Time Standardization For Building Maintenance Tasks
Mr. Nikhil A. Shete 1 and Prof. Dhananjay S. Patil 2
1-PG Student, Department of Civil Engineering,
2-Associate Professor, Department of Civil Engineering, Rajarambapu Institute of Technology,Rajaramnagar, Islampur, Dist. Sangli, Maharashtra, India
Abstract
Its natural that the construction facility starts deteriorating from the time it has constructed. Maintaining the constructed facilities is the call of the how and should be given first preference than constructing new. In order to maintain a building the owner should know the expenses which might occur for maintenance task, Labour cost demanded for maintenance has large impact on the budget of owner, So in order to have guidelines for budgeting provision this work has been undertaken to studying the standard time required, based on cost also can be calculated. The result shows the variation in labour cost.
Keywords- Labour Cost, Maintenance task, Standard Time, Work Measurement,
-
Introduction
Time is very important resource in any of construction work and how long a job should take must be known to plan that job. Here we are using the work measurement techniques to know prior the standard time of the maintenance jobs. Maintenance jobs are different from the regular construction jobs. They require skilled workforce to indentify the problem and take correct action to repair it. Basically the cost problems are more in maintenance works as it differs from the original works. Here we have found out the standard times for some of the frequently occurring maintenance tasks. From those standard times we have found out labour cost required to do the work. In the maintenance industry there is lack of standards about time requirement of the particular maintenance job. So work is undertaken to find out the standard time require for maintenance jobs. This can be helpful while planning and managing the maintenance works. If we
know the work breakdown structure of the maintenance job we can plan and execute the jobs in well manner. So we decided to apply the work measurement technique to find out the standard time requirement of maintenance jobs.
Work measurement is the application of techniques designed to establish the time for a qualified worker to carry out a task at defined rate of working. Work measurement as name suggests provides management with a means of measuring the time taken in performance of an operator or series of operations in such a way that the ineffective time is shown up and can be separated from effective time.
Building and services are under the maintenance phase for 95% of its life from concept to demolition. So maintenance can be defined as maintenance is synonymous with controlling the condition of a building including its services so that the serviceability remains within specified region of acceptability. Building maintenance is actually a process by which a building is kept usable at a pre-determined standard for the use and benefit of its occupants or users.
-
Methodology
General Building Maintenance
General Building Maintenance
Defects in Parts
Defects in Service Installation
Water Leakages
Selection of Maintenance Job
Selection of Maintenance Job
Work Breakdown Structure of Job
Work Breakdown Structure of Job
Video Shooting of Maintenance Job on Site
Video Shooting of Maintenance Job on Site
Analysis of Videotape
Analysis of Videotape
Finding the time required for each activity
Finding the time required for each activity
Standardization of the Time for Maintenance Job
Standardization of the Time for Maintenance Job
-
Selecting the Task-In this process the Building is divided into three parts as stated above, like defects in building parts, defects in building services installations and problems of water leakages. According to this we contacted the concerned professionals who are working in the field of building maintenance and repairs. The maintenance sites were found out and Data collection work was done.
-
Taking the labour and site supervisor into confidence and explaining them about objectives of study.
-
Collect the required data on site with the video camera. From the start to end video recording of the tasks is done.
-
Work break down structure of the each task is done. Time required to complete it is found from analysis of video.
-
Work measurement analysis of task is done to find out standard time of each task.
-
-
Work measurement Analysis
3.1. Standard Time-The standard time for the particular task is the sum of the standard times for all the elements of which it is made up. It is the total time in which a job should be completed at standard performance. Standard Time is unit value for the accomplishment of work task as determined by proper application of appropriate work measurement technique.
= +
-
Allowances-Allowance is the amount of time added to the normal time to provide for personal delays, fatigue of the worker. Allowances when added to the normal time, it results in standard time. The fundamental purpose of allowances is to add enough time to the normal time to enable the average worker to meet the standard when performing at a normal pace. Total Allowance allocated as follows
-
Personal allowance -5%
-
Fatigue allowance -15%
-
Safety Protective dress 10%
-
Tediousness + Mental strain -10%
-
-
Rating System- When collecting the data we observe carefully the performance of the worker during the entire course of time. Performance rating or Rating is a technique for equitably calculating the time required to perform a task by the normal operator after the observed value of the operation under study have been recorded. The rating factor is used to convert observed time into basic time.
For this work measurement analysis work we used the 0-100 standard rating scale has been adopted as the British Standard. In the 0-100 scale, 0 represents zero activity and 100 the normal rate of working of the motivated qualified worker that is standard rate.
TABLE 1
0-100 STANDARD RATING SCALE
Scale 0-100
Standard
Description
0
No Activity
50
Very slow no interest in job
75
Steady, deliberate unhurried performance of the worker.
100
(Standard Rating)
Brisk, businesslike performance with quality and accuracy.
125
Very fast with a degree of assurance dexterity and coordination of movement.
150
Exceptionally fast, requires intense effort and concentration, cannot be kept long periods.
Referring to the 0-100 Standard Rating Scale,
100represents standard performance
= ×
100
Sample Calculation of standard Time for activity
in task Repair of Malfunction of waterproofing, Leakage for sample A
WBS
activities
Start time
End time
Observe d time
For1m
2
Breaking of
0:01:0
1:29:5
1:28:53
0:53:1
waterproofin
0
3
8
g coat
Time given in (HH:MM:SS) format
Rating given for this activity is 75 on rating scale So basic Time =0:53:18*75/100
=0:39:58
After taking the average three samples namely Sample A, Sample B, Sample C Average Basic Time is calculated and it is given in table for this task
So Average of Basic Time for Breaking of waterproofing coat =0:43:44
After Addition of Allowances to Basic Time we get the Standard time for the particular activity of the task. The Standard Time for the particular task is the sum of the standard times for all the activities of which it is made up.
-
-
DATABASE OF STANDARD TIME FOR TASKS UNDER STUDY
-
Task- External Plaster Pebble Type
Unit of Measurement=Square Meters
TABLE 2
STANDARD TIME FOR EXTERNAL PEBBLE TYPE PLASTER
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Breaking
0:03:51
0:05:23
Bond Coat
0:00:28
0:00:39
Dash Coat
0:01:40
0:02:20
First Coat
0:01:13
0:01:42
Leveling & filling spots
0:02:01
0:02:49
Second Coat
0:02:44
0:03:50
Total Time
0:16:43
16 Minutes 43 Seconds
Labour Cost required for External Plaster Pebble Type of 1m2
Assuming the transportation for each labour is 5 Km distance. Time required for this distance is 12minutes.So that time is also added for the cost calculations with their respective rate.
TABLE 3
LABOUR COST FOR EXTERNAL PEBBLE TYPE
Type of labour
On Site Rate (8Hours)
Rate according to DSR (8 Hours)
Cost for 1m2 onsite rates
Cost for 1m2 DSR
rate
Skilled Labour
Plasterer
500
311
24.15
15.08
Breaker
350
270
12.57
2.92
Semiskilled
300
270
17.76
15.99
Unskilled
200
270
11.84
15.99
66.34
49.99
66 Rs.
50Rs.
Actual Labour Rate on site for External Plaster Pebble Type of 1m2 =70Rs.
-
Task- Micro-concrete for repairs of beam for problems of bulging, falling off of concrete from beam with reinforcement exposed
Unit of Measurement= Running meter Size of beam 230mm X 400mm
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Breaking of waterproofing coat
0:43:44
1:01:13
Breaking of slab cover
0:58:11
1:21:28
Cleaning of area
0:21:25
0:29:59
Aggregate spreading
0:08:52
0:12:25
Fixing sockets
0:18:41
0:26:09
Grouting
0:08:06
0:11:20
Cleaning of area
0:16:29
0:23:05
Waterproofing coating
0:06:40
0:09:20
Dash coat
0:02:20
0:03:16
Filling with concrete
0:06:07
0:08:34
Finishing work
0:11:41
0:16:21
Total Time
4:43:12
4 Hours 43
Minutes 12 Seconds
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Breaking of waterproofing coat
0:43:44
1:01:13
Breaking of slab cover
0:58:11
1:21:28
Cleaning of area
0:21:25
0:29:59
Aggregate spreading
0:08:52
0:12:25
Fixing sockets
0:18:41
0:26:09
Grouting
0:08:06
0:11:20
Cleaning of area
0:16:29
0:23:05
Waterproofing coating
0:06:40
0:09:20
Dash coat
0:02:20
0:03:16
Filling with concrete
0:06:07
0:08:34
Finishing work
0:11:41
0:16:21
Total Time
4:43:12
4 Hours 43
Minutes 12 Seconds
TABLE 4
STANDARD TIME FOR MICRO CONCRETE FOR REPAIRS OF
BEAM
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Rust Kill Coat & Bond Coat
0:01:57
0:02:44
Fixing necessary reinforcement
0:21:58
0:30:45
Fixing the shuttering
0:13:13
0:18:30
Filling the POP
0:05:04
0:07:06
Micro concrete filling
0:16:28
0:23:03
Removing shuttering
0:03:29
0:04:53
Total Time
1:27:01
1Hour 27Minutes 1Second
Labour Cost required for Micro-concrete for repairs of beam 1m
TABLE 5
LABOUR COST FOR MICRO-CONCRETE FOR REPAIRS OF
BEAM
Type of labour
On Site Rate (8 Hours)
Rate according to DSR (8 Hours)
Cost for 1m onsite rates
Cost for 1m DSR
rate
Skilled Labour
Bar bender
450
270
42.45
25.47
Carpenter
450
311
35.02
24.20
Semiskilled
300
270
21.89
19.70
Unskilled
200
266
37.08
49.20
136.46
118.59
136 Rs.
119
Rs.
Type of labour
On Site Rate (8 Hours)
Rate according to DSR (8 Hours)
Cost for 1m onsite rates
Cost for 1m DSR
rate
Skilled Labour
Bar bender
450
270
42.45
25.47
Carpenter
450
311
35.02
24.20
Semiskilled
300
270
21.89
19.70
Unskilled
200
266
37.08
49.20
136.46
118.59
136 Rs.
119
Rs.
Labour Cost required for Repair of Malfunction of waterproofing, Leakage 1m2
TABLE 7
Type of labour
On Site Rate (8
Hours)
Rate according to DSR (8 Hours)
Cost for 1m2 onsite rates
Cost for 1 m2 DSR
rate
Skilled Labour
Leakage worker/ Mason
320
311
196.93
191.19
Semiskilled
200
270
110.67
166.00
307.60
357.19
307Rs.
357Rs.
Type of labour
On Site Rate (8
Hours)
Rate according to DSR (8 Hours)
Cost for 1m2 onsite rates
Cost for 1 m2 DSR
rate
Skilled Labour
Leakage worker/ Mason
320
311
196.93
191.19
Semiskilled
200
270
110.67
166.00
307.60
357.19
307Rs.
357Rs.
LABOUR COST FOR REPAIR OF MALFUNCTION OF WATERPROOFING, LEAKAGE
Actual Labour Rate on site for Micro-concrete for repairs of Beam 1m = 170 Rs.
-
Task- Repair of Malfunction of waterproofing, Leakage
Unit of Measurement=Square Meters
TABLE 6
STANDARD TIME FOR REPAIR OF MALFUNCTION OF WATERPROOFING, LEAKAGE
Actual Labour Rate on site for Repair of Malfunction of waterproofing, Leakage 1m2 =320 Rs.
-
Task- Polymer modified mortar for repairs &patching of spalling surfaces of slab
Unit of Measurement=Square Meters
TABLE 8
STANDARD TIME FOR POLYMER MODIFIED MORTAR FOR REPAIRS
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Fixing the necessary steel
0:14:20
0:20:04
Bond coat
0:01:25
0:01:59
Dash coat
0:06:55
0:09:40
Hand placing of PMM
0:17:24
0:24:22
Total Time
0:56:05
56 Minutes 5Seconds
Labour Cost required for Polymer modified mortar for repairs &patching of spalling surfaces of slab 1m2
TABLE 9
LABOUR COST FOR POLYMER MODIFIED MORTAR FOR REPAIRS
Type of labour
On Site Rate (8
Hours)
Rate according to DSR (8 Hours)
Cost for 1 m2 onsite rates
Cost for 1m2 DSR
rate
Skilled Labour
PMM
labour
550
311
55.00
31.10
Bar Bender
450
270
30.03
18.02
Semi skilled
300
270
42.66
38.39
127.70
87.52
128 Rs.
88 Rs.
Actual Labour Rate on site for Repair of Polymer modified mortar for repairs &patching of spalling surfaces of slab 1m2 =130 Rs.
-
Task- External wall paint work Unit of Measurement=Square Meters
TABLE 10
STANDARD TIME FOR EXTERNAL WALL PAINT WORK
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Surface cleaning
0:00:14
0:00:20
Crack finding,spliting
0:00:34
0:00:48
Crack filling
0:01:43
0:02:24
Applying Primer
0:03:11
0:04:27
Applying paint coat 1
0:02:50
0:03:58
Paint Coating to windows
0:00:48
0:01:07
Applying paint coat 2
0:02:44
0:03:50
Total Time
0:16:54
16 Minutes 54 Seconds
Labour Cost required for External wall paint work 1m2
TABLE 11
Labour Cost for External wall paint work
Type of labour
On Site Rate (8 Hours)
Rate according to DSR (8 Hours)
Cost for 1m2 onsite rates
Cost for 1m2 DSR
rate
Skilled labour
Painter
450
277
26.75
16.46
Unskilled
200
266
11.89
15.69
38.64
32.16
40 Rs.
32 Rs.
Actual Labour Rate on site for Repair of External wall paint work 1m2 =45 Rs
-
Task- External Sand faced Plaster Unit of Measurement=Square Meters
TABLE 12
STANDARD TIME FOR EXTERNAL SAND FACED PLASTER
WBS Activities
Basic Time (HH:MM:SS)
Standard Time (HH:MM:SS)
Breaking
0:03:51
0:05:46
Bond Coat
0:00:13
0:00:20
Dash Coat
0:02:00
0:03:00
First Coat
0:04:49
0:07:13
Leveling & Filling spots for first coat
0:04:09
0:06:14
Second coat
0:01:25
0:02:08
Leveling & Filling spots for Second coat
0:04:19
0:06:28
Application of sprung
0:03:18
0:04:57
Total Time
0:36:06
36 Minutes 06 Seconds
Labour Cost required for External Sand faced Plaster 1m2
-
-
RESULTS
The results show the Standard time for six maintenance tasks. Basic times for tasks are calculated from the observed time. Addition of allowances to the basic time gives the Standard time for the tasks. Standard Times are calculated for the unit of 1m2or 1m
TABLE 13
LABOUR COST FOR EXTERNAL SAND FACED PLASTER
Type of labour
On Site Rate (8 Hours)
Rate according to DSR (8 Hours)
Cost for 1 m2 onsite rates
Cost for 1m2 DSR
rate
Skilled Labour
Plasterer
500
311
43.94
27.33
Breaker
350
270
12.73
9.821
Semiskilled
300
270
26.36
23.73
Unskilled
200
270
20.03
27.03
103.08
87.92
103
Rs.
88 Rs.
Actual Labour Rate on site for External Sand faced Plaster 1m2 = 110 Rs
P.A. – Personal allowance F.A.-Fatigue allowance
S.P.D.A.-Safety Protective dress T.M.S.-Tediousness + Mental strain
P.A. – Personal allowance F.A.-Fatigue allowance
S.P.D.A.-Safety Protective dress T.M.S.-Tediousness + Mental strain
Sr.
No.
Task
Basic Time
Allowance Added
Standard Time
P.A.
F.A.
S.P.D.A.
T.M.S.
1.
External Plaster Pebble Type (1m2)
11
Minutes 27 Seconds
5%
15%
10%
10%
16 Minutes 43 Seconds
2.
Micro-concrete for repairs of Beam
(1m)
1 Hour
02 Minutes
10 Seconds
5%
15%
10%
10%
1 Hour 27 Minutes
1 Seconds
3.
Repair of Malfunction of waterproofing, Leakage (1m2)
3 Hour
22 Minutes
17 Seconds
5%
15%
10%
10%
4 Hours 43
Minutes 12 Seconds
4.
Polymer modified mortar for repairs of slab (1m2)
40
Minutes 07 Seconds
5%
15%
10%
10%
56 Minutes 5Seconds
5.
External wall paint work (1m2)
12
Minutes 04 Seconds
5%
15%
10%
10%
16 Minutes 54 Seconds
6.
External Sand faced Plaster (1m2)
24
Minutes 04
5%
15%
10%
10%
33 Minutes 42 Seconds
Sr.
No.
Task
Basic Time
Allowance Added
Standard Time
P.A.
F.A.
S.P.D.A.
T.M.S.
1.
External Plaster Pebble Type (1m2)
11
Minutes 27 Seconds
5%
15%
10%
10%
16 Minutes 43 Seconds
2.
Micro-concrete for repairs of Beam
(1m)
1 Hour
02 Minutes
10 Seconds
5%
15%
10%
10%
1 Hour 27 Minutes
1 Seconds
3.
Repair of Malfunction of waterproofing, Leakage (1m2)
3 Hour
22 Minutes
17 Seconds
5%
15%
10%
10%
4 Hours 43
Minutes 12 Seconds
4.
Polymer modified mortar for repairs of slab (1m2)
40
Minutes 07 Seconds
5%
15%
10%
10%
56 Minutes 5Seconds
5.
External wall paint work (1m2)
12
Minutes 04 Seconds
5%
15%
10%
10%
16 Minutes 54 Seconds
6.
External Sand faced Plaster (1m2)
24
Minutes 04
5%
15%
10%
10%
33 Minutes 42 Seconds
TABLE 14 RESULTS OF STANDARD TIME
-
CONCLUSION
From the above study important conclusions are as follows.
-
Building owners can beforehand understand the maintenance cost and can plan for the budgetary requirements.
-
Building owners will be able to negotiate the task labour rates.
-
There is wide difference between actual cost required and cost quoted for maintenance tasks. This study will help engineers and owner to decide on maintenance task prioritization based on available budget.
-
From the data collected, Actual labour rates are2.36% to 25% higher than the computed rates based on the time requirement.
-
Maintenance engineers can supervise the work on basis of work break down structure given for the tasks.
-
-
REFERANCES
-
Abdul Talib Bon, Aliza Ariffin An Impact Time Motion Study on Small Medium Enterprise Organization, International Conference on Business and Economic Research, pp1-11,2010.
-
Ammar Olabi, Ammar Olabi, Jean Hunter, Peter Jackson, Michele Segal, Rupert Spies, Carolyn Wang, Christina Lau, Christopher Ong, Conor Alexander, Evan Raskob, Jennifer Plichta, Ohad Zeira, Randy Rivera, Susan Wang, Bill Pottle, Calvin Leung, Carrie Vicens, Christine Tao, Craig Beers, Grace Fung, Jacob Levine, Jaeshin Yoo, Joanna Jackson, Kelly Saikkonen, Matthew Zimmerman, Megan Cunningham, Michele Crum, Naquan Ishman, Norman Voo, Raul Cadena, Robert Relinger, Saori Wada Work Measurement for Estimating Food Preparation Time of a Bioregenerative Diet, Habitation , Vol.9, pp1-44,2003.
-
CPWD maintenance manual ,pp 1-277 ,2000
-
Liju Joshua,Koshy Varghese Classification of bricklaying activities in work sampling categories using accelerometers, Construction Research Congress ASCE, pp 919-928,2012.
-
Productivity Networks, Inc How to use Work Measurement for High Productivity Maintenance Operations, pp 1-8,2002.
-
Repairs and maintenance needs of RCC structure
Rebuild, vol.4, pp 1-20, 2010.
-
Shabbir Syed Abdul, Luai A. Ahmed, Rachapalle Reddi Sudhir, Jeremiah Scholl , Yu-Chuan Li , Der-Ming Liou Comparison of Documentation Time Between an Electronic and a Paper Based Record System by Optometrists at an Eye Hospital in South India: A Time Motion Study Elsevier Computer Methods and Programs in Biomedicine, Vol.100, pp283288,2010.
-
Sitaramraju Mantena, Lisa K. Spainhour, Yaw A. Owusu Time and Motion Study for Affordable traffic Data collection system for the State of florida vol.15, pp 122-131,2008.
-
Tom Best Work Measurement in Skilled Labour Environment Society for Health System, pp 1-26,2009
-
O.P.Khanna Work Study Motion and Time Study Revised Edition, 1992, Dhanpat Rai and Sons, New Delhi