Developing Installed DC Power Backup System for the APR1400 for Station Black-Out (SBO) Coping.

DOI : 10.17577/IJERTV5IS110276

Download Full-Text PDF Cite this Publication

Text Only Version

Developing Installed DC Power Backup System for the APR1400 for Station Black-Out (SBO) Coping.

Shiran K. A, R. M. Field

KEPCO International Nuclear Graduate School, KINGS. Ulsan, Republic of Korea.

Abstract:- On March 11, 2011 the Fukushima Daichi and Daini nuclear plants were severely impacted by the Great East Japan earthquake. Seismic damage to the transmission system led to the loss of nearly all offsite power. Internal flooding damage from the concomitant tsunami resulted in loss of all medium voltage emergency AC power buses at the four (4) original units at the Daichi site. These units were then subjected to Station Blackout (SBO) conditions for an extended period. Several units at the Fukushima Daini site were similarly subjected to SBO conditions. Following the events described above, the nuclear industry and regulators have issued many analyses and reports which focus on Fukushima specific design margins, safety features, and operator actions. However, little attention is paid to the near complete loss of instrumentation and control power which made operator monitoring and response to the accident significantly more difficult. Despite heroic efforts to restore power to the DC instrument buses (e.g., using car batteries connected in series) operators were left in the dark. This paper examines proposed designs for direct onsite charging of DC instrumentation bus batteries (independent of the AC medium voltage buses) which utilize decay heat as a source of energy.

Keywords:- APR1400, Fukushima Daichi, Micro Steam Turbine-Generator Station Black-Out, Systems Engineering,

INTRODUCTION

Following the tragic events at the Fukushima Daichi nuclear plant following the Great East Japan earthquake, the nuclear industry, its critics, and nuclear regulators have engaged in a re-examination of nuclear safety in particular and of the use of nuclear power in general. The Fukushima disaster has shaken public confidence in nuclear safety and led to a re-examination of the way in which many of the core principles which underlie the safety of commercial nuclear power plants have been implemented. These include defense-in-depth, nuclear safety culture, design basis, beyond design basis, and nuclear safety regulation. Many safety improvements in the areas of design, regulation, and culture have been proposed including post-Fukushima action items in the U.S. In Korea, the nuclear operator, KHNP has committed to a long list of safety post-Fukushima improvements in many areas including: (i) design enhancements, (ii) flooding vulnerability reviews, (iii) mobile emergency diesel generator units, (iv) upgrades to emergency procedures, and (v) post-accident containment vent systems.

However, in reviewing various responses to the Fukushima experience, it appears that one area which

has not received sufficient attention is robust power supply for DC instrumentation. Most proposals assume that power for providing power supply to DC buses and for charging of DC batteries can be provided by medium voltage AC power buses once such power is restored. In the event these buses become damaged or are inoperable, power will likely be subsequently lost to the DC buses. An increase in battery capacity for supplying the DC buses can address this concern to some extent but capacity alone does not result in a robust capability. To help operators cope with SBO conditions until recovery of AC bus power can be achieved (either from onsite or offsite sources) the ability to provide direct and sustained charging of emergency DC batteries will greatly improve the ability to cope with prolonged SBO conditions.

From a human factors standpoint, it is critical that operators have the ability to monitor and respond to the SBO event sequence while other groups are working to restore emergency shutdown capability. Proposed here are relatively simple design concepts which can maintain the charge in the DC batteries and hence power to the DC instrument and control buses. This will permit the operators to monitor conditions and execute responses for an indefinite period while others work to restore AC power.

An energy source for charging DC batteries is available in the form of decay heat as released to the atmosphere via steam relief from the secondary side to the atmosphere. Two options to harness this steam are examined here, one using the steam discharged from the atmospheric dump valve and the other using steam supplied to the steam turbine driven auxiliary feed water pump.

This paper presents the physical arrangements for these proposed designs. Next analysis which demonstrates that required battery charging for an extended period can be maintained. Option 1 has a greater capability but requires direct interface with the safety related piping which supplies the turbine driven auxiliary feed water pump.

BACKGROUND

After the Fukushima Daiichi accident, Design Extension Conditions (DECs) such as total loss of feed water (TLOFW), and prolonged Station Black-Out

(SBO) attracted the attention of nuclear experts. The focus was on the defense in depth concept, redundancy and sustainability of the systems, and development of the passive safety systems which rely on natural physics laws.

WLB

WLB

RVR 1%

RVR 1%

SLOCA

SLOCA

ATWS

4%

ATWS

4%

4% 4%

4% 4%

PLOESW

6%

PLOESW

6%

SBO

41%

SBO

41%

Likewise, the SBO event is the largest contributor to Core Damage Frequency (CDF) for many operating plants. Figure 1 shows the CDF contribution for the APR1400 by internal initiating events.

F GTRN

F GTRN

LSSB-D2% 2%

LSSB-D2% 2%

SGTR4%

SGTR4%

PLOCCW

10%

PLOCCW

10%

MLOCA

10%

TLOCCW/TL

OESW 13%

MLOCA

10%

TLOCCW/TL

OESW 13%

Fig. 1. CDF Contribution by Internal Initiating Events

Maanshan – Ten years before Fukushima Daiichi nuclear disaster, Maanshan NPP Unit 1 in Taiwan experienced an SBO event. On March 18, 2001 a seasonal sea smog resulted in containing salt deposits which caused a malfunction of all four 345KV power transmission lines. The 4.16 kV essential bus A breaker No. 17 opened and the No. 15 closed, transferring supply from the 161 kV offsite power. A few minutes later, power to the 345 kV was restored, but during transfer a ground fault at essential bus A occurred. The unit then lost power from all offsite sources. Furthermore, both the emergency diesel generators failed to operate, resulting in an SBO accident.

There was also report from onsite staff that heavy smoke was coming out from the control building at floor location 46-ft below the control room, where the essential buses were located. Examination subsequent to the event indicated a severely damaged essential bus (medium voltage bus 1A).

During that night, as the DC batteries drained, operators lost plant control and monitoring instrumentation. Plant workers were focused on restoring the EDGs and connecting them manually to bus A. The work was conducted in darkness, under very challenging conditions. Firemen helped by providing lighting. Despite this, operators could not estimate plant conditions and parameters. After several attempts, workers successfully returned one EDG to operation. Following that, plant staff separated the Unit

1 Bus B from the damaged Bus A. Bus B was powered via 161KV from Unit 2 transformer.

The Fukushima Daichi, Fukushima Daini, an Maanshan events all illustrate that the ability to restore a source of power to the medium voltage essential AC

buses does not provide robust assurance that power can be restored to the essential DC buses. This paper examines an alternative approach to restoring power to the DC buses with available power sources under SBO scenarios.

METHODOLOGY

Systems Engineering A Systems Engineering (SE) approach has been used for this study, by which an interdisciplinary approach is employed to assure the realization of successful Micro Steam Turbine-Generator System (MSTGS). The SE approach for developing the MSTGS involves inputs, process activities, enablers, controls, and outputs. The processes of SE approach for developing the MSTGS are shown in Fig. 2.

Controls

-USNRC Regulations

-Safety Classifications

-APR1400 Documentation

Controls

-USNRC Regulations

-Safety Classifications

-APR1400 Documentation

Inputs

– DC Charging System Req. Analysis

-User Requirements

-APR1400

Characteristics

Inputs

– DC Charging System Req. Analysis

-User Requirements

-APR1400

Characteristics

Outputs

  • MSTGS system specifications

  • MSTGS architecture design

Outputs

  • MSTGS system specifications

  • MSTGS architecture design

Process Activities

– APR1400 decay heat & Steam Flow Analysis

– Backpressure Effect on Valve Capacity

– Downstream Steam Conditions

– Moody Coefficient

-Functional & Design Requirements

-Interdisciplinary Calculations

Enablers

-Shin Kori unit 3

-Apr1400 simulator

Enablers

-Shin Kori unit 3

-Apr1400 simulator

Fig. 2. Systems Engineering Processes

For input to the SE, the requirements analysis consists of determining the APR1400 DC power system loads under SBO conditions. Table 1 summarizes the power demand. The required power to supply all essential and non-essential DC buses is 200 kW (i.e., 192 kW with applied margin). The MSTGS will operate intermittently (e.g., based on ADV operating cycle) and therefore the design must then provide an average of this power for battery charging while accommodating the existing battery capacity (e.g., 8-hrs).

DC power system continuous loads

Class 1E 125 VDC Power System

Non-Class 1E 125 VDC Power System

Train A

Train B

Division I

441.4

A

55175

W

384.1

A

48012.5

W

72.4 A

9050 W

Train C

Train D

Division II

291.9

A

36487.5

W

289

A

36125

W

59.4 A

7425 W

Train A+C

Train B+D

733.3

A

91662.5

W

673.1

A

84137.5

W

Total Class 1E load is

175.80 kW

Total Non- Class 1E load is

16.48 kW

Total continuous loads is 192.28 kW

Table [1] APR1400 On-site DC Power System Loads.

The onsite DC power system is divided into independent Class 1E and non-Class 1E DC power systems. Table 2 shows the functionality of the existing APR1400 DC power system.

Furthermore, a set of user requirements were defined based on APR1400 characterizations and systems design. The user requirements are:

  1. The MSTGS shall be able to generate an average of 200 kW power under SBO conditions

  2. The MSTGS shall be able to work even under discontinuous and varying steam flow rate.

  3. The MSTGS shall not affect the function or performance of other safety systems and must meet the classification requirements.

  4. The MSTGS have to be connected to the existing DC system converters.

Under the process activities section of the SE process (Fig. 1.) the available APR1400 decay heat was analyzed and the amount of the steam generated by the decay heat was calculated versus time. Two system configurations are considered in this study. Case 1 assumes that all steam which is discharged from the ADVs is directed to the MSTGS. Case 1 assumes the microturbine skid is located in the turbine drive auxiliary feedpump room and steam is supplied by the steam supply line to the pump turbine. For Case 2 the microturbine is located in or adjacent to the Main Steam Isolation Valve room. Steam is taken from the non-safety related discharge line serving the MS ADV

Table [2] The Functionality of Existing APR1400 DC Power System

DC power system

Class 1E DC power systems

Non-Class 1E DC power system

System

Functionality

Comment

System

Functionality

Comment

Class 1E 125 VDC Power System

supplies reliable power to the plant safety system dc loads and essential I&C system loads

Included in this study

Non-Class 1E 125 VDC Power System

The system is designed to supply

The emergency lighting and emergency lighting panel

Included in this study

Class 1E 120 VAC

Is required for all plant operating

Excluded

Non-Class 1E 250

Supplies power to high-inrush

Excluded

Instrumentation and

conditions. The Class 1E 120 Vac

from this

VDC Power System

dc loads that generally serve as

from this

Control Power System

I&C power system supplies a

study since its

backups to turbine generator

study since

continuous, reliable, and regulated

AC load

ac loads.

the turbine

ac power to the safety-related

has been

plant instruments, control

tripped off

equipment, and engineered safety

feature component control

system (ESF-CCS), which are

required to be operational during

the momentary or complete loss of

onsite ac power.

Stea m Flow Rate

S/ G T

S/G P

Hin

Sin

Hisen

Energy Availab le

lbm/h r

(De g F)

(psi a)

(BTU/lb m)

(BTU/lb m-deg F)

(BTU/lb m)

(BTU/lb m)

3 hours

142,0

00

482

579.

1

1203.94

1.450

962.14

242

27 hours (1 Day)

107,0

00

290

57.6

1176.81

1.647

1098.08

79

55 hours (2 days)

78,00

0

290

57.6

1176.81

1.647

1098.08

79

Stea m Flow Rate

S/ G T

S/G P

Hin

Sin

Hisen

Energy Availab le

lbm/h r

(De g F)

(psi a)

(BTU/lb m)

(BTU/lb m-deg F)

(BTU/lb m)

(BTU/lb m)

3 hours

142,0

00

482

579.

1

1203.94

1.450

962.14

242

27 hours (1 Day)

107,0

00

290

57.6

1176.81

1.647

1098.08

79

55 hours (2 days)

78,00

0

290

57.6

1176.81

1.647

1098.08

79

Case 1 – For this case, steam is supplied to the MSTGS from the steam supply line to the turbine driven pump. The parameters for available steam (i.e., to drive the MSGTS) are calculated as a function of time following the initiation of the SBO accident in three time intervals as shown in Table 3. Note that only a small fraction of available steam is required to drive the AF pump turbine to provide sufficient makeup for heat removal (i.e., the pump add less than 8 BTU/lbm while each pound of water supplied to the S/G absorbs ~1000 BTU/lbm). Thus steam delivered to the MSGTS will not impact the ability of the AF system to deliver water to the S/G.

Table [3] Steam Parameters for Case 1

Case 2 – For this case, steam is supplied to the MSTGS from the non-safety related ADV discharge line. However, for the existing design, the available steam pressure from this line is too low. Thus the APR1400 configuration is modified by placing an orifice in the ADV discharge line. This will increase pressure in the discharge line while the ADV is releasing steam which in turn will increase available energy to the MSTGS.

As a result of this configuration change, the inlet steam pressure to the MSTGS then equals the back- pressure which is produced from the orifice. However, the orifice will also increase backpressure on the ADV potentially impacting ADV flow capacity. To address this issue, analysis of required ADV capacity was performed.

Fig. 3 illustrates the required ADV steam flow coefficient as a function of back-pressure ratio (downstream pressure P2 divided by upstream pressure P1). There are three design basis conditions placed on the ADV flow capacity, (i) maximum flow,

(ii) minimum guaranteed flow, and (iii) controlling flow, from top curve to bottom curve, respectively. For all three conditions, the increase in steam flow coefficient from the current fully choked flow condition to the predicted backpressure for Case 2 is

~20%, within the capacity for the existing valve body.

Fig. 3 ADV Required Cv vs. Back-Pressure.

The parameters for available steam to power the microturbine for Case 2 are calculated after the initiation of the SBO accident in three time intervals shown in Table 4.

Table [4] Steam Parameters for Case 2

Microturbi ne

Steam Flow

Inlet Pressu re

Inlet Enthalp y

Inlet Entropy

Outlet Enthalp y Isentrop ic

Isentro pic Power

(lbm/hr)

(BTU/lb m)

(BTU/lb m-oF)

(BTU/lb m)

(10^3

BTU/hr)

3 hours

(10,000

sec)

142,00

0

91.65

254.47

10,000

85.20

1184

1.6157

1069.2

1,150

20,000

78.75

1183

1.6221

1073.6

2,184

30,000

72.29

1181

1.6290

1078.3

3,087

40,000

65.84

1179

1.6365

1083.4

3,839

50,000

59.38

1177

1.6448

1089.1

4,418

60,000

52.93

1175

1.6540

1095.4

4,790

70,000

46.47

1173

1.6645

1102.5

4,914

80,000

40.02

1170

1.6764

1110.6

4,730

27 hours (1 Day)

107,00

0

69.06

60

254.47

10,000

62.61

1178

1.6406

1086.2

922,

17,000

58.09

1177

1.6466

1090.3

1,474

24,000

53.57

1175

1.6531

1094.7

1,937

31,000

49.05

1174

1.6601

1099.5

2,300

38,000

44.54

1172

1.6679

1104.8

2,548

45,000

40.02

1170

1.6764

1110.6

2,660

52,000

35.50

1167

1.6860

1117.2

2,613

55 hours (2 days)

78,000

50.35

60

254.47

8,000

45.18

1172

1.6667

1104.0

544

12,000

42.60

1171

1.6714

1107.2

765

16,000

40.02

1170

1.6764

1110.6

946

20,000

37.44

1168

1.6818

1114.3

1,083

24,000

34.85

1167

1.6875

1118.2

1,173

28,000

32.27

1166

1.6937

1122.4

1,209

32,000

29.69

1164

1.7003

1126.9

1,184

In the output process using SE, the estimated power from the available steam for powering the microturbine for Cases 1 and 2 is presented in Tables 5 and 6, respectively.

Table [5] The DC Power Generated in Case 1

Time Intrval

Req'd Power

Req' Steam for 200 kWe

%

Available Steam

(BTU/hr = 200

kWe)

(lbm/hr)

(%)

3 hours (10,000 sec)

682,428

4,704

3%

27 hours1 (Day)

682,428

14,447

14%

55 hours (2 days)

682,428

14,447

19%

Table [6] The DC Power Generated in Case 2

Furthermore, MSTGS system specifications based on the requirements which had been developed early in this study and component specifications which are available in the commercial market are generated in Table 7. Fig. 4 and 5 illustrate the MSTGS conceptual design configurations for Cases 1 and 2, respectively

To ATMOSPHERE

MSTGS

Microturbine Steam Flow

Inlet Pressure

>2 bar

Isentropic Power

Isentropic Power

Generator Output

(lbm/hr)

(1 = TRUE)

(10^3

BTU/hr)

(kWe)

(kWe)

3 hours (10,000 sec)

10,000

1

1,150

337.1

202

20,000

1

2,184

640.2

384

30,000

1

3,087

904.8

543

40,000

1

3,839

1125.3

675

50,000

1

4,418

1294.8

777

60,000

1

4,790

1404.0

842

70,000

1

4,9141

1440.3

864

80,000

1

4,730

1386.3

832

27 hours (1 Day)

10,000

1

922,

270.4

162

17,000

1

1,474

432.1

259

24,000

1

1,937

567.9

341

31,000

1

2,300

674.2

405

38,000

1

2,548

746.8

448

45,000

1

2,660

779.8

468

52,000

1

2,613

765.8

459

55 hours (2 days)

8,000

1

544

159.7

96

12,000

1

765

224.2

135

16,000

1

946

277.3

166

20,000

1

1,083

317.6

191

24,000

1

1,173

343.9

206

28,000

1

1,209

354.4

213

32,000

1

1,184

347.1

208

Microturbine Steam Flow

Inlet Pressure

>2 bar

Isentropic Power

Isentropic Power

Generator Output

(lbm/hr)

(1 = TRUE)

(10^3

BTU/hr)

(kWe)

(kWe)

3 hours (10,000 sec)

10,000

1

1,150

337.1

202

20,000

1

2,184

640.2

384

30,000

1

3,087

904.8

543

40,000

1

3,839

1125.3

675

50,000

1

4,418

1294.8

777

60,000

1

4,790

1404.0

842

70,000

1

4,9141

1440.3

864

80,000

1

4,730

1386.3

832

27 hours (1 Day)

10,000

1

922,

270.4

162

17,000

1

1,474

432.1

259

24,000

1

1,937

567.9

341

31,000

1

2,300

674.2

405

38,000

1

2,548

746.8

448

45,000

1

2,660

779.8

468

52,000

1

2,613

765.8

459

55 hours (2 days)

8,000

1

544

159.7

96

12,000

1

765

224.2

135

16,000

1

946

277.3

166

20,000

1

1,083

317.6

191

24,000

1

1,173

343.9

206

28,000

1

1,209

354.4

213

32,000

1

1,184

347.1

208

From S/G

ADV MSSV MSIV

Fig. 4. Case 1 MSTGS Design Configuration.

To Turbine Building

To ATMOSPHERE

From MSIV Room

MSTGS

Fig. 5. Case 2 MSTGS Design Configuration

AFP

Table [7] MSTGS System Specifications.

System Specification

Comments

Full Load Power Output

550 kWe @ 480 V, 60 Hz, 3

Phase

  • 275 kWe/ micro turbine-generator unit

  • For micro turbine-generator exciting in the market

Standard Maximum Inlet Pressure

200 psig

  • A reduction steam valve is placed at the steam inlet

  • For micro turbine-generator exciting in the market

pipe.

Standard Minimum Discharge Pressure

2 psig

For micro turbine-generator exciting in the market

Steam Flow Rate

54,355 lb/h,

13,589 lb/h from each ADV

Dimension

34" x 42" x 78"

  • For each micro turbine-generator

  • Vertical Shaft

  • Similar specifications for micro turbine-generator

exciting in the market

Life time

60 years

The turbine generator units will be changed Every 15 years

ACKNOWLEDGEMENT

This research was supported by the 2016 research fund of the KEPCO International Nuclear Graduate School (KINGS), Republic of Korea.

CONCLUSION

The ability to maintain monitoring and control a nuclear unit under the challenging conditions associated with loss of all AC power is critical to successfully bringing the unit to a cold shutdown condition. As shown by recent events at Maanshan, Fukushima Daichi, and Fukushima Daini, unit status and shutdown actions cannot be adequately monitored without proper instrumentation. A key to maintaining proper instrumentation is a supply of reliable, continuous power to the buses which power the instruments.

Proposed here are two options which using available decay heat can provide an installed capability to maintain DC bus power for an extended period. The results of steam and decay heat calculations in this study have demonstrated that decay heat from the APR1400 can provide a sufficient amount of dumped steam for at least 55 hours from initiating the extended SBO accident. Two cases were developed. In Case 1, the MSTGS requires only 3-19% of the steam generated by decay heat to provide 200 kW of DC power. Case 2 results proved that generating the targeted DC power is also possible but for a somewhat shorted period. The MSTGS is the product of systems engineering approach in this research which is qualified to produce power enough to maintain charging the existing batteries for an extended period (more than 24 hours and as much as 60 hrs). This will provide sufficient power for instrumentation and control system loads, plant safety system DC loads, and emergency lighting under SBO of similar accident conditions.

REFERENCES

  1. Fukushima Nuclear Accident Analysis Report, Tokyo Electric Power Company, Inc. (2012)

  2. APR1400 Design Control Document, Tier 2, Chapter 6, Engineered Safety Features, Korea Electric Power Corporation (KEPCO) and Korea Hydro & Nuclear Power Co., Ltd. (KHNP)

  3. APR1400 Design Control Document, Tier 2, Chapter 19, Probabilistic Risk Assessment and Severe Accident Evaluation, Korea Electric Power Corporation (KEPCO) and Korea Hydro & Nuclear Power Co., Ltd. (KHNP)

  4. APR1400 Design Control Document, Tier 2, Chapter 6, Electric Power, Korea Electric Power Corporation (KEPCO) and Korea Hydro & Nuclear Power Co., Ltd. (KHNP)

  5. D.D. WALDEN, G.J. ROEDLER, K.J FARSBERG, R.D. HAMELIN, T.M. SHORTELL, INTERNATIONAL COUNCIL ON SYSTEMS ENGINEERING, Systems Engineering Handbook A Guide: A Guide for System Life Cycle Process and Activities 4th Edition,. Chapter 5, John Wiley &, Hoboken, New Jersey, (2015)

  6. Loss of All Alternating Current Power, U.S.NRC Regulation, Title 10 Code of Federal Regulations Part 50, Section 63

  7. JONGROK HWANG, Developing Optimal Procedure of Emergency Outside Cooling Water Injection for APR1400 Extended SBO Scenario Using MARS Code, Gyeongju, Korea, Transactions of the Korean Nuclear Society Autumn Meeting October 24-25, (2013)

  8. The Station Blackout Incident of the Maanshan NPP Unit 1, Atomic Energy Council Taiwan, R.O.C. (2001)

  9. DENNIS M. BUEDE, WILLIAM D. MILLER, The Engineering Design of Systems: Models and Methods 2nd Edition, Chapter 1, John Wiley &, Hoboken, New Jersey, (2009).

Leave a Reply