Neural Network Prediction Model for Construction Project Duration
Silvana Petruseva 1, Vahida Zujo 2, Valentina Zileska-Pancovska 3
1 Assis. Prof. PhD, University St. Cyril and Methodius, Faculty of Civil Engineering, (Mathematics Department) Skopje, Macedonia,
2 . Prof. PhD, C.E., University Demal Bijedi in Mostar, Faculty of Civil Engineering, Bosnia and Herzegovina,
3 Prof. PhD, C.E., University St. Cyril and Methodius, Skopje, Faculty of Civil Engineering, Macedonia, (Department for Management of Construction)
Abstract
This paper presents neural network model for predicting construction project duration.
Key data of the total of 75 buildings constructed in the Federation of Bosnia and Herzegovina have been collected through field studies. The collected data contain information for the contracted and real time of construction, the contracted and real price of construction and there are also data for the use of these 75 objects and for the year of construction.
First, a linear regression using time-cost model was applied to these data for forecasting the construction time. Then, a multilayer perceptron neural network (MLP – NN) predictive model to the same data was applied and significant improvement of the accuracy of the prediction was obtained.
Keywords: artificial neural network, construction time, construction cost, linear regression, multilayer percep- tron
-
Introduction
Project deadline is an essential element of each construction contract, but in numerous construction projects there is non-compliance of the contracted time (that is included in the building contract and certified by the contractor and client) and planned time (that is determined by the technical preparation department with one of the planning methods) of construction. This
problem is confirmed by many authors worldwide [12], [14], [4], [30], [31].
Numerous scientific studies have been addressed to the investigation of contracted construction time and contracted price at various construction markets.
Bromilow investigated the relation between construction price and construction time. From his research stems the well known time cost model. Afterwards the model has been confirmed in many countries [7], [4], [30], [15], [8], [24], [13], [19].
Yakubu Adisa Olawale and Ming Sun identified causes of cost and time overruns. They studied factors inhibiting the ability of practitioners to effectively control their projects [18].
Jieh-Haur Chen and Wei-Hsiang Chen derived a mathematical way of defining the contractor's costs for factoring account receivables [6].
Yanshuai Zhang and S. Thomas Ng applied an evolutionary-based optimization algorithm known as an ant colony system to solve the multi-objective time- cost optimization problems [29].
Abbas Afshar and Habib Fathi presented a multi- objective model to search the non-dominated solutions considering total duration, required credit, and financing cost as three objectives. Fuzzy-sets theory is used to account for uncertainties in direct cost of each activity for determining the required credit and financing cost [2].
Ehsan Eshtehardian, Abbas Afshara and Reza Abbasnia presented an approach to investigate stochastic time cost tradeoff problems employing fuzzy logic theory [9].
This paper presents linear regression and neural network (NN) prediction models applied to the data of
75 objects built in the Federation of Bosnia and Herzegovina in the period from 1999 to 2012. Comparison of these two models shows that the application of NN prediction model significantly improves the accuracy of the prediction.
Artificial neural networks (ANN) have been found to be powerful and versatile computational tools for many different problems in engineering over the past 2 decades. Many applications of ANN have proven that they can be applied successfully to many engineerings problems and that in many cases they perform better than conventional methods. They have proved useful for solving certain types of problems, which are too complex, or too resource-intensive nonlinear problems to tackle using more traditional computational methods, such as the finite element method. ANNs are intelligent tools, which have gained strong popularity in a large array of engineering applications such as pattern recog- nition, function approximation, optimization, forecas- ting, data retrieval, automatic control or classification, where conventional analytical methods are difficult to pursue, or show inferior performance.
The first journal article on neural network application in civil engineering was published in 1989. Since then, many articles on NN application in different areas of civil engineering like structural engineering, manage- ment [3], [11], environmental and water resources engi- neering, traffic, geotechnical and geomechanical engi- neering have been published [1],[20].
-
Linear regression and neural network prediction models for construction project duration
Data were collected for a total of 75 structures built in the Federation of Bosnia and Herzegovina in the period from 1999 to 2012 using questionnaires and interviews. Key data were: structure type; construction year; contracted and realized construction time;
overrun was 100%, and the price was 68.75% while the average contracted deadline has been exceeded for 11.55% and 2.77% for the price. Contracted deadline reduction was registered at 11 structures (14.67%), while simultaneously the contracted deadline and the contracted price reduction was registered at 2 structures (2.67%).
Total of five different reasons for non-compliance appear: approvals and permits; climate; incomplete and inaccurate technical documentation; material delivery and terms of financing [5],[31].
-
Linear regression prediction model for construction project duration
-
Linear regression is an approach to model the relationship between a scalar dependant variable y and one or more explanatory variables denoted X. The case of one explanatory variable is called simple linear regression. For more than one explanatory variable, it is called multiple linear regression [26], [25].
In linear regression, data are modeled using linear predictor functions, and unknown model parameters are estimated from the data.
Since linear regression is restricted to fitting linear (straight line/plane) functions to data, it rarely works as well on real-world data as more general techniques such as neural networks which can model non-linear functions. However, linear regression has many practical uses and a number of strengths, for example linear regression analysis can be applied to quantify the strength of the relationship between y and the xj, to assess which xj may have no relationship with Y at all, and to identify which subsets of the xj contain redundant information about Y, also linear regression models are simple and require minimum memory to implement, so they work well on embedded controllers that have limited memory space [22].
For construction time prediction Bromilows time cost model given in Eq. (1) is used.
contracted and realized construction price; reasons for non-compliance of deadline. From a total of 75
T K CB
(1)
structures, disregard of the contracted deadline was registered at 55 of them (73%), disregard of the contracted price was registered at 40 structures (53%), while simultaneously the contracted deadline and the contracted price overrun were registered at 36 structures (48%). The maximm contracted deadline
where: T – contracted time; C – contracted price;
K – model parameter that is a specific way to measure productivity because it shows the average time needed for the construction of a monetary value;
B – model parameters that shows time dependence of costs change.
For the requirements of linear regression model, we shall write this model in linear form, using logarithmic transformation [4], as shown in Eq. (2):
lnT= lnK + BlnC (2)
The linear form of the equation allows usage of the simple statistical procedure, i.e., a single linear regression. We shall determine the values of parameters K and B in this model.
For creating the linear regression model for predicting of the construction time for the 75 objects, DTREG software package was used [23].
DTREG analysis results of the model are presented in Table 1 to Table 3. Considering eq. (2) variable ln(real time) is used as target variable, and ln(real price) as predicted variable.
From Table 1 the coefficients of the linear regression model can be read: B = 0.550208 (which is multiplied with variable ln(real price), and the constant lnK = – 2,37546 and from here K= e-2,37546.
The linear regression model for prediction of construc- tion time will be:
T= e-2,37546C0,550208
A part of the data was used for training the model (training data, Table 2) and a part of the data was used for validation of the model (Table 3).
We can estimate the accuracy of the model from the statistics of validation data (Table 3):
Most often used estimators of a predictive model are R2 and MAPE. In statistics, the coefficient of determination denoted R2 indicates how well data points fit a line or curve. It is a measure of global fit of the model. In linear regression R2 equals the square of Pearson correlation coefficient between observed and modeled (predicted) data values of the dependent variable. R2 is an element of [0.1] and is often interpreted as the proportion of the response variation explained by the regressors in the model. So, the value R2 = 0.73341 from our model may be interpreted: around 73% of the variation in the response can be explained by the explanatory variables. The remaining 27% can be attributed to unknown, lurking variables or inherent variability [27].
MAPE (Mean Absolute Percentage Error) is a measure of accuracy of a method for constructing fitted times series values in statistics. It usually expresses accuracy as a percentage [28]. For this model MAPE =
=10.355481 which means that the error of the model is around 10%.
Table 1. Linear regression model for predicting real time of construction using DTREG package
Summary of Variables ============
Number Variable Class Type Missing rows categories
—— ————————— ——— ———– ———— ———-
1 |
Number of project |
Unused |
Continuous |
0 |
||
2 |
use of the object |
Unused |
Categorical |
0 |
||
3 |
year of construction |
Unused |
Continuous |
0 |
||
4 |
contracted time (days) |
Unused |
Continuous |
0 |
||
5 real time of constr. (days) Unused Continuous 0 |
||||||
6 |
difference (days) |
Unused |
Continuous |
0 |
||
7 |
price contracted [KM] |
Unused |
Continuous |
0 |
||
8 |
real price |
Unused |
Continuous |
0 |
||
9 |
difference of prices |
Unused |
Continuous |
0 |
||
10 |
ln(real time) |
Target |
Continuous |
0 |
||
11 |
ln(real price) |
Predictor |
Continuous |
0 |
75 |
|
============ Linear Regression Parameters ============ ————– Computed Coefficient (Beta) Values ————– Variable Coefficient Std. Error t Prob(t) 95% Confidence Interval ————– ————- ———— ——— ——— ———— ———— |
||||||
ln(real price) 0.550208 |
0.0509 10.82 < 0.00001 |
0.4484 |
0.652 |
|||
Constant -2.37546 |
0.6581 -3.61 0.00064 |
-3.693 |
-1.058 |
— Training Data —
Mean target value for input data = 4.7038902 Mean target value for predicted values = 4.7038902 Variance in input data = 0.8306976
Residual (unexplained) variance after model fit = 0.2753121 Proportion of variance explained by model (R^2) = 0.66858 (66.858%)
Coefficient of variation (CV) = 0.111546 Normalized mean square error (NMSE) = 0.331423
Correlation between actual and predicted = 0.817666 Maximum error = 1.7033044
RMSE (Root Mean Squared Error) = 0.5247019 MSE (Mean Squared Error) = 0.2753121
MAE (Mean Absolute Error) = 0.4108599
MAPE (Mean Absolute Percentage Error) = 9.2084657
— Training Data —
Mean target value for input data = 4.7038902 Mean target value for predicted values = 4.7038902 Variance in input data = 0.8306976
Residual (unexplained) variance after model fit = 0.2753121 Proportion of variance explained by model (R^2) = 0.66858 (66.858%)
Coefficient of variation (CV) = 0.111546 Normalized mean square error (NMSE) = 0.331423
Correlation between actual and predicted = 0.817666 Maximum error = 1.7033044
RMSE (Root Mean Squared Error) = 0.5247019 MSE (Mean Squared Error) = 0.2753121
MAE (Mean Absolute Error) = 0.4108599
MAPE (Mean Absolute Percentage Error) = 9.2084657
2. Statistics for training data for the linear regression model ( DTREG)
— Validation Data —
Mean target value for input data = 4.6575062 Mean target value for predicted values = 4.6797136 Variance in input data = 1.0179999
Residual (unexplained) variance after model fit = 0.2713927 Proportion of variance explained by model (R^2) = 0.73341 (73.341%)
Coefficient of variation (CV) = 0.111852 Normalized mean square error (NMSE) = 0.266594
Correlation between actual and predicted = 0.858757 Maximum error = 0.8396821
RMSE (Root Mean Squared Error) = 0.5209536 MSE (Mean Squared Error) = 0.2713927
MAE (Mean Absolute Error) = 0.462848
MAPE (Mean Absolute Percentage Error) = 10.355481
— Validation Data —
Mean target value for input data = 4.6575062 Mean target value for predicted values = 4.6797136 Variance in input data = 1.0179999
Residual (unexplained) variance after model fit = 0.2713927 Proportion of variance explained by model (R^2) = 0.73341 (73.341%)
Coefficient of variation (CV) = 0.111852 Normalized mean square error (NMSE) = 0.266594
Correlation between actual and predicted = 0.858757 Maximum error = 0.8396821
RMSE (Root Mean Squared Error) = 0.5209536 MSE (Mean Squared Error) = 0.2713927
MAE (Mean Absolute Error) = 0.462848
MAPE (Mean Absolute Percentage Error) = 10.355481
Table 3. Statistics for validation data for the linear regression model ( DTREG)
2.2 Neural network prediction model for construction project duration
Neural networks are intelligent systems that are based on simplified computing models of the biological structure of the human brain, whereas the systems based on traditional computer logic require comprhen- sive programming in order to perform a given task.
There are several aspects that make ANNs attractive, such as: relation with biological neural networks; relation with the concept of parallel distributed
processing and relation with the concept of learning and self-organization[10].
ANNs are suitable for multivariable applications where they can easily identify interactions and patterns between inputs and outputs. ANN models do not require complicated and time consuming finite element input file preparation for routine design applications. They are able to infer important information for the task, which is being solved by them, if data that is representative of the underlying process to be implemented, is provided .
Neural networks have a self-learning ability, which is particularly useful where comprehensive models that are required for conventional computing methods are either too large or too complex to represent accurately, or simply doesnt exist at all. The highly connected, distributed nature of neural networks also provides a high degree of generalization capability and noise immunity. In the last 20 years there have been several pointers toward the issue of feelings and emotions as needed features for development of artificial neural networks, especially in the speeding up the process of their learning [21].
Software package DTREG, which is used in this paper implements the most widely used types of neural networks: Multilayer Perceptron Networks (MLP), Probabilistic Neural Networks (PNN) and General Regression Neural Networks (GRNN), Radial Basic Function (RBF) networks, Polynomial Neural Networks (GMDH), and Cascade Correlation networks [22].
In this paper, Multilayer Perceptron Neural network is used as a predictive model.
A multilayer perceptron (MLP) is a feed forward artificial neural network that maps sets of input data onto a set of appropriate outputs. An MLP consists of multiple layers of nodes in a directed graph, with each layer fully connected to the next one. Except for the input nodes, each node is a neuron (or processing element) with a nonlinear activation function. For training the network MLP utilizes a supervised learning technique called back propagation [17].
What makes a multilayer perceptron different is that each neuron uses a nonlinear activation function which was developed to model the frequency of action potentials. This function is modeled in several ways, but always must be normalizable and differentiable.
There are two main activation functions used in current applications which are both sigmoid:
where: the former function is a hyperbolic tangent which ranges from -1 to 1, and the latter, the logistic function, is similar in shape but ranges from 0 to 1.
MLPs were a popular machine learning solution, finding applications in diverse fields such as speech recognition, image recognition, forecasting and machine learning software.
MLP network (Figure1.) has an input layer (on the left), one hidden layer (in the middle) and an output layer (on the right) [22]. There is one neuron in the input layer for each predictor variable (x1,,xp).
A vector of predictor variable values (x1,,xp) is presented to the input layer. The input layer (or processing before the input layer) standardizes these values so that the range of each variable is -1 to 1. The input layer distributes the values to each of the neurons in the hidden layer.
Arriving at a neuron in the hidden layer, the value from each input neuron is multiplied by a weight (wji), and the resulting weighted values are added together producing a combined value uj. The weighted sum (uj) is fed into a transfer function, , which outputs a value hj. The outputs from the hidden layer are distributed to the output layer.
Arriving at a neuron in the output layer, the value from each hidden layer neuron is multiplied by a weight (wkj), and the resulting weighted values are added together producing a combined value vj. The weighted sum (vj) is fed into a transfer function, , which outputs a value yk. The y values are the outputs of the network.
The goal of the training process is to find the set of weight values that will cause the output from the neural network to match the actual target values as closely as possible.
One of the most important characteristics of a multilayer perceptron network is the number of neurons in the hidden layer(s). If an inadequate number of neurons are used, the network will be unable to model complex data, and the resulting fit will be poor.
If too many neurons are used, the training time may become excessively long, and, worse, the network may over fit the data. When over fitting occurs, the network will begin to model random noise in the data. The result is that the model fits the training data extremely well, but it generalizes poorly to new, unseen data. Validation must be used to test for this. Software
DTREG includes an automated feature to find the optimal number of neurons in the hidden layer.
In this model three layer MLP with one hidden layer is used.
A typical neural network might have a couple of hundred weighs whose values must be found to produce an optimal solution. If neural networks were linear models like linear regression, it would be easy to find the optimal set of weights. But the output of a neural network as a function of the weights is often highly nonlinear and this makes the optimization process complex. DTREG uses the Nguyen-Widrow algorithm to select the initial range of starting weight values. It then uses the conjugate gradient algorithm
-
to optimize the weights.
The training algorithms follows this cycle to refine the weight values :
-
Run the predictor values for a case through the network using a tentative set of weights.
-
Compute the difference between the predicted target value and the actual target value for the case. This is the error of the prediction.
-
Average the error information over the entire set of training cases.
-
Propagate the error backward through the network and compute the gradient (vector of derivatives) of the change in error with respect to changes in weight values.
-
Make adjustments to the weights to reduce the error.
-
Each cycle is called an epoch. Because the error information is propagated backward through the network, this type of training method is called backward propagation or backprop.
Table 4, Table 5 and Table 6 present the result of the modeling MLP using DTREG package.
Considering the eq. (2) for dependence of the time of construction from the price of construction, here the target variable is ln(real time) and predictor variables are chosen to be ln(contracted time), ln(contracted price) and ln(real price).
Table 4 presents general statistics and parameters of the MLP model. Table 5 presents the statistics for training data, and Table 6 for validation data.
Figure 1. Multilayer perceptron (with permission of the author Phill Sherrod of DTREG package) Table 4. General statistics of the MLP predictive model (using DTREG package)
Number of variables (data columns): 13 Data subsetting: Use all data rows Number of data rows: 75
Total weight for all rows: 75
Rows with missing target or weight values: 0 Rows with missing predictor values: 0
— Statistics for target variable: ln(treal time) — Mean value = 4.6946134
Standard deviation = 0.9319347 Minimum value = 2.7080502 Maximum value = 6.4922398
============ Summary of Variables ============
Number Variable Class Type Missing rows Categories
—— ————————— ——— ———– ———— ———-
1 |
Number of project |
Unused |
Continuous |
0 |
|
2 |
use of the object |
Unused |
ategorical |
0 |
|
3 |
year of construction |
Unused |
Continuous |
0 |
|
4 |
contracted time (days) |
Unused |
Continuous |
0 |
|
5 real time of constr. (days) Unused Continuous 0 |
|||||
6 |
difference (days) |
Unused |
Continuous |
0 |
|
7 |
price contracted [KM] |
Unused |
Continuous |
0 |
|
8 |
real price |
Unused |
Continuous |
0 |
|
9 |
difference of prices |
Unused |
Continuous |
0 |
|
10 |
ln(treal time) |
Target |
Continuous |
0 |
|
11 |
ln(real price) |
Predictor |
Continuous |
0 |
75 |
12 |
ln(contracted time) |
Predictor |
Continuous |
0 |
31 |
13 |
ln(contracted price) |
Predictor |
Continuous |
0 |
75 |
============ Neural Network Parameters ============
— Neural Network Architecture —
The network will be built using 7 neurons for hidden layer 1.
— Training Data —
Mean target value for input data = 4.6946134 Mean target value for predicted values = 4.7049379 Variance in input data = 0.8685023
Residual (unexplained) variance after model fit = 0.021151 Proportion of variance explained by model (R^2) = 0.97565 (97.565%)
Coefficient of variation (CV) = 0.030979 Normalized mean square error (NMSE) = 0.024353
Correlation between actual and predicted = 0.987832 Maximum error = 0.594998
RMSE (Root Mean Squared Error) = 0.1454337 MSE (Mean Squared Error) = 0.021151
MAE (Mean Absolute Error) = 0.1033324
MAPE (Mean Absolute Percentage Error) = 2.2472572
— Training Data —
Mean target value for input data = 4.6946134 Mean target value for predicted values = 4.7049379 Variance in input data = 0.8685023
Residual (unexplained) variance after model fit = 0.021151 Proportion of variance explained by model (R^2) = 0.97565 (97.565%)
Coefficient of variation (CV) = 0.030979 Normalized mean square error (NMSE) = 0.024353
Correlation between actual and predicted = 0.987832 Maximum error = 0.594998
RMSE (Root Mean Squared Error) = 0.1454337 MSE (Mean Squared Error) = 0.021151
MAE (Mean Absolute Error) = 0.1033324
MAPE (Mean Absolute Percentage Error) = 2.2472572
Table 5. Statistic for the training data for the MLP predictive model (DTREG
— Validation Data —
Mean target value for input data = 4.6946134 Mean target value for predicted values = 4.6900164 Variance in input data = 0.8685023
Residual (unexplained) variance after model fit = 0.0261502 Proportion of variance explained by model (R^2) = 0.96989 (96.989%)
Coefficient of variation (CV) = 0.034446 Normalized mean square error (NMSE) = 0.030110
Correlation between actual and predicted = 0.984851 Maximum error = 0.6874137
RMSE (Root Mean Squared Error) = 0.1617104 MSE (Mean Squared Error) = 0.0261502
MAE (Mean Absolute Error) = 0.1127981
MAPE (Mean Absolute Percentage Error) = 2.4984055
— Validation Data —
Mean target value for input data = 4.6946134 Mean target value for predicted values = 4.6900164 Variance in input data = 0.8685023
Residual (unexplained) variance after model fit = 0.0261502 Proportion of variance explained by model (R^2) = 0.96989 (96.989%)
Coefficient of variation (CV) = 0.034446 Normalized mean square error (NMSE) = 0.030110
Correlation between actual and predicted = 0.984851 Maximum error = 0.6874137
RMSE (Root Mean Squared Error) = 0.1617104 MSE (Mean Squared Error) = 0.0261502
MAE (Mean Absolute Error) = 0.1127981
MAPE (Mean Absolute Percentage Error) = 2.4984055
Table 6. Statistic for the validation data for the MLP predictive model (DTREG)
We can see from table 6 that estimators R2 and MAPE for the validation data of the model are: R2= 0.96989, and MAPE = 2.4984055, indicating significant improve-ment of the accuracy of the prediction in comparison with the linear regression model.
CONCLUSION
The paper presents two models for predicting the time construction of an object: linear regression model and neural network model (multilayer perceptron).
75 objects structured in the period of 1999 to 2012 in the federation of Bosnia and Herzegovina have been analyzed. First, the conventional linear regression model was build using the time cost model. Then, the neural network multilayer perceptron predictive model was applied to the same data.
-
The linear regression model for predicting the real time of construction was estimated by
R2 = 0.73341, and MAPE=10.355481 (for the
validation data).
-
MLP model for predicting the real time of construction was estimated by: R2 = 0.96989, and MAPE= 2.4984055 (for the validation data).
Models comparison results show that application of the MLP-NN model indicates significant improvement of the accuracy of the prediction.
The authors hope that the presented model will prove very useful for improving planning in construction industry in general.
REFERENCES
-
H.Adeli, Review article, Neural Networks in Civil Engineering:1989-2000, Computer Aided and Civil and Infrastructure Engineering, 16, 126-142, 2001
-
A.Afshar and H.Fathi, Fuzzy multi-objective optimization of finance-based scheduling for construction projects with uncertainties in cost, Engineering Optimization Volume 41, Issue 11, 2009, pages 1063-1080
-
M.Arafa, M.Alqedra, Early Stage Cost Estimation of Buildings Construction Projects using Artificial Neural Networks, Journal of Artificial Intelligence, 4 (1), 2011, pp. 63-75
-
Car Pui D., Methodology of anticipating sustainable construction time,(in croatian) PhD thesis,
2004, Faculty of Civil Engineering, University of Zagreb.
-
D.W.M. Chan. and M.M.A. Kumaraswamy.: Study of the factors affecting construction duration in Hong Kong, Construction management and economics, 13(4): pp. 319-333, 1995
-
J.H.Chen and W.H.Chen, Contractor Costs of Factoring Account Receivables for a Construction Project, Journal of Civil Engineering and Management, Volume 18, Issue 2, 2012, pages 227-234).
-
I.Choudhry and S.S. Rajan, Time cost relation- ship for residential construction in Texas, College Station, 2003, Texas A&M University.
-
O.Durson and C. Stoy, Time-cost relationship of building projects: statistical adequacy of categorization with respect to project location, Construction Management and Economics, Vol. 29: 97-106, 2011
-
E.Eshtehardian, A. Afshara and R.Abbasnia, Investigation stochastic time-cost trade-off problems employing fuzzy logic theory, Construction Manage- ment and Economics Volume 26, Issue 7, 2008, pages 679-691
-
S. Haykin,: Neural Networks: A Comprehesive Foundation, 2nd ed., Pearson Education Inc., Canada, 2005
-
T. Hegazy, A.Ayed , Neural Network Model for Parametric Cost Estimation of Highway Projects, Journal of Construction Engineering and Management, may/june, 1998,
-
G.J.Hoffman, A.E.Thal, T.S.Webb and J.D.Weir, Estimating performance time for construction projects, Journal of Management in Engineering, 23(4): 193 199, 2007
-
A.Kaka and A.D.F.Price, Realitionship between value and dration of contruction projects, Constructi- on Management and Economics, 1991, Vol. 9: pp. 383- 400.
-
L.Le-Hoai, Y.D.Lee and J.Y.Lee, Delay and Cost Overruns in Vietnam Large Construction Projects: A Comparison with Other Selected Countries, Journal of Civil Engineering, 12(6): 367-377, 2008
-
L. Le-Hoai and Y.D. Lee, Time-cost relationships of building construction project in Korea, Facilities, 2009, Vol. 27 Iss: 13/14: 549-559.
-
Moller, M.Fodslette , A Scaled Conjugate gradi- ent Algorithm for Fast Supervised Learning, 1993, Pergamon Press.
-
L. Noriega, Multilayer Perceptron Tutorial, Scho- ol of Computing Sta_ordshire University, Beaconside Sta_ordshire ST18 0DG, 2005
-
I. Pesko: Model for estimation of costs and time of construction for urban traffic arteries, PhD Thesis (in serbian), Novi Sad, 2013
-
S.Petruseva, Neural Networks and their application in civil engineering. Isothreshold Adaptive Network (IAN), SJCE (Scientific Journal of Civil Engineering), Volume 2, Issue 1, July 2013
-
S.Petruseva, Forward Chaining algorithm for solving the shortest path problem in arbitrary deterministic environment in linear time applied for the Tower of Hanoi Problem, Proceedings of 32nd Annual German Conference on AI, Paderborn, Germany, LNAI 5803, KI 2009: Advances in Artificial Intelligence, Springer,2009
-
P. Sherrod: DTREG Predictive Modeling Software
– tutorial, 2013, www.dtreg.com
-
P. Sherrod: DTREG Predictive Modeling Software,
2013, www.dtreg.com
-
C.Sun and J.Xu,Estimation of Time for Wenchuan Earthquake Reconstruction in China, Journal of Construction Engineering and Management, 2011, Vol 137(3): 179-187.
-
www.http://en.wikipedia.org/wiki/Regression_analysis
-
www.http://en.wikipedia.org/wiki/Linear_regression
-
www.http://en.wikipedia.org/wiki/Coefficient
_of_determination
-
www.http://en.wikipedia.org/wiki/Mean_absolute
_percentage_error
-
Y.Zhang and S.Thomas, An ant colony system based decision support system for construction time- cost optimization, Journal of Civil Engineering and Management, Volume 18, Issue 4, 2012, pages 580-589
-
V. Zujo: Contribution of Construction Time Plan- ning to Construction Project Management (in bosnian), PhD thessis, 2008, Faculty of Civil Engineering, Uni- versity, Demal Bijedi of Mostar.
-
V. Zujo, V. Zileska-Pancovska, M.Chechez, Pre- diction model for sustainable construction project duration, 15th International Symposium (of MASE) , Struga, Macedonia, 18-21 Sept., 2013