

    33.

    Natural disasters such as earthquake, floods, hurricane etc

    0.6071

    33

    34.

    Remote location cost

    0.5928

    34

    35.

    Shortage of equipment

    0.5928

    35

    36.

    Poor financial control

    0.5928

    36

    37.

    Experience in the line of work

    0.5857

    37

    38.

    Changes in government regulations and laws

    0.5857

    38

    39.

    Unclear arbitration process for legal disputes between construction parties

    0.5714

    39

    40.

    Inflation

    0.5642

    40

    41.

    Unreliable supplier of material

    0.5571

    41

    42.

    Monopoly of material suppliers

    0.5500

    42

    43.

    Obsolete technology

    0.5500

    43

    44.

    Absenteeism of labour

    0.5285

    44

    45.

    Deficient documentation

    0.5214

    45

    46.

    Period of contract

    0.5142

    46

    47.

    Difficulties in importing equipments and materials

    0.5000

    47

    48.

    Size of contract

    0.4928

    48

    49.

    Cultural heritage issue

    0.4857

    49

    50.

    Personal conflicts among labour

    0.4571

    50

    51.

    Social and cultural impacts

    0.4500

    51

    52.

    Changing of bankers policy for loans

    0.4428

    52

    Table 2: List of top five important factors

    Sr. No.

    COST OVERRUN FACTORS

    RII

    RANK

    1.

    Escalation of material prices

    0.8785

    1

    2.

    Right of way acquisition (Land acquisition)

    0.8642

    2

    3.

    Incorrect planning and scheduling by contractor

    0.8500

    3

    4.

    Improper construction methods

    0.8357

    4

    5.

    Contract failure-new contract establishment cost

    0.8285

    5

  2. Fuzzy Logic Controller

    Figure 1: Fuzzy Logic Controller

    The term "fuzzy" refers to the fact that the logic involved can deal with concepts that cannot be expressed as the "true" or "false" but rather as "partially true". A fuzzy logic system (FLS) can be defined as the nonlinear mapping of an input data set to a scalar output data. A FLS consists of four main parts: fuzzifier, rules, inference engine, and defuzzifier. These components and the general architecture of a FLS is shown in Figure 1. Firstly, a crisp set of input data are gathered and converted to a fuzzy set using fuzzy linguistic variables, fuzzy linguistic terms and membership functions. This step is known as fuzzification. Afterwards, an inference is made based on a set of rules. Lastly, the resulting fuzzy output is mapped to a crisp output using the membership functions, in the defuzzification.

    1. Membership Functions

      A membership function is a curve in which input space is sometimes referred to as the universe of discourse, defining how each point in the input space is mapped to a membership value between 0 and 1. Membership functions are used in the fuzzification and defuzzification steps of a FLS, to map the non-fuzzy input values to fuzzy linguistic terms and vice versa. There are different shapes of membership functions, viz, triangular, trapezoidal, Gaussian, bell-shaped etc. Triangular membership functions are used in this study as they are widely used

    2. Fuzzy Rules

      In a FLS, a rule base is constructed to control the output variable. A fuzzy rule is a simple IF-THEN rule with a

      condition and a conclusion. The actual meaning of the if…. and… then rules is

      If x is A i and y is B j then z is C k

    3. Defuzzification

      Defuzzification is the process in which outcomes of control models in the form of fuzzy numbers can be converted to precise output numbers. Fuzzy outcomes of fuzzy control model, including effects of all input variables of problem, and considering integrated effects of them by accessing various cost overrun phenomenon by fuzzy rules, are undergone fuzzy removing process and cost overrun is determined as an interval of zero to one.

  3. Analysis steps for the model development using fuzzy toolbox of MATLAB software

    To develop the model, following steps are performed on fuzzy logic tool box of MATLAB.

    1. Construct a five input, one output system in the FIS editor. The identified cost overrun factors and cost overrun are entered as input members and output member respectively.

    2. Membership functions of all of the input and output variables are defined in membership function editor.

    3. In order to perform fuzzy inference, rules which connect input variables to output variables are defined. For the present model 210 rules are constructed in the form of IF-THEN

    4. The relative importance indices (RIIs) of cost overrun factors are assigned as weight to the fuzzy rules to develop the assessment model to estimate the probability of cost overrun.

  4. Cost Overrun Prediction Model using Fuzzy toolbox of MATLAB software

    Development of cost overrun assessment model in fuzzy inference system involves steps such as FIS editor, membership function editor, Formation of rules (Rules editor), Weighing of rules and defuzzification. Following table 3 shows linguistic variables used in model and their membershipfunction.

    Table 3: Linguistic variables used for model development and their membership functions

    Variables

    Range

    MFs

    No of MFs

    Name of the parameters

    Escalation of material prices

    [0-1]

    trimf

    5

    1.very low 2.low 3.medium 4.high 5.very high

    Right of way/Land acquisition

    [0-1]

    trimf

    5

    1.very low 2.low 3.medium 4.high

    5.very high

    Incorrect planning and scheduling by manager

    [0-1]

    trimf

    5

    1.very low 2.low 3.medium 4.high

    5.very high

    Improper construction methods

    [0-1]

    trimf

    5

    1.very low 2.low 3.medium 4.high

    5.very high

    Contract failure-new contract establishment cost

    [0-1]

    trimf

    5

    1.very low 2.low 3.medium 4.high

    5.very high

    1. Fuzzy Inference Editor

      The FIS Editor displays general information about a fuzzy inference system. In this step, input and output parameters are fixed. We have considered five input and one output system. So from edit option, five inputs are added. Editing and nomenclature of each of five inputs and single output is done. Thereafter, file is saved by exporting it to workspace. In this way, FIS editing is completed. Mamdani and sugeno are two types of inference systems used. Mamdani type of inference system is used here. FIS editor from fuzzy toolbox is shown in the figure 2.

      Figure 2: Fuzzy Inference Editor

    2. Membership Function Editor

      The Membership Function Editor is the tool that lets you display and edit all of the membership functions associated with all of the input and output variables for the entire fuzzy inference system. Membership function editor from fuzzy toolbox is shown in the figure 3.

      Figure 3: Membership Function Editor

    3. Rule Editor

      At this point, the fuzzy inference system has been completely defined, in that the variables, membership functions, and the rules necessary to analyze cost overrun are in place. Total 210 rules are created using all five input

      variable factors and one output variable. While creating rules, as maximum as possible possibilities and combinations of input variable factors are taken as uncertainty involved is maximum. While inserting rules by combination of two input variable factors, assign weight as average of relative importance index of both the factors. Sample rules are given below:

      1. If Escalation of material prices is Very Low then Cost overrun is Very Low (0.8785)

      2. If Escalation of material prices is Low then Cost overrun is Low (0.8785)

      3. If Escalation of material prices is Medium then Cost overrun is Medium (0.8785)

      4. If Escalation of material prices is Medium then Cost overrun is Medium (0.8785)

      5. If Escalation of material prices is Very High then Cost overrun is Very High (0.8785)

      6. If Right of way aquisition is Very Low then Cost overrun is Very Low (0.8642)

      7. If Escalation of material prices is Very Low and Right of way acquisition is Very Low then Cost overrun is Very Low (0.8713)

    4. Rule Viewer

      The Rule Viewer displays a roadmap of the whole fuzzy inference process. It is based on the fuzzy inference diagram described in the previous section. The Rule Viewer allows you to interpret the entire fuzzy inference process at once. The Rule Viewer also shows how the shape of certain membership functions influences the overall result.

      Figure 4: Rule Viewer

    5. Surface Viewer

      In surface viewer, we can see variation of any two cost overrun factors acting in combination with respect to cost overrun.

      Figure 5: Surface Viewer

  5. Model Validation

Model validity concerns the degree to which the variables, as measured by the research reflects the hypothesized construct. A detailed case study analysis of state highway construction project is carried out to validate the survey findings on most significant factors contributing to cost overrun. The completed state highway construction project Kapurhol-Purandar which is located in Pune district, Maharashtra. Following are the major factors due to which project suffered cost overrun with the percentage loss caused by each factor shown in table 4:

  1. Specification change- 20.5%

  2. Latent conditions such as rock and soil suitability, terrain and ground conditions etc- 19%

  3. Delay in reviewing and approving design documents during construction by consultant-15.5%

  4. Frequent change of subcontractors- 8%

  5. Payments delay- 2.5%

    Table 4: List of major factors responsible for a cost overrun in a case study with RII

    Sr. No.

    FACTORS

    RII

    1.

    Specification change

    0.7642

    2.

    Right of way acquisition (Land acquisition) Latent conditions such as rock

    and soil suitability, terrain and ground conditions etc

    0.7428

    3.

    Delay in reviewing and approving design documents during construction by

    consultant

    0.7857

    4.

    Frequent change of subcontractors

    0.7928

    5.

    Payments delay

    0.8214

  6. RESULTS AND DISCUSSIONS

Results obtained by implementing the developed model to a case study are tabulated in table 5. Results show that for different Percentage loss of each of theinput variable i.e. factors responsible for cost overrun, the increase in estimated cost of the project (cost overrun) in percentage can be found out. This model gives us prediction about cost

overrun due to worst activity of different factors. Considering first combination of different Percentage loss of factors, due to which Kapulhor-Purandar state highway suffered increase in estimated cost of project would have been predicted as 17.3%. Similarly, cost overrun can also be predicted for another different combination of percentage loss of factors as shown in table 5.

Table 5: Cost overrun for different % loss of factors-case study

Factors

Specification change (%loss)

Latent conditions such as rock and soil suitability, terrain and ground conditions etc (%loss)

Delay in reviewing and approving design documents during construction by consultant (%loss)

Frequent change of subcontractors (%loss)

Payments delay cost (%loss)

Cost overrun (%)

1.

20.5

19

15.5

8

2.5

17.3

2.

15

25

5

5

15

22.1

3.

20

15

10

10

5

17.2

In table 6, all the information regarding project such as estimated and final cost of the project, cost overrun estimated by the application of developed model to the mentioned state highway project and actual cost overrun is tabulated. Percentage error between estimated cost overrun

and actual cost overrun is calculated as 8.09% which means model can give results with an accuracy of ±5-10%. As estimated cost overrun is less than and close to actual cost overrun, the proposed model holds good for prediction of cost overrun.

Table 6: Final results of a case study

Project details

Type of Project

Highway Construction

Name of Project

Kapurhol-Puranadar/SH-63, Dist-Pune

Specification change

20.5 % loss

Latent conditions such as rock and soil suitability, terrain and ground

conditions

19 % loss

Delay in reviewing and approving design documents during construction by consultant

15.5 % loss

Frequent change of subcontractors

8 % loss

Payments delay cost

2.5 % loss

Estimated cost of Project

Rs. 127500000

Final Cost of Project

Rs. 151350000

Cost Overrun (estimated)

17.3%

Cost overrun (actual)

18.7%

% error=[(Actual-Estimated)/Estimated]x100

8.09%

IV. CONCLUSION

Cost overrun phenomenon is very common in highway construction industry. Only some projects are completed within the budget. To avoid construction cost overrun, there is need to develop a cost overrun prediction/assessment model as a decision support tool for the project managers, cost estimators for the construction projects before bidding stage. The fuzzy logic has a great prediction capability given by many researchers; it has bright scope in civil engineering research (optimization). Some conclusions of the case study are enlisted below:

  1. Cost overrun can be estimated at the planning stage itself and suitable preventive measures can be adopted to overcome the situation and to avoid serious consequences.

  2. The factors that are responsible for increase in cost are identified in this report. The percentage of affectability of factors changes from project to project. So for different projects, this model can be applied effectively only by allocating value of RII corresponding to factors considered keeping all parameters same.

  3. The fuzzy logic handles the uncertainties which reside during construction projects and it can handle multiple inputs easily and quantify more realistically the classical problem analysis.

  4. Other approaches require accurate equations to model real-world behaviors, fuzzy logic can accommodate the ambiguities of human languages and logics.

  5. One of the shortcoming of this method is that as fuzzy rules are based on expert judgement and literature survey findings, it is clear that a completely different model may be proposed by other researchers based on different expert opinions.

REFERENCES

  1. Abdullah Alhomidan (2013): Factors Affecting Cost Overrun in Road Construction Projects in Saudi Arabia, International Journal of Civil & Environmental Engineering, 13(3), pp. 1-4.

  2. Ahmed A. Shaheen, Aminah Robinson Fayek, S.M.AbouRizk (2007): Fuzzy Numbers in Cost Range Estimating, Journal of Construction Engineering and Management

  3. AraziIdrus, MuhdFadhilNuruddin, M. ArifRohman (2011): Development of project cost contingency estimation model using risk analysisand fuzzy expert system, Elsevier, Expert Systems with Applications, 38 (2011), pp. 1501-1508.

  4. George J. Klir and Bo Yuan Fuzzy Sets and Fuzzy Logic Theory and Applications, Prentice Hall of India, 2000, ISBN:978-81-203-1136-7.

  5. Garry D. Creedy, Martine Skitmore, Johnny K.W.Wong (2010): Evaluation of Risk Factors Leading to Cost Overrun in Delivery of Highway Construction Projectws, Journal of Construction Enginnering and Management, 136(5),

    ©ASCE, pp. 528-537.

  6. HemantaDoloi (2013): Cost Overruns and Failure in Project Management: Understanding the Roles of Key Stakeholders in Construction Projects, Journal of Construction Engineering and Management, 139(3), ©ASCE, pp. 267- 279.

  7. Ibrahim Mahamid, AmundBruland (2011): Cost Overrun in Road Construction Projects: Consultants Perspective, International Conference on Construction and Project Managaement, IPEDR vol.15(2011), Singapore, pp. 6-11.

  8. JesperKranker Larsen, Geoffrey QipingShen, Søren Munch Lindhard, Thomas DitlevBrunoe (2015): Factors Affecting Schedule Delay, Cost Overrun, andQuality Level in Public Construction Projects, Journal of Management in Engineering, ©ASCE, pp. 1-10.

  9. Karla Knight, Aminah Robinson Fayek (2002): Use of Fuzzy Logic for Predicting Design Cost Overrunson Building Projects, Journal of Construction Engineering and Management, ©ASCE, pp. 503-512.

  10. Murat Gunduz, Yasemin Nielsen, Mustafa Ozdemir (2014): Fuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects, Journal of Management in Engineering, ©ASCE, pp. 1-14.

  11. Nabil Ibrahim El Sawalhi (2012): Modeling the Parametric Construction Project Cost Estimate using Fuzzy Logic, International Journal of Emerging Technology and Advanced Engineering, 2(4), pp. 631-636.

  12. VacharaPeansupap, LakhenaCheang (2015): Identifying issues of change leading to cost conflicts: case study in Cambodia, Creative Construction Conference 2015, Procedia Engineering 123, pp. 379-387.

  13. Yehiel Rosenfeld (2013): Root-Cause Analysis of Construction-Cost Overruns, Journal of Construction Engineering and Management, 140(1), ©ASCE, pp. 1-10.

  14. ZayyanaShehu, IntanRohaniEndut, AkintolaAkintoye, Gary

D. Holt (2014): Cost overrun in the Malaysian construction industry projects: A deeper insight, International Journal of Project Management, pp. 1-10.

Leave a Reply