Engineering Marvel: Pouring 7858 Cum of M40 Grade Concrete in Blast Furnace Proper Raft in 36 HR

DOI : 10.17577/IJERTV13IS050192

Download Full-Text PDF Cite this Publication

Text Only Version

Engineering Marvel: Pouring 7858 Cum of M40 Grade Concrete in Blast Furnace Proper Raft in 36 HR

Sandhyarani Sahoo

M Tech in Construction Technology Management Gandhi Institute for Technology, Bhubaneswar, Odisha, India

Abhijit Mangaraj

Assistant Professor, Department of Civil Engineering Gandhi Institute for Technology, Bhubaneswar, Odisha, India

Abstract Industrial construction projects involve time, economy as well as high production output considerations. In this study, an approach to determine a time-optimized solution for speedy construction using a genetic algorithm for a blast furnace proper raft is used to achieve the milestone provided by client. An objective function is formulated for minimizing the reinforced cement concrete (RCC) work duration, subject to certain constraints, ensuring the practicality and safety of the construction. The solution provides the usage of temperature- controlled concrete which reduces the RCC work duration and safe construction. It is found from the study that a well coordination between planning, execution, fleet, resources, supply chain management team have resulted a successful record of achieving 7858 cum of concreting within 36 hours with ensuing all the safety and quality parameters, and thus ensure speedy construction. It is also observed that the M40 grade of temperature concrete provides an acceptable combination for speedy construction with due consideration of safety.

Keywords Temperature controlled concrete, Speed of construction, Pour plan.

  1. INTRODUCTION

    A Blast furnace is a construction designed to convert iron oxide into pure, molten iron through the application of heat and the presence of flux and coke. The furnace itself is a tall stack, often constructed from steel. Raft is an important parameter for the blast furnace operator to judge the thermal state of the hearth. It determines the initial gas temperature of the hearth, thus affecting the heat transfer, reduction, slagging, desulfurization, hot metal temperature, composition, etc. Project is an organized unit dedicated to the attainment of a goal- the successful completion of a developed project on time, within budget, in conformance with pre-determined program specifications. It can be defined as a temporary endeavor which is designed to achieve a set of goals such as a product or service which has a definite beginning and end and is typically undertaken to obtain some benefit or to add value. Recent advancements have made it possible to now undertake complex and technologically intense projects.

  2. LITERATURE REVIEW

    Temperature differences can cause stress that leads to thermal cracks, as well as loss of structural integrity, thus shortening the life and decreasing the strength of the mass concrete element. If the temperature goes below a certain number, the

    hydration of water can slow or stop meaning the concrete wont set properly and wont achieve optimal strength. When temperatures are properly monitored, it allows for appropriate adjustments to be made. Therefore, temperature Controlled concrete is prepared by weight & is designed.

    A paper states that selecting proper construction equipment is a challenging task in the construction industry due to the broad array of available equipment in the market and many criteria required to be considered during decision making.

    A model was developed to address the difficulties experienced during the multifaceted process. The example illustrates how an AHP-based model helps address the multitude of qualitative, intangible factors, both among the factors themselves and then vis-a-vis costs, by means of a systematic and traceable process. The method enables project managers, and their equipment selection teams to exercise their knowledge, intuition, and professional judgment, and at the same time to address the context and specifics of the projects under examination.

    A paper reviews the existing research and finds that automation and robotics, innovations, research and developments of newer techniques, prefabricated and modular constructions and use of information technology in this sector are getting popular day by day and conventional construction methods because of their limitations of time consumption and slow progress are becoming out of fashion.

    A detailed literature study was carried out to understand the causes of accidents, preventive measures, and development of safe work environment. This paper presents the results of a questionnaire survey, which was distributed among various categories of construction workers.

    The Study of Supply Chain Management Strategy and Practices on Supply Chain Performance stated the relationship between supply chain management strategy and chain management practices on supply chain performance.

  3. ACTION PLAN

    1. Project Execution Plan

      A Project Execution Plan (PEP) is a crucial document that provides a roadmap for project managers, sponsors, and teams to ensure successful project delivery.

    2. Logistic Plan

      The circumference of the location has been divided into four approaches, two are for entry purpose and two are for exit purpose. This approach is identified that there will be no overtaking of equipment during transportation.

    3. Crew Distribution

      The entire team has been divided into 3 crew in three shifts since we have the target to complete the pouring un 36 hours.

    4. Resource Mobilization Plan

      • The allocation, mobilization, and deployment of 3M resources of the project i.e. Manpower, Machinery and material have been planned with optimization technique followed by safety and quality parameters.

    5. Quality Plan

      • Initial Setting Time-7:40 Hour

      • Final Setting Time-10:39 Hour

      • There was a no. of check lists which are adopted at site to ensure quality at every step for this mega pour.

      • Admixture Used-CICO Plast Super C-711

      • Design Mix of M40 grade was finalized as Cement: Fine aggregate: Coarse aggregate=1:1.501:2.625 with Water: Cement ratio of 0.36 and admixture dose of 0.5 %. The slump cone was found out to be 130 mm to 180 mm. The target strength achieved after 28 days was 48.93 N/mm2

    6. Pour Plan

      • Pouring Time at site was 45 Min.

      • The concrete temperature was maintained at 24 0c using 420 MT of ice.

      • The thickness of each layer was maintained to be 450 mm.

      • The concrete quantity per layer of casting was 804 Cum.

      • Batching plant production was 1222 Cum in 7 hr by considering 65% productivity.

  4. RESULTS

      • With proper planning and execution, the mega pour was successfully achieved 7858 cum within 36 hours.

      • Zero Fatality as with optimum quality standard.

      • The total revenue generated against this structure was

    5,38,86,724.29.

  5. CONCLUSION

    The construction of any civil structure with s subject to industrial based is a very risky, costly, and time-consuming process. A proper coordination of all the 3M i.e manpower, machinery and material make a project less risky, cost effective within safety limit.

    A milestone in a project can be achieved with the help of teamwork. In a construction project the team leader is basically a planner. Use of new effective techniques with reference to the construction project plays an important role. With the achievement of milestones, we must give equal attention towards safety and quality parameters also.

    During my time spent on this marvelous project, I came to know about all the well co-ordination between different

    departments and cost effectiveness of speedy industrial construction.

  6. ACKNOWLEDGMENT

    First, I would like to express my sense of appreciation to my supervisor Prof. Abhijit Mangaraj for his consistent support and guidance for my research. This work would not have been completed without his technical comment, patience, and understanding.

    Our head of the department Prof. Surajit Patnaik was a constant source of inspiration, and his guidance was like a blessing to us. I dedicate this work to all the lecturers and support staff of the Dept. of Civil Engineering for their concern, constant support, and guidance in making us who we are today.

  7. REFERENCES

  1. Srinil Soni1, Vasav Rakholia2, Temperature Controlled Concrete,

    2018.

  2. I. Temiz and G. Calis*Ege University, Department of Civil Engineering, 35100 Bornova, Izmir, Turkey Selection of Construction Equipment by Using Multi-criteria,2017.

  3. Aviad Shapira Systematic Evaluation of Construction Equipment Alternatives: Case Study, 2017.

  4. Bilal Ahmad, Pushpendra Kumar Sharma PG Scholar, SCE, Lovely Professional University. Modern and Conventional Construction Methods.,2020.

  5. Daniel Jato-Espino a, Elena Castillo-Lopez b, Jorge Rodriguez- Hernandez a, Juan Carlos Canteras-Jordana, A review of application of multi-criteria decision-making methods in construction,2014.

  6. S. Kanchana,1 P. Sivaprakash,2 and Sebastian Josepp, Labour Safety in Construction Sites.,2015.

  7. Bent Flybjerg Quality Control and Due Diligence in Project Management: Getting Decisions Right by Taking the Outside View.,2013.

  8. Abu Bakar Hamid, Rohaizat Baharun, Rosman Md Yusoff ,The Study

of Supply Chain Management Strategy and Practices ,2012.