The Application of Statistical Package for the Social Sciences into Data Analysis to Identify and Evaluate the Risk Factors Influencing to the Implementation of the Renovation and Improvement National Highway 53, Tra Vinh – Long Toan Section, Tra Vinh Province, Vietnam

DOI : 10.17577/IJERTV10IS020011
Download Full-Text PDF Cite this Publication

Text Only Version

 

The Application of Statistical Package for the Social Sciences into Data Analysis to Identify and Evaluate the Risk Factors Influencing to the Implementation of the Renovation and Improvement National Highway 53, Tra Vinh – Long Toan Section, Tra Vinh Province, Vietnam

Anh Tuan Nguyen, Lecturer, PhD. Ho Chi Minh City University of Transport

2 Vo Oanh Street, Binh Thanh District, Ho Chi Minh City, Viet Nam.

Truong Vu Pham

Ho Chi Minh City University of Transport 2 Vo Oanh Street, Binh Thanh District, Ho Chi Minh City, Viet Nam.

Abstract – This article applies a descriptive statistical analysis method through the Statistical Package for the Social Sciences (SPSS) software based on the results of surveyors’ opinion through a questionnaire with The 5- level Likert scale of respondents to check the level of risks affecting the implementation of The Renovation and Improvement National Highway 53, Tra Vinh – Long Toan section, Tra Vinh Province Project in Vietnam. The research results show that the capacity of the Stakeholder including: Contractors, Sponsors and PMUs; and the price slippage are the risk factors that most affect the investment process. So the authors make recommendations to the Sponsors to develop a plan, study well the issues related to the capacity of contractor, sponsors and PMUs as well as the selection of contractors; promptly respond to macroeconomic fluctuations and instability that cause an increase in fuel and material price indexes. Sponsors, PMUs need to improve their management capacity, honesty and objectivity in project management, especially the selection of contractors so that their real capacity is appropriates their performance in the bids in order to minimize risk factors affecting the project investment implementation.

Keywords: Risk management; Descriptive statistical analysis, SPSS; Project Management Unit.

  1. INTRODUCTION

    Risks are situations that occur randomly, unforeseen when practical activities cause negative impacts on objects, subjects, things or phenomena, leaving reversible consequences but paying costly or irreversible such as fatal accidents.

    Construction risks are the risks occurring in the process of work construction investment from the stage of investment preparation, investment execution and investment completion. Risks in construction activities include all the one of delaying progress, low quality of the works, the construction costs

    rising above the total investment, traffic accidents, labor accidents and others.

    Risk management in construction investment activities is a set of processes, orders, procedures, methods and solutions that are mandatory conditions that participants must comply to avoid risks, treatment risks in best effectiveness.

    In fact, the process of investing in the construction of works, especially transport works contruction, always has potential risk factors causing unpredictable consequences such as: In serious sittuation, it will be deadly. For example, In the Can Tho bridge contruction project, due to lack of geographic research, the scaffoldings collapsed suddently while concreting the bridge deck, killing many people; poor quality of the work: Forr the highway of Da Nang – Quang Ngai section project, the work have just completed for one month but started damaging, leading to prosecution of the accuseds as well as the projects. If it is mild, it will make progress slowly, exceed the total cost. This risk level is common.

    To overcome this situation, we need to correctly identify the risk factors and properly assess the level of risk for each factor in order to develop a response plan to minimize the risk in construction investment activity.

    To determine the cause of a risk, first of all, we must identify the factors that cause risks in traffic construction investment activities, including:

    R1: Group of risk factors related to project characteristics such as: Natural topographic characteristics and project characteristics, long survey time, prolonged bidding time, Inaccurate survey. Because it is a road traffic project, stretching along as route, through many different geological regions, topographical and geological surveys require the true reflection of the nature, representing each area to meet the task requirements. new approved survey has suitable design solution. Do not accept the value of interpolation and prediction survey. Therefore, the survey time is longer than construction works with more concentrated scope. Due to the very large volume of the transport industry, divided into many

    bidding packages, the bidding packages cannot be completed at the same time from design to verification, evaluation and approval. So, when completing designing approval any package, the Investor will auction that package. This stage should last a long time. If these causes occur, consequences are serious such as: Poor construction quality, death, delayed progress, exceeding the cost total. If the survey is inaccurate, It must be adjusted and supplemented.

    R2: Group of risk factors related to the capacity of stakeholders such as: The design and estimate Unit; Investor; PMU; the verification Unit. If the capacities of these subjects fail to meet the requirements, it will endanger the work’s quality, death, wrong order, procedures, delay, and total investment.

    R3: Group of risk factors specific to traffic works: Difficulty in site clearance; works stretching in wide area, causing difficulties in management and construction organization; the coordination between consultancy units. Road traffic works require construction ground with a large and prolonged occupation area, so site clearance is time consuming, difficult and complicated; construction management needs to be scientific to promote construction efficiency, to avoid loss of properties and materials; the coordination between consulting units, especially supervision consultants, verification consultants, design consultants, regularly and continuously. Failure to perform these factors will cause delay, exceeding the total investment, prolonged complaints, and unsatisfactory quality of the work.

    R4: Group of risk factors involved in the design process: Changing design drawings; Time for designing and estimating; Time for designed and estimated verifying. These factors cause the risk of delayed progress, unsatisfactory design quality require additional adjustments which makes construction costs increase.

    R5: Group of risk factors related to economics and legal policy: Financial resources of the investor; Domestic financial market; Regular legal policy changes; The guiding documents are not specific. This is a group of objective factors that happen with a very low frequency. However, if it

    standard (for plain section), the design speed is 80km/h according to TCVN 4054-2005 with the following parameters: Cross section Bn/Bm = 12m /11m; High-grade asphalt concrete pavement A1, only for high-grade plastic straightening and smoothing sections A2; Modulus Eyc 140Mpa.

    The bridge section consists of 5 repaired bridges, 2 renewed bridges, of which Bang Da, Phuoc Hao, Tra Cuong 1, Tra Cuong 2 and O Lak bridges proceed to dismantle balustrades and different – level sidewalks to expand the vehicle lane up to 9m, turning into 10m for total of bridge width; Nhi Trung and Lo Da bridge has been newly built with a bridge width of 12m, with vehicle lane Bmc = 11m, the barrier and handrail lane Bgc = 2×0.5m = 1.0m. the bridge is built permarnently of reinforced concrete and prestressed reinforced concrete.

    Surveying the current situation, determining the risk factors, th risk factors affecting the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project from experts’ opinions. Analysis and ranking of the found risks and model construction aims to further study the nature of risk factors in construction investment, to improve project management qualifications; to understand more of the viewpoint of experts on risk factors in transport construction investment; to practice proficiently in SPSS software to apply in work.

  2. RESEARCHING METHOD
  1. Introduction to research method

    Apply descriptive statistical methods to statistic and analyze opinions of experts working in relevant agencies and units on the risk factors affecting The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. This method uses SPSS software to perform frequency statistics and description. The research steps are shown in Figure 1.

    Research implementation process

    happens, it will have a great impact on the success of the project, the project may have to delay, postpone or bankrupt, for example: In 2011, to stabilize the macro economy, the Government. issued Resolution No. 11/2011/NQ-CP on reducing equitable investment by suspending and rescheduling a series of projects. Considering the current economic context, this group of factors does not affect The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project due to the identified and arranged capital as well as The project has deployed 70% of the volume.

    R6: The group of risk factors is related to the price slippage factors that cause excess investment: the price of fuel,

    RESEARCH METHOD

    Survey questionnaire Data collecting

    Research tools

    Conclusions and reccomendation

    materials, labor and machine increase. This group of factors occurs often, most of the projects are affected by the group of price slippage factors due to the increase of the material price index causing the increase in construction costs.

    The project to renovate and upgrade NH.53, Tra Vinh – Long Toan section, Tra Vinh province with a total length of 43,800 km, was invested and built in the areas of Chau Thanh, Cau Ngang and Duyen Hai districts, Tra Vinh province. The project road is designed according to The III level road design

    Figure 1. Diagram of research process according to SPSS method

  2. Method content
    1. Detailed research implementation process

      (2) Research

      target (1) Research

      (5) Preliminary

      1. Bidding time prolongs.
      2. The survey result is not accurate
        • Group of risk factors related to the capacity of stakeholders
      3. Capacity of the designing and estimating unit
      4. Capacity of Investor or PMU.
      5. Capacity of constructor.
        1. Theoretical basic
        2. Draft scale

      research:

      – Group decussion

      – Group of risk factors that are specific to traffic work contruction

      (8) Difficulty of site clearance

      1. Official research

        (7) Official scale

        (6) Correction

      2. Construction organization
      3. Asset management
      4. Appropriate to local contruction planning

      (9) Cronbach alpha

      (9.1) Remove the variables with small total variable correlation

      (9.2) Checking cronbach alpha index

      (12) The coordination between consultants

      – Group of risk factors involved in the design process:

      (13) Change of design drawing

      (10) Descriptive statistical analysis

      (11) Conclude

      (10.1) Descriptive statistics of the survey object

      (10.2) Descriptive statistics by groups and aggregates

      1. Time of designing and cost estimating
      2. Time of design and cost estimate verification

        – Group of risk factors related to economics and legal policy

      3. Investor’s financial resources
      4. Financial capacity of contractor
      5. Frequent legal policy changes
      6. The guiding documents are not specific

        Figure 2. Research implementation process

    2. Research model

      Risks affecting the project implementation

      1. Policy on construction investment
        • Group of risk factors related to cost increasing
      2. Increased fuel prices
      3. Material price increases
      4. Labor cost increases
      5. Prices of construction machine and equipment increase.

      b) Group of dependent factors: There is an independent group of risk factors and 01 observed variable. Therefore, the observed variable is also a research and evaluation factor: Risks affecting the implementation of investment The Renovation and Improvement NH.53, Tra Vinh – Long Toan

      Group of risk factors related to characteristics of the project (Cha)

      Group of risk factors related to the capacity of stakeholders (Cap)

      Group of risk factors related to the specifics of the trasport construction (Spe)

      Group of risk factors related to survey and design (Sur)

      Group of risk factors related to economics and legal policy (Eco)

      Group of risk factors related to cost increasing (Inc)

      section, Tra Vinh Province Project 3.3. Data collection

      a) Scale

      In the survey questionnaire, the five-level Likert scale of the respondents will be used to examine the impact of risks affecting the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. The Likert scale shows 5 levels from 1 = “No effect” to 5 = “Very much impact”.

      Infulence level
      Non – Influence Little Influence Medium Influence Quite Influence Enormous Influence
      (1) (2) (3) (4) (5)
      Infulence level
      Non – Influence Little Influence Medium Influence Quite Influence Enormous Influence
      (1) (2) (3) (4) (5)

       

      TABLE I. FIVE LEVELS LIKERT TABLE

      Figure 3. Research method

    3. Survey questionnaire content

      The survey questionnaire is designed as shown in Appendix 1.

      1. Qualitative factor group Includes: Gender, Age, Education, Experience, Agency.
      2. Quantitative factor group
  1. Group of independent factors: There are 06 independent groups of risk factors and 24 observed variables for these 06 groups of risk factors as follows:
    • Group of risk factors related to project characteristics
    1. Natural topographical features and project characteristics.
    2. Survey time prolongs.
  2. Research tools:
    • Sample size: Objects which surveyed consist of the subjects related to the surveyed content.
    • About sample size:
    • Analysis of discovery factors EFA:

      + According to Hair et al. (1998), the sample size is> 100 units;

      + On the other hand, according to Comrey (1973), the minimum sample size is 5 times to the total number of observed variables. This is a suitable sample size for research using factor analysis. Therefore, the sample size should be n>

      = 5 * m, m is the number of questions in the survey. The

      research topic has 24 observed variables (24 questions) for groups of independent factors. So the sample size needed is: 5 * 24 = 120 samples

      with:

      a = Np1 + p (N 1)

      + p is the average correlation coefficient between the

      – For multivriate regression analysis:

      + According to Tabachnick and Fidell (1996): The minimum sample size to achieve is calculated by the formula as n> = 50 + 8 * m (m: number of independent variables). Research topic has 06 independent variables. So the sample size needed is: 50 + 8 * 6 = 98 samples.

      Thus, to choose a sample that satisfies the conditions for EFA test and multivariate regression analysis when choosing the number of samples must satisfy all three conditions above. The team decided to take a sample size of 120 samples to increase the value of the study.

  3. Survey Questionnaire coding:

    Questions entering the SPSS software are encoded as shown in Appendix 2.

  4. Data processing tools:

    After issuing the survey questionnaire, the results will be collected, then the collected data and the coded variables will be imported into SPSS 20 Software (Statistical Package for the Social Sciences 20) – a software that is widely used on computers and it is used for scientific, social and econometric research. SPSS is also used as an optimal tool for parametric analysis, correlation analysis, scale reliability testing, …

  5. Descriptive statistics

    Descriptive statistics is a technique that helps researchers to describe generally the characteristics of research samples and survey results obtained. Descriptive statistics will include: Frequencies statistics and average statistics. Sample information includes gender, age, work experience, position, education level. The study uses a tool to calculate the average value (mean), the maximum value (maximum) and the minimum (minimum). At the same time, fully synthesizing the sample information such as quantity, calculating percentage, cumulative percent.

  6. Methods of analyzing reliability for Cronbanch’s Alpha Index.
    • The reliability of the scale is assessed by the method of intrinsic consistency through Cronbach’s Alpha coefficient. Use Cronbach’s Alpha’s confidence coefficient method before analyzing EFA factors to eliminate unsuitable variables because these variables can create dummy factors (Nguyen Dinh Tho & Nguyen Thi Mai Trang, 2009). Confidence Cronbach’s Alpha’s coefficients only indicate whether measurements are linked; but does not show which observed variables to remove and which observed variables to keep. Then, the calculation of the variable-sum correlation coefficient will help to eliminate which observed variables do not contribute much to the description of the concept to be measured (Hoang Trong & Chu Nguyen Mong Ngoc, 2005).

      Criteria to use when evaluating the reliability of the scale:

    • Types of observed variables with small variable-total correlation coefficient (less than 0.3); criteria for selecting the scale when the alpha reliability is greater than 0.6 (the larger the alpha, the higher the internal consistency reliability) (Nunally & Burnstein 1994; cited by Nguyen Dinh Tho & Nguyen Thi Mai Trang, 2009).

      Cronbach’s Alpha coefficient formula is:

      questions. Greek characters p in the formula represents the mean correlation between all pairs of questions is checked.

      + By convention, coefficient is greater than or equal to 0.8, a set of questions used to measure is evaluated well.

      • Values for evaluating Cronbach’s alpha coefficients: (Nunally, 1978; Peterson, 1994; Slater, 1995; cited by Hoang Trong and Chu Nguyen Mong Ngoc, 2005).

        + From 0.8 to close to 1: The scale is very good. + From 0.7 to almost equal to 0.8: The scale is fine.

        + From 0.6 or more: Scale qualified.

      • The observed variables with small variable-total correlation (less than 0.3) are considered garbage variables, they will be eliminated and the scale is accepted when the confidence coefficient Alpha is satisfactory (greater than 0.6). (Nguyen & Nguyen, 2009).

III. DATA ANALYSIS AND RESEARCH RESULTS

  1. Analyze evaluation results
    1. Description of survey object information

      After issuing survey forms (directly and indirectly), 120 valid votes were collected. All samples after being tested are satisfactory because there is no sample with a defective answer, the answer is not wrong with the question. A sample of 120 was entered into SPSS software for the study.

      The survey sample information includes: Gender, age, professional qualifications, work experience and fields of work in the transport construction industry.

      Male

      Female

      Male

      Female

       

        1. Gender statistics

          GENDER

          10; 8%

          110;

          92%

          GENDER

          10; 8%

          110;

          92%

          Figure 4. Gender statistic

          Based on the above survey results, it can be seen that, with a total of 120 questionnaires collected, the rate “gender” is:

          Female accounted for 8.33% with 10 votes. Male accounted for 91.67% with 110 votes

        2. Statistics on the age of the surveyed person
          1. Based on the above survey results, it can be seen that, with a total of 120 questionnaires collected, the rate of Age is:
          2. Under 30 years old accounts for 14.17% with 17 votes.
          3. From 30 to 40 years old accounts for 35% with 42 votes.
          4. From 41 years old to 50 years old, accounts for 46.66% with 56 votes.
          5. Over 50 years old accounts for 4.17% with 5 votes.
          6. Thus, the survey samples mostly show that most of the respondents at the age from 30 to 50 years old are working in the transport construction industry.

          Figure 5. Age stastitic

        3. Statistics of the surveyed people’s qualifications

          Figure 6. Education background

          Based on the above survey results, it can be seen that, with a total of 120 questionnaires collected, the rate of “Educational attainment” is:

          College accounts for 5.83% with 7 votes. University accounts for 91.67% with 110 votes Postgraduate level 2.5% with 3 votes

          Thus, the majority of survey samples show that most of the surveyed subjects have university degree, no one has intermediate degree.

        4. Statistics of the surveyed’s work experience

          Work experience

          28; 23%

          60; 50%

          32; 27%

          Work experience

          28; 23%

          60; 50%

          32; 27%

          Under 5 years

          T 5 nm n 10 nm

          Trên 10 nm

          Under 5 years

          T 5 nm n 10 nm

          Trên 10 nm

           

          Figure 7. Work experience

          Based on the above survey results, it can be seen that, with a total of 120 collected survey forms, the rate of “Work experience” is:

          Under 5 years accounted for 23.33% with 28 votes,

          From 5 years to 10 years accounted for 26.67% with 32 votes,

          Over 10 years accounted for 50% with 60 votes.

          Thus, the majority of survey samples show that the majority of respondents have more than 10 years of experience.

          Sponsor PMU

          Design consultant

          Supervision consultant

          Contractor

          Sponsor PMU

          Design consultant

          Supervision consultant

          Contractor

           

          6; 5%

          20; 15%

          6; 5%

          20; 15%

           

        5. Statistics of the surveyed person’s work agency

      Work agency

      Work agency

       

      40; 31%

      40; 31%

       

      18; 14%

      18; 14%

       

      46; 35%

      46; 35%

       

      Figure 8. Work agency

      Based on the above survey results, it can be seen that, with a total of 120 questionnaires collected, the rate of “Working Unit” is:

      Investor accounts for 33.33% with 40 votes,

      Project management board accounted for 38.33% with 46 votes.

      Design Consulting accounted for 15% with 18 votes,

      Supervision Consultant accounted for 8.33% with 10 votes. Contractors accounted for 5% with 6 votes.

      Thus, the survey samples mostly show that most of the surveyed subjects are working at the Investor and Project Management Boad 7, who directly invest in the project.

  2. General information about the object to be surveyed

    Information of surveyed subjects is summarized in Table 2. TABLE II. OVERVIEW OF SUBJECTS TO BE SURVED

    INFORMATION SAMPES Sample mass Percent (%) Cumulative percent (%)
    Gender (C1) Male 110 91,67 91,67
    Female 10 8,33 100
    Age (C2) Under 30 17 14,17 14,17
    30 up to 40 42 35 49,17
    41 up to 50 56 46,66 95,83
    Over 50 5 4,17 100
    Education background

    (C3)

    College 7 5,83 5,83
    University 110 91,67 91,67
    Post graduate 3 2,5 100
    Work experience (C4) Under 5 years 28 23,33 23,33
    5 up to 10 years 32 26,67 50
    Over 10 years 60 50 100
    Work agency (C5) Sponsor 40 33,33 40
    PMU 46 38,33 71,66
    Design consultant 18 15 86,66
    Supervision consultant 20 8,33 95
    Contractor 6 5 100
  3. Test the model

    Cronbach’s Alpha’s test of scales

    Test the reliability of the scale Cronbach’s Alpha is to test the reliability scale of a observed variables set that can also be measured, showing the properties of the “parent factor”. This tool will help to check whether the observed variables of the “parent factor” (factor A) are reliable or not. This test reflects the degree of close correlation between observed variables in the same factor. It shows the observed variables in the same factor, which variables contributed to the measurement of the concept of factors, which variables did not.

    Factors that need to be verified include (1) Group of risk factors related to project characteristics (Cha); (2) Group of risk factors related to the capacity of stakeholders (Cap);

    1. Risk factors are specific to the traffic construction industry (Spe); (4) Group of risk factors related to the design process (Des); (5) Group of risk factors related to economics and legal policy (Pol); (6) Group of risk factors related to cost increasing (Inc).

    Figure 9. Chart of Cronbach’s Alpha Index of factor groups

    TABLE III. RISK FACTORS

    Group of risk factors Cronbach’s Alpha N of Items
    Project characteristics 0,,823 4
    Capacity of stakeholders 0,866 3
    Traffic construction characteristics 0,859 5
    Involved in the design process 0,815 3
    Economics and legal policy 0,877 5
    Cost increasing 0,885 4

    Factors with total variable correlation coefficients of greater than 0.3 should not be excluded (Nunally & Burnstein 1994; cited by Nguyen Dinh Tho & Nguyen Thi Mai Trang, 2009). Therefore, all of these 4 research variables on the reliability scale. Cronbach’s Alpha will be further analyzed in other contents.

  4. Descriptive Statistics
    1. Descriptive statistics by group of factors

      * Group of risk factors related to project characteristics The average value of the observed variables from Cha1 to Cha4 in the group of risk factors related to the project’s characteristics are in the range from 2.5 to less than 4 on the 5 point Likert scale. Thus, more than half of the respondents who responded to the survey agreed with the criteria in the group of risk factors related to the project’s characteristics.

      Average values of Cha1 to Cha4 are not much different and are in the range from 2.5 to 3.5 on a 5-point scale. This shows that these risk factors have impacts on the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. However, just above average.

      N Min Max Mean Std.

      Deviation

      Cha1 120 1,00 4,00 2,55 0,672
      Cha2 120 2,00 4,00 2,57 0,645
      Cha3 120 2,00 5,00 3,42 0,668
      Cha4 120 2,00 5,00 2,69 0,754
      Valid N (listwise) 120
      N Min Max Mean Std.

      Deviation

      Cha1 120 1,00 4,00 2,55 0,672
      Cha2 120 2,00 4,00 2,57 0,645
      Cha3 120 2,00 5,00 3,42 0,668
      Cha4 120 2,00 5,00 2,69 0,754
      Valid N (listwise) 120

       

      TABLE IV. STATISTICS DESCRIPTION OF RISK RELATED TO PROJECT CHARACTERISTICS

      * Group of risk factors related to the capacity of stakeholders:

      The average value of observed variables from Cap1 to Cap3 in the group of risk factors related to the capacity of stakeholders are in the range from 4.42 to 4.47 on the 5-point Likert scale. Thus, most of the survey responses agreed with the criteria of stakeholder capacity significantly affecting the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. The average values of Cap1 to Cap3 are not much different from each other and are in the range from 4.4 on a 5-point scale. This suggests that these risk factors have approximately the same degree of impact.

      TABLE V. STATISTICS DESCRIBUTING RISK RELATED TO THE PERFORMANCE OF PARTIES

      N Min Max Mean Std.

      Deviation

      Cap1 120 3,00 5,00 4,43 0,603
      Cha2 120 3,00 5,00 4,42 0,512
      Cha3 120 3,00 5,00 4,47 0,517
      Valid N (listwise) 120

      * Group of risk factors that are specific to the traffic construction industry

      The average value of the observed variables from (1 to Spe 5 in the group of risk factors related to the specifics of the traffic construction industry ranged from 2.30 to 4.02 on the 5-point Likert scale. Thus, about half of the survey responses agree with the criteria specific to the transport construction industry affecting the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. The average value of Spe1 to Spe5 is not much different and lies in the range from 2.3 to 4.02 on a 5-point scale. This suggests that these risk factors have varying degrees of impact.

      TABLE VI. STATISTICS DESCRIPTION OF RISK OF TRAFFIC CONTRUCTION INDUSTRY CHARACTERISTIC

      N Min Max Mean Std.

      Deviation

      Spe1 120 3,00 5,00 4,02 0,809
      Spe2 120 2,00 5,00 3,20 0,729
      Spe3 120 2,00 5,00 3,13 0,681
      Spe4 120 2,00 5,00 3,07 0,676
      Spe5 120 1,00 4,00 2,03 0,669
      Valid N (listwise) 120
      • Group of risk factors related to the design process

        TABLE VII. STATISTICS DESCRIPTION OF RISK RELATED TO THE DESIGN ESTABLISHMENT

        N Min Max Mean Std.

        Deviation

        Des1 120 2,00 3,00 2,15 0,359
        Des2 120 2,00 3,00 2,05 0,219
        Des3 120 2,00 3,00 2,05 0,219
        Valid N (listwise) 120

        Average value of observed variables from Des1 to Des3 in the group of risk factors related to the design process is from

        2.05 to 2.15 on the 5-point Likert scale. Thus, less than half of the respondents who answered the survey agreed with the criteria in the group of risk factors related to design. The average values of Des1 to Des3 are not much different and are in the range from 2.05 to 2.15 on a 5-point scale. This shows that these risk factors have impacts on the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project. However, just below average.

      • Group of risk factors related to economics and legal policy Average values of observed variables from Pol1 to Pol5 in the group of risk factors related to economics and legal policy ranged from 2.96 to 4.17 on the 5 point Likert scale. Thus, most of the respondents who answered the survey agree with the criteria in the group of risk factors related to economics and legal policies. The average values of Pol1 to Pol4 are not much different and are in the range from 3.24 to 4.17, while Pol5 has a value of 2.96 slightly lower than other factors on the 5 point scale. This shows that these risk factors have a relatively large impact on The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project.

        TABLE VIII. STATISTICS DESCRIPTION OF ECONOMIC RISK AND LEGAL POLICY

        N Min Max Mean Std.

        Deviation

        Pol1 120 3,00 5,00 4,17 0,760
        Pol2 120 3,00 5,00 3,68 0,552
        Pol3 120 3,00 5,00 3,68 0,552
        Pol4 120 2,00 5,00 3,24 0,550
        Pol5 120 1,00 4,00 2,96 0,585
        Valid N (listwise) 120
      • Group of risk factors is related to slippage factors

      Average values of observed variables from Inc1 to Inc4 in the group of risk factors related to slippage are in the range from 3.84 to 4.47 on the 5-point Likert scale. Thus, most of the survey responses agreed with the criteria of stakeholder capacity significantly affecting the implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan

      Inc2 120 2 5 4.22 .822
      Inc3 120 3 5 4.21 .721
      Inc4 120 2 5 3.84 .722
      Valid N (listwise) 120
      Inc2 120 2 5 4.22 .822
      Inc3 120 3 5 4.21 .721
      Inc4 120 2 5 3.84 .722
      Valid N (listwise) 120

       

      section, Tra Vinh Province Project. The average values of Cap1 to Cap3 are not much different from each other and are in the range of 4.22 on the 5-point scale. This suggests that these risk factors have approximately the same degree of impact.

      TABLE IX. STATISTICS DESCRIBUTING THE RISK RELATED TO THE EXCHANGE FACTORS

      N Min Max Mean Std. Deviation
      Inc1 120 3,00 5,00 4,47 0,660
      Inc2 120 2,00 5,00 4,22 0,822
      Inc3 120 3,00 5,00 4,21 0,721
      Inc4 120 2,00 5,00 3,84 0,722
      Valid N (listwise) 120
      N Min Max Mean Std. Deviation
      Inc1 120 3,00 5,00 4,47 0,660
      Inc2 120 2,00 5,00 4,22 0,822
      Inc3 120 3,00 5,00 4,21 0,721
      Inc4 120 2,00 5,00 3,84 0,722
      Valid N (listwise) 120

       

    2. General descriptive statistics

      Average values of 24 observed variables of risk factors affecting the real implementation of The Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh province are in the score from 2 , 55 to 4.47 on the 5- point Likert scale, only 2 observed variables have the value 2.05.

      N Min Max Mean Std.

      Deviation

      Cha1 120 1 4 2.55 .672
      Cha2 120 2 4 2.57 .645
      Cha3 120 2 5 3.42 .668
      Cha4 120 2 5 2.69 .754
      Cpa1 120 3 5 4.43 .603
      Cap2 120 3 5 4.42 .512
      Cap3 120 3 5 4.47 .517
      Spe1 120 3 5 4.02 .809
      Spe2 120 2 5 3.20 .729
      Spe3 120 2 5 3.13 .681
      Spe4 120 2 5 3.07 .676
      Spe5 120 1 4 2.30 .669
      Des1 120 2 3 2.15 .359
      Des2 120 2 3 2.05 .219
      Des3 120 2 3 2.05 .219
      Pol1 120 3 5 4.17 .760
      Pol2 120 3 5 3.68 .552
      Pol3 120 3 5 3.68 .552
      Pol4 120 2 5 3.24 .550
      Pol5 120 1 4 2.96 .585
      Inc1 120 3 5 4.47 .660
      N Min Max Mean Std.

      Deviation

      Cha1 120 1 4 2.55 .672
      Cha2 120 2 4 2.57 .645
      Cha3 120 2 5 3.42 .668
      Cha4 120 2 5 2.69 .754
      Cpa1 120 3 5 4.43 .603
      Cap2 120 3 5 4.42 .512
      Cap3 120 3 5 4.47 .517
      Spe1 120 3 5 4.02 .809
      Spe2 120 2 5 3.20 .729
      Spe3 120 2 5 3.13 .681
      Spe4 120 2 5 3.07 .676
      Spe5 120 1 4 2.30 .669
      Des1 120 2 3 2.15 .359
      Des2 120 2 3 2.05 .219
      Des3 120 2 3 2.05 .219
      Pol1 120 3 5 4.17 .760
      Pol2 120 3 5 3.68 .552
      Pol3 120 3 5 3.68 .552
      Pol4 120 2 5 3.24 .550
      Pol5 120 1 4 2.96 .585
      Inc1 120 3 5 4.47 .660

       

      TABLE X. DESCRIPTION STATISTICS SUMMARY OF RISK FACTORS

      IV. CONCLUSIONS AND RECOMMENDATIONS

      In the current stable economic conditions (although affected by the COVID -19 translation), most of the survey responses agree with the criteria of the group of risk factors. Risks affecting the implementation of Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province Project are as follows:

      • The factor of NL3 in construction contractor’s capacity and TG1 – fuel price slippage (due to COVID -19 epidemic affecting world oil prices) has the highest average value of
          1. This shows that most of the responses agree that given the fully equitized state-owned transport construction state- owned enterprises, the capacity of privately owned joint stock companies is no longer available. keep the capacity, experience and tradition of operation, construction management in association with professional ethics as before. Hence, it caused a decrease in confidence among industry experts. This survey results reflect the concerns of industry experts about the contractor’s capacity to have a great impact on the risks in project construction investment. Regarding the factor that Inc1 is fuel price slippage, many experts worry that the Covid-19 pandemic could cause fluctuations in gasoline prices to the point where it is difficult to control, so the majority of respondents agree that this is a risk factor that greatly affects. most to the project implementation process.
      • Next, the observed variable Cap2, Investor’s capacity and PMU average value of 4.42 also significantly affect the project investment implementation process.
      • The time of design and cost estimation by the factor of Des2, time for design verification and estimate is equal to the average value of Des3 and by 2.05 as the lowest value in the description table. This shows that, in the context of the current design and verification consulting capacity, the references that these two factors also affect the level of risk in project implementation but at the below average, not insignificant.

With the above results, making recommendations to the Investor to develop a plan, study well the issues related to the capacity of the contractor, the capacity of the investor and the PMU in the selection of contractors; promptly respond to macroeconomic fluctuations and instability that cause an increase in fuel and material price indexes. The solution is that the Investor, the PMU needs to improve their management capacity, honesty and objectivity in project management, especially the selection of contractors so that their capacity is really suitable. evaluation capacity according to the bidding documents in order to minimize the risk factors affecting the investment implementation of Renovation and Improvement NH.53, Tra Vinh – Long Toan section, Tra Vinh Province.

Regarding the factor of fuel price slippage, it is recommended that the Investor need to reserve a budget to compensate for the contractor to avoid exceeding the total investment in case the world oil price fluctuates strongly due to the Covid pandemic – 19.

In addition, it is necessary to carefully consider other factors that have a relatively large impact on the risk level of the Project in order to have appropriate response measures.

REFERENCES

      1. Curriculum Analysis of Research Data with SPSS by Hoang Trong and Chu Nguyen Mong Ngoc.
      2. Documents related to the formation and development process of Project Management Unit 7 – Ministry of Transport.
      3. The project of investment, construction, renovation and upgrading of NH.53, section Km67 + 000 – Km114 + 000 in Tra Vinh province was approved by the Minister of Transport in Decision No. 3046 / QD-BGTVT dated October 20, 2009 .
      4. The adjusted profile of NH.53 Improvement and Upgrading Project, Tra Vinh – Long Toan section, Tra Vinh province approved by the Minister of Transport in Decision No. 2818 / QD-BGTVT dated December 26, 2018.
      5. Nunnally, J.C. and Bernstein, I.H. (1994) The Assessment of Reliability. Psychometric Theory, 3, 248-292.
      6. Peterson, R. A. (1994). A Meta-Analysis of Cronbachs Coefficient Alpha. Journal of Consumer Research, 21, 381-391. http://dx.doi.org/10.1086/209405
      7. Nunnally, J.C. (1978) Psychometric theory. 2nd Edition, McGraw- Hill, New York.
      8. Slater, S. (1995). Issues in Conducting Marketing Strategy Research. Journal of Strategic Marketing, 3(4), 257-270.
      9. Hoang Trong and Chu Nguyen Mong Ngoc (2005), Data Analysis by SPSS, Statistical Publisher.

APPENDIX 1. SURVEY QUESTIONNAIRE PART I. PERSONAL INFORMATION

  1. Your gender:
    • Male (1) Female (2)
  2. Your age:
    • Under 30 years old (1) 30 40 years old (2)
    • 41 – 50 years old (3) Over 50 years old (4)
  3. Your education background:
    • Highschool (1) University (4)
    • Intermediate (2) Postgraduate (5)
    • College (3)
  4. Your major experience:
    • Under 5 years (1) 5 10 years (2)
    • Over 10 years (3)
  5. Your major:
  • Contractor (1) Supevisor (4)
  • Sponsor (2) PMU (5)
  • Design consultant (3)

PART II. QUESTIONNAIRE

Would you please tell us the influence of the factors listed below on the factors that affect the implementation of the NH.53 Improvement and Upgrading Project, Tra Vinh – Long Toan, Tra Vinh Province .

Check the box containing the corresponding numbers:

  1. Non influence, (2) Very little influence, (3) Medium influence, (4) Big influence, (5) Great influence.
    No. Influe-nt factors Your coments
    Non – influen-ce Very little influence Med. influen- ce Big influe- nce Great influe- nce
    (1) (2) (3) (4) (5)
    1 Group of risk factors related to project characteristics (Cha)
    Natural topographic al features and project characteristi cs.
    Survey time prolongs
    Bidding time prolongs
    The survey result is not accurate
    2 Group of risk factors related to the capacity of stakeholders (Cap)
    Capacity of the designing and estimating unit
    Capacity of

    Investor or PMU.

    Capacity of construct-or
    3 Group of risk factors that are specific to traffic work contruction (Spe)
    Difficulty of site clearance
    Construc-tion organizati-on
    Asset managem-ent
    Appropriate to local

    contructo-n planning

    The coordinati-on between consultants
    4 Group of risk factors involved in the design process (Des)
    Change of design drawing
    Time of designing and cost estimating
    Time of

    design and cost estimate verificatio-n

    5 Group of risk factors related to economics and legal policy (Pol)
    Investor’s financial resources
    Financial capacity of contractor
    Frequent legal policy changes
    The guiding document-s are not

    specific

    Policy on constructio-n investment
    6 Group of risk factors related to cost increasing (Inc)
    Increased fuel prices
    Material price increases
    Labor cost increases
    Prices of contructio-n machine and equipment increase

    PART III. EVALUATE

    1. In your opinion, are there any different factors effecting to this project, apart from the above ones, in

fact?

………………………………………………………………………………………

.

……………………………………………………………………………………..

  1. With the factors that you just mentioned, if you face in reality, what solutions do you have to overcome?

    ………………………………………………………………………………………

    .

    ………………………………………………………………………………………

    .

    In case of need, you can contact me via email at Vpt1975@gmail.com

    Thank you very much for taking the time to answer the question!

    APPENDIX 2. CODING THE SURVEY QUESTIONS

    • Group of qualitative factors:

– Gender:

Observed variables Coding
Male 1
Female 2

– Ae:

  • Education background :
    Observed variables Coding
    Highschool 1
    Intermediate 2
    College 3
    University 4
    Post graduate 5
  • Work experience :
    Observed variables Coding
    Under 5 years 1
    5 up to 10 years 2
    Over 10 years 3
  • Work agency:
Observed variables Coding
Contractor 1
Sponsor 2
Design consultant 3
Supervision consultant 4
PMU 5
N

o

Variables coding Factor group
A QUALITATIVE FACTORS
C1 Gender
C2 Age
C3 Education background
C4 Work experience
C5 Agency
B QUANTITATIVE FACTORS
INDEPENDENT VARIABLES
1 Cha Group of risk factors related to project characteristics (Cha)
Cha1 Natural topographical features and project characteristics
Cha2 Survey time prolongs
Cha3 Bidding time prolongs
Cha4 The survey result is not accurate
2 Cpa Group of risk factors related to the capacity of stakeholders (Cap)
Cap1 Capacity of the designing and estimating unit
Cap2 Capacity of Investor or PMU.
Cap3 Capacity of constructor
3 Spe Risk factors are specific to the traffic construction industry (Spe)
Spe1 Difficulty of site clearance
Spe2 Construc-tion organization
Spe3 Asset management
Spe4 Appropriate to local contructon planning
Spe5 The coordinati-on between consultants
N

o

Variables coding Factor group
A QUALITATIVE FACTORS
C1 Gender
C2 Age
C3 Education background
C4 Work experience
C5 Agency
B QUANTITATIVE FACTORS
INDEPENDENT VARIABLES
1 Cha Group of risk factors related to project characteristics (Cha)
Cha1 Natural topographical features and project characteristics
Cha2 Survey time prolongs
Cha3 Bidding time prolongs
Cha4 The survey result is not accurate
2 Cpa Group of risk factors related to the capacity of stakeholders (Cap)
Cap1 Capacity of the designing and estimating unit
Cap2 Capacity of Investor or PMU.
Cap3 Capacity of constructor
3 Spe Risk factors are specific to the traffic construction industry (Spe)
Spe1 Difficulty of site clearance
Spe2 Construc-tion organization
Spe3 Asset management
Spe4 Appropriate to local contructon planning
Spe5 The coordinati-on between consultants

 

* GROUP OF QUANTITATIVE FACTORS

Observed variables Coding
Under 30 1
30 up to 40 2
41 up to 50 3
Over 50 4
4 Des Group of risk factors related to the design process (Des)
TK1 Change of design drawing
TK2 Time of designing and cost estimating
Des3 Time of design and cost estimate verification
5 Pol Group of risk factors related to economics and legal policy (Pol)
Pol1 Investor’s financial resources
Pol2 Financial capacity of contractor
Pol3 Frequent legal policy changes
Pol4 The guiding documents are not specific
Pol5 Policy on construction investment
6 Inc Group of risk factors related to cost increasing (Inc)
Inc1 Increased fuel prices
Inc2 Material price increases
Inc3 Labor cost increases
Inc4 Prices of contruction machine and equipment increase
DEPENDENT VARIABLE
7 Y Risks affecting the implementation of the renovating and upgrading NH.53 from Tra Vinh – Long Toan, Tra Vinh Province project.