Planning and Scheduling of College Building by using Primavera P6

DOI : 10.17577/IJERTCONV10IS10031

Download Full-Text PDF Cite this Publication

Text Only Version

Planning and Scheduling of College Building by using Primavera P6

1Veerabhadragouda P Patil, 2Sushma R K,

Assistant professor Department of Civil Engineering

R.R Institute of technology Bangalore 560090

3Bikesh Bhattarai, 4Mukesh Kumar,

5Chandra Bhusan Mahato, 6Md Imran Ansari

U.G Students, Department of Civil Engineering

    1. Institute of technology Bangalore 560090

      Abstract – For Successful Completion of Project, Planning and Scheduling are two most important factors. Due to the increase in Workloads and Shrinking resources Construction Work Department Found New Technology Which helps to Manage the Project easily. With the help of Primavera P6 Software proper planning and scheduling can be done. Prima vera can easily compare between the planned progress of construction work and actual progress of construction project. In this study, G+5 college Building Plan is drafted in AutoCAD and estimate the building material quantity and scheduling and controlling the project by primavera p6 .

      Keywords – Planning, Scheduling, Primavera p6

      1. IINTRODUCTION

        A project is composed of jobs, activities, functions or tasks that are related one to the other in some manner, and all of these should be completed in one order to complete the project. Project management involves three phases: project planning, project scheduling, project controlling. For the completion of project to basic things are material resources and manpower resources. The basic element of project network is event and activity. The commencement or completion of an activity is called an event. An activity is the actual performance of the task. Oracle primavera p6 is also known as EPPM which is abbreviated as enterprise project portfolio management. It is also the most powerful strong and easy handling software and used solution for worldwide, Organizing, planning, managing, and execute project, programs and portfolios. Primavera P6 software helps to achieve the maximum return on investments in project and progress. Primavera P6 gives a single solution for multi projects of any size. Primavera can handle the projects of large size according the persons need.

      2. LITERATURE REVIEW:

        [1]Planning, Analysis & Construction Controlling of G+5 Building by Using Primavera.

        The main objective of this project is to analyses and to construction scheduling of an apartment building (G+5) using STAAD Pro and Primavera P6 software. First of all, the planning is done using Auto CAD and code refered for this project is IS 456-2000. The first and foremost thing which we can get by effectively planning in primavera is start date on

        01 July 2019 and finishing date of 27 Dec 2022 project. Primavera P6 helps in effectively scheduling the project by assigning two relationships at a time to each activity and considerably reduces the float. All the important steps like creating an EPS, creating a WBS, linking of activities

        according to their interdependence and availability of resources and determination of critical path are clearly exhibited in this report. Budgeted cost, time, and materials of the project are obtained by resource allocation.

        [2] Project Management of in Construction using primavera (August 2017)

        For the successful completion of a project, planning and scheduling are two most important factors. The demand of construction industry requires a precise planning, scheduling and management which can allow the overall optimization of the cost, time and resources. Due to the increase in workloads and shrinking resources public work department found new technology which helps to manage the project easily. Project management software is used as a tool for managing and organizing work which helps industries to grow in a rapid manner. There are so many computers software are available in market now a days which is such as MSP, Primavera p6, etc..for doing project management. With the help for this software proper planning and controlling of project can be done. Primavera can easily compare between the planned progresses of construction work and actual progress of Construction project. Project management software Primavera P6, include collecting, recording, monitoring, controlling and reporting information concerning project perform.

        [3] Planning and Scheduling of High-Rise Building Using Primavera (June 2014)

        Although the long-introduced Industrialized Building System (IBS) has promised to solve and improve the current construction method and scenario in our country, but the IBS method has not gained enough popularity. One of the reasons is due to lack of research works done to quantifying the benefit of IBS especially in construction time saving. In lieu with such scenario, this study conducted to quantify evidence of time saving in IBS application. The methodology adopted for this study is by modelling the construction process for high-rise residential building for both conventional and IBS with shared more a less the same nature and size of the structure. The model was developed using Primavera(P3) project planning software. The comparison was made by comparing selective building components for both method of construction. Different high-rise residential projects have been selected for this study. The result of the study clearly indicated that sufficient time saving can be archived.

      3. OBJECTIVE OF WORK

        1. For planning and scheduling of the construction of

          college building.

        2. To control the project time.

        3. For creating strategies, controlled the delay of the project

      4. METHODOLOGY

  1. Auto cad planning and drafting

  2. Estimation using excel sheet

  3. Planning and scheduling using primavera p6.

    1. Case Study

      The project site that was taken for our project is in Bangalore. With the help of plans and other structural drawings the estimation work was carried out.

      Sl.no

      Name Of the Work

      Construction of college Building Bangalore

      1

      NO Of Floors

      Basement, G+5

      2a

      Basement

      1768.00 sqm.

      2b

      Ground Floor

      1768.00 sqm

      2c

      GroundFloor to Fifth floor

      1768.00 sqm. (Each floor)

      3a

      Basement provided

      Laboratory, store room, open area Principal room, chairman room, Board room, library etc.

      3b

      Ground floor

      Principal room, chairman room,

      Board

      room, library etc.

      3c

      First floor to fifth floor

      Basic-science Department, Civil department,

      CSE Department, ISE Department, Auditorium

      4

      Staircase

      1-nos

      5

      Lifts

      1-nos

      Salient Features of the project

      Table -1

    2. Planning By Using Auto CAD

      CAD drawings means detailed and accurate computer-aided design drawings to illustrate the design.

      Fig:1(a)-Basement

      Fig :1(b)-Ground Floor

      Fig:1(c)-First Floor(Basic Science Department)

      Fig :1(d)-Second Floor (Civil Department)

      • ESTIMATION:

        Estimation is the scientific way of working out the approximate cost of an engineering project before execution f the work. We have done the estimation to take take off quantities of structural elements using Microsoft Excel.

      • Steps involve in controlling and monitoring

i. Creating EPS:

The project contains a set of different activities and associated information that constitutes a plan for creating a product or service. The project is created under respective divisions in EPS.

Fig:2(a)- Creating EPS

  1. Creating project:

    The project contains a set of different activities and a s s o c i a t e d information that constitutes a plan for creating a product or service. The project is created under respective divisions in EPS.

    Fig:2(b) -Creating New Project

  2. Creating calendar:

    Calendars enable you to define available workdays and work

    hours in a day.

    Fig:2(c)- Creating Calendar

  3. Work breakdown structure:

    WBS elements have defined and organize the project elements.

    Fig:2(d)- Work breakdown structure

  4. Defining activity

Activities are the basic work elements of a project.

Fig:2(f)- Gantt chart

  1. Units of measures:

    User-Defined Fields (UDFs) enable you to add an unlimited number of custom fields and values to the project database.Resource UDFs enable you to create a custom unit of measure, so you can track critical items.

    Fig :2(g) -Units of Measure

    • Scheduling in primavera p6

Scheduling of activities for basement and ground floor.

vi) Gantt chart

Fig:2(e)- DefiningActivity

Fig:2(h)- Activities and dates

A graphic display of schedule related information listing project elements on left side of the chart. Date across the top and activity duration are shown as date placed horizontal bars. It is also known as Bar Chart.

  • RESULTS

The results we got from estimation are- Estimation of quantity (for basement and ground floor).

Table -2

Sl.no

Particulars

Quantity

units

1

Excavation

6451.59

m3

2

Footing

468.64

m3

3

Column up to plinth

27.89

m3

4

Plinth Beam

93.68

m3

5

Footing steel

58.58

tonne

Basement Floor

SI.NO

Description

Start

Finish

Original Duration

1

college Building

5-Sep-21

1-Mar-23

393

2

Preconstruc tion

5-Sep-21

31-Mar-22

151

3

Project start

05-Sep-21

6-Sep-21

1

4

Architecture Design

6-Sep-21

6-Jan-22

90

5

Basic survey

7-Sep-21

15-Sep-21

7

6

Soil investigation

7-Sep-21

15-Sep-21

7

7

Structural Design

07-Jan-22

17-Feb-22

30

8

Mep Design

18-Feb-22

31-Mar-22

30

9

Allocation of contract

18-Feb-22

31-Mar-22

30

10

Initiation

1-Apr-22

19-Apr-22

13

11

machinery mobilization

01-Apr-22

11-Apr-22

7

12

site boundary fixation

01-Apr-22

5-Apr-22

3

13

temporary connection of electrical

06-Apr-22

11-Apr-22

4

14

Engineering office and labor

12-Apr-22

14-Apr-22

3

15

Survey work for constructions

15-Apr-22

19-Apr-22

3

16

Substructure

20-Apr-22

18-May-22

21

17

marking

20-Apr-22

22-Apr-22

3

18

excavation

22-Apr-22

27-Apr-22

4

19

foundation

28-Apr-22

6-May-22

7

20

ssm

08-May-22

17-May-22

7

21

Backfilling

12-May-22

16-May-22

3

22

dpc

17-May-22

18-May-22

2

Basement

24

Structure

6-May-22

18-Jul-22

53

25

column concreting

06-May-22

2-Jun-22

20

26

wall construction

08-May-22

15-Jul-22

50

Table-3

Sl.no

Particulars

Quantity

units

1

column

79.68

m3

2

Beam

93.68

m3

3

Slab

352

m3

4

Column steel

8.07

tonne

5

Beam steel

14.05

tonne

6

Slab steel

44

tonne

7

Stair case

3.78

m3

8

Stair case steel

0.47

tonne

9

Wall

175.28

m3

10

Plastering

2191.2

m2

11

Painting

2191.2

m2

12

Cladding

82.80

m2

Wooden work

13

Main Door

12

No

Door(Toilet)

10

No

Ventilation

4

No

16

Windows

40

No

Ground Floor

Sl.no

Particulars

Quantity

units

1

column

79.68

m3

2

Beam

93.68

m3

3

Slab

352

m3

4

Column steel

8.07

tonne

5

Beam steel

14.05

tonne

6

Slab steel

44

tone

7

Stair case

3.78

m3

8

Stair case steel

0.47

tone

9

Wall

214.34

m3

10

Plastering

2489.6

m2

11

Painting

2489.6

m2

12

Cladding

82.80

m2

Wooden work

13

Main Door (teak wood)

13

No

14

Door (Toilet)(pvc)

13

No

15

Ventlation

4

No

16

windows

40

No

17

Inner door

1

No

Table-4

  • Activities Start & Finish Date

Table-5

SI. NO

Description

Start

Finish

Original Duration

27

lintel beam

21-Jun-22

4-Jul-22

10

28

beam and slab work

05-Jul-22

18-Jul-22

10

29

Ground Floor

30

Structure

19-Jul-22

29-Sep-22

54

31

column concreting

19-Jul-22

15-Aug-22

20

32

wall construction

21-Jul-22

28-Sep-22

50

33

lintel beam

02-Sep-22

15-Sep-22

10

34

beam and slab work

16-Sep-22

29-Sep-22

10

35

MEP

Basement and Structure

28-Apr-22

3-Nov-22

138

36

lift casing

28-Apr-22

29-Jun-22

45

37

electrical transmission wire

30-Sep-22

6-Oct-22

5

38

electrical conduicts

30-Sep-22

6-Oct-22

5

39

gasline, sewage line

30-Sep-22

6-Oct-22

5

40

OHT

30-Sep-22

13-Oct-22

10

41

water proofing

06-Oct-22

12-Oct-22

5

42

plumbing fixture

13-Oct-22

28-Oct-22

12

43

connection to water supply and gas line

30-Oct-22

3-Nov-22

4

44

Finishing (Basement)

4-Nov-22

30-Dec-22

42

45

plastering

04-Nov-22

1-Dec-22

20

46

painting

01-Dec-22

9-Dec-22

7

47

flooring

11-Dec-22

23-Dec-22

10

48

HVAC

25-Dec-22

27-Dec-22

2

49

fire fighting

28-Dec-22

29-Dec-22

2

50

cctv

29-Dec-22

30-Dec-22

2

51

Finishing (Ground floor)

1-Jan-23

1-Mar-23

44

52

plastering

01-Jan-23

27-Jan-23

20

53

painting

29-Jan-23

7-Feb-23

7

54

flooring

08-Feb-23

21-Feb-23

10

55

HVAC

22-Feb-23

23-Feb-23

2

56

fire fighting

24-Feb-23

27-Feb-23

2

57

cctv

28-Feb-23

1-Mar-23

2

58

Infrastructure

4-Nov-22

23-Dec-22

36

59

landscaping

04-Nov-22

24-Nov-22

15

60

infra road

25-Nov-22

23-Dec-22

21

Fig-3

Fig-4

Fig-5

CONCLUSION:

  1. The quantities of different elements like footing, beam, column etc can be estimated by using estimation methods like center line or long wall – short wall method and using excel format to tabulate estimated result efficiently.

  2. The planning, scheduling and monitoring of the start and end dates of activities can be done for the project using primavera. The duration for the completion of the project be from 5-sep-2021 to 1-mar-2023.

  3. Project management Technique helps in forecasting the project duration before starting any activity of the construction. Such that it helps to use the time efficiently and overcome any further delays in the project.

  4. Hence using modern tools like primavera over conventional method help in planning, scheduling, tracking and monitoring the constructional activities efficiently.

REFRENCES:

[1] Planning, Analysis & Construction Controlling of G+5 Building by Using Primavera, (23 August 2021) Mr. S. V. Siva Raju, SK. Nagar Basha, SK. Mohammad Abubakr, G. Venkata Ramakrishna4, Gopanaboina Jhansi Bhuvaneswari, Vasavada Man gamma

[2] Project Management of in Construction using primavera

(August 2017) Himanshu, Khushpreet Singh, Uma Malik

[3] Planning and Scheduling of High-Rise Building Using Primavera (June 2014) T. Subramani1, A. Sarkunam2, J.

Jayalakshmi3

[4] DR. B.C. PUNMIA AND K.K.KHANDELWAL PROJECT PLANNING AND

CONTROL WITH PERT AND CPM4TH EDITION 2002.