Advantages of using EMV in Auditing Construction Processes

DOI : 10.17577/IJERTV4IS110394

Download Full-Text PDF Cite this Publication

Text Only Version

Advantages of using EMV in Auditing Construction Processes

Idlir Dervishi1,

Dep. of Building Constructions and Transport Infrastructure Faculty of Civil Engineering, Polytechnic of Tirana Tirana, Albania

Dhimitri Papa2

Dep. of Building Constructions and Transport Infrastructure Faculty of Civil Engineering, Polytechnic of Tirana, Tirana, Albania

Abstract Audit process is the final stage of the construction process chain for the execution of the civil engineering works. At this stage are certified or not all the cash flows, the technical parameters of the project, the quality of work and compliance with laws and regulations. It is important that during the audit phase to gather reliable evidence in order to have uncontestable recommendations and to be in accordance with reality. The integration of Earned Value Method, during the auditing phase, in order to measure the performance of the implemented engineering interventions and restoration of works which are considered monument of culture; it results in the increase of efficiency and effectiveness of the construction process. This paper shows the calculation of performance indexes, based on international auditing standards, laws and regulations in force, all the technical, financial and legal documentation of the civil engineering and restoration projects that will be applied.

Keywords: Civil Engineering Projects, Restoration Projects, Audit, Earned Value Method, Performance Index.

  1. INTRODUCTION

    The audit process is mainly applied during the recent years in the cycle of civil engineering projects, but it is not directly related to the construction stages and its processes. The audit of civil engineering projects is generally performed post factum, which means when all the works are completed. Application of EVM can also be performed during the execution phase of the project, where can be calculated the performance indexes, in order to draw conclusions in forecasting its future performance of it. [1], [4].

    We analyzed the reconstruction and restoration works of the Former Kinostudio Building ", Cultural Monument of the Second Category, shown in Figure 3.1 [8]. The works which will be subject to restoration, since it is a monument of culture and based on the law of cultural heritage, represents a high risk in terms of performance of reference prices, quality and quantity specified in the project. The object is located in Tirana and the process of restoration was carried out in 270 days, the original deadline for its completion has been 180 days. As evidenced, the reconstruction and restoration process was completed 90 days later. The value execution of the reconstruction and restoration project is 103,258,474 ALL. Engineering intervention and restoration work was carried out during the years 2013 -2014.

  2. METHODOLOGY USED

    For the realization of this paper are used two different methods: "Desk research" and "Field research", which helped in drawing the final conclusions. Initially, with the "Desk research" method, it is reviewed the available literature, which address the issues of managing civil engineering projects with public investments, monitoring, controlling and auditing them. In these books there are important and plenty information about the Earned Value Method and calculation methods of quantitative project progress [2]. Also, from the theoretical part, there are outlined several important empirical formulas for calculating the performance indexes of costs and schedules. These formulas help us to present in the quantum way the results obtained from the implementation of the project. "Field Research" Method consists in preparing a specific questionnaire divided into 3 parts: directed to the civil engineers of the company that are implementing the engineering and restoration part of the project, and officials of the public institution that procured and constantly controlled the restoration process and the engineering intervention.

  3. CASE STUDY. RESULTS ANALYSIS. According to the definition of PMBOK 2008, Earned

    Value Method is a method used to measure the performance of the project, by integrating deadlines, costs and real physical progress of the project [1], [3]. As part of EVM:

    Earned Value- EV express the value of work performed at a point in time T Time now according to the estimated BOQ price.

    • Planned Value-PV or Budgeted cost of the work scheduled, expresses the total value of works included in the bill of quantities of reconstruction and restoration activity to be performed by the end date.

    • Actual Cost-AC or Actual Cost of Work Performed expresses the paid cost for the works performed by the time T "Time now" [7].

      In the meantime, the calculation of the performance index of the project takes into consideration the costs and deadlines stated as follows [2], [5]:

    • Cost Variance- CV = Earned Value Actual Cost: CV = EV- AC (1)

    • Schedule Variance- SV = Earned Value Planned Value:

      SV = EV- PV (2)

    • Cost Performance Index – CPI = Earned Value /Actual Cost:

    CPI = EV / AC (3)

    • Schedule Performance Index – SPI = Earned Value/ Planned Value:

    SPI = EV / PV (4)

    The purpose of this paper is to measure the performance i of the project in the point time T (06.10.2014), by integration of the above formulas in the computer software PROING®. The software is developed to calculate the performance indexes of the project, and enabled in obtaining the data in Table 3.2.

    The difference in quantity and volume of the work performed, for those works that had had a lower performance are argued as follows:

    • Construction of reinforced concrete roof with wooden frames and tiles: The Final Statement presents 290 m2 and the Measurement Sheet presents in an analytical way a total quantity of 290 m2. These works are carried out only on the sides of the building frame, closing the spaces after the demolition of existing chimneys and removal of ventilation tubes, respectively 15.31 m2 + 7.88 m2 + 2.25 m2. Whereas, from the photos found in the technical file and during the check of the project, the construction of this type of roof (reinforced concrete roof) with surface (132.41 + 132.41 m2=

      264.82 m2) turns out that is not performed in the main buildings. In this part are performed works for setting tiles and hydro isolation. By subtracting these works, the price for unit goes to 4200 lek/m2 – 1590 lek/m2 (tile) – 1100 (hydro isolation) = 1,510 lek/m2. Also, in this section is laid a concrete leveling layer of 10 cm, which is presented in a special voice for the work. The difference in quantity is 290 m2 – 25.18 m2 = 264.82 m2. From the calculation of PROING® computer software, Cost Performance Index for this type work is CPI = 0.087 < 1. This value indicates that the amount paid is higher than the real value of the works, where the quantity of the work performed is smaller than the one presented in the Measurement Sheet.

    • Supply and fixing of the Vertical Rain Gutter: The Final Statement presents 340 ml and the Measurement Sheet presents in an analytical way a total quantity of 340 ml. From the verification on the ground and the technical design of the project in electronic version , showed that are fixed in total 19 vertical rain gutters, where fifteen (15) of these have the length of 8 ml, and the other 4 have the length of 15 ml. In conclusion, (15 x 8ml + 4 x 15 ml) = 120 ml + 60 ml = 180 ml vertical rain gutter fixed in the object. The differnce is

      340 ml – 180 ml = 160 ml. From the calculation of PROING® computer software, Cost Performance Index for this type of work is CPI = 0.525 < 1. This value indicates that the amount paid is higher than the real value of the works, where the quantity of work performed is smaller than the one presented in the Measurement Sheet. This work has had the lowest performance in relation to the cost, also not

      the highest impact during all the reconstruction and restoration process.

    • Supply and Fixing of the Marble Wall Covering: The Final Statement presents 120 m2 and the Measurement Sheet presents in an analytical way a total quantity of 120 m2. From the verifications done on the ground, it results that these floor tiles are not placed in the cove of the object, and the cove is in its previous state. Cost Performance Index for this type of work is CPI = 0.0 < 1, this value indicates that the work is not performed. The quantity presented in the Measurement Sheet does not correspond to the facts. This work has had the biggest negative impact on the performance of the costs of the entire reconstruction and restoration process.

    • Transport of inert and solid waste: The Final Statement presents 2500 m3 and the Measurement Sheet presents in an analytical way a total volume of 2500 m3. From the verification of the Final Statement, the Measurement Sheet for all the works of demolition-removal and after the calculations, it results that are 1111 m3 of wastes to be transported, shown at the table below:

      TABLE 3.1

      Description

      Area

      Thickness

      Quantity

      m2

      m

      m3

      Removal of the tiles

      1750

      0.1

      175

      Demolition and Removal of the

      ground floor

      280

      0.1

      28

      Demolition and Removal of the brick wall

      196

      0.25

      49

      Demolition and Removal of the interior brick wall

      2200

      0.1

      220

      Removal of the external plastering

      1519

      0.1

      152

      Removal of the ornamental

      plastering

      150

      0.1

      15

      Removal of the column

      patching

      60

      0.1

      6

      Removal of the ceiling plastering

      437

      0.1

      43.7

      Removal of the floor tiles

      190

      0.05

      9.5

      Removal of the wall tiles

      43

      0.05

      2.15

      Removal of the wooden

      window

      230

      0.1

      23

      Removal of the wooden doors

      52

      0.1

      5.2

      Removal of the window iron

      bars

      70

      0.14

      9.8

      Removal of the windows

      marble

      80

      0.05

      4

      Removal of the air conditioning

      equipment

      10

      0.5

      5

      Removal of the rain gutter

      525

      0.2

      105

      Removal of the sanitary

      equipment

      1

      1

      1

      Removal of the wiring

      1

      10

      10

      Removal of the plumbing

      fixture

      1

      5

      5

      Wall openings

      85

      0.2

      17

      Decoration cleaning

      1

      20

      20

      Demolition and removal of the walls under the roof

      49.44

      0.25

      12.36

      Dismantling works

      52

      0.05

      2.6

      Removal of the back window

      1

      5

      5

      Demolition and Removal of the

      roof

      414

      0.2

      82.8

      Demolition and Removal of reinforced layer of the roof

      414

      0.25

      103.5

      Total Quantity

      1111

      Figure 1. AC, PV and EV, Calculated in PROING®

      Figure 2 CPI and SPI Chart

      Table 3.2. Calculation of Cost Performance Index and Schedule Performance Index using PROING®

      Restoration of Kinostudio Building

      Unit

      Bill of Quantities

      Price/ Unit

      Planned Quantity

      Declared Quantity

      Measured Quantity

      Declared Progress

      Real Progress

      PV

      AC

      EV

      CV

      SV

      CPI

      SPI

      Description

      ALL

      ALL

      Unit

      Unit

      Unit

      %

      %

      ALL

      ALL

      ALL

      ALL

      ALL

      A

      Roof works

      1

      Construction of the roof+ tiles H>12m

      m2

      2,319,200

      4,460

      520

      501.0

      414.5

      96%

      80%

      2,319,200

      2,234,460

      1,848,670

      -385,790

      -470,530

      0.8273

      0.7971

      2

      Fixing of wooden frames + tiles

      m2

      2,184,000

      4200

      520

      501

      414.5

      96%

      80%

      2,184,000

      2,104,200

      1,740,900

      -363,300

      -443,100

      0.8273

      0.7971

      3

      Construction of reinforced concrete roof + tiles H>12

      m2

      785,200

      1510

      520

      290

      25.2

      56%

      5%

      785,200

      437,900

      38,022

      -399,878

      -747,178

      0.0868

      0.0484

      4

      Supply and fixing of the Vertical Rain

      Gutter

      ml

      1,123,200

      3120

      360

      340

      180

      94%

      50%

      1,123,200

      1,060,800

      561,600

      -499,200

      -561,600

      0.5294

      0.5000

      5

      Supply and fixing of

      reinforcement rebars

      ton

      235,600

      124000

      1.9

      1.9

      0.7

      100%

      35%

      235,600

      235,600

      83,204

      -152,396

      -152,396

      0.3532

      0.3532

      B

      Wall and plastering works

      1

      Exterior plastering H>8m

      m2

      2,632,500

      1620

      1,625

      1,584.0

      1,549.0

      97%

      95%

      2,632,500

      2,566,080

      2,509,380

      -56,700

      -123,120

      0.9779

      0.9532

      2

      Supply and fixing of the floor tiles

      m2

      300,900

      2950

      102

      90.0

      59.7

      88%

      59%

      300,900

      265,500

      176,115

      -89,385

      -124,785

      0.6633

      0.5853

      3

      Supply and install of the parquet flooring

      m2

      1,781,040

      4920

      362

      340.0

      317.0

      94%

      88%

      1,781,040

      1,672,800

      1,559,640

      -113,160

      -221,400

      0.9324

      0.8757

      4

      Supply and fixing of the Marble Wall

      Covering

      m2

      987,600

      8230

      120

      120

      0

      100%

      0.00%

      987,600

      987,600

      -987,600

      -987,600

      0.0000

      0.0000

      5

      Transport of inert and solid waste

      m2

      714000

      340

      2100

      2500

      1111

      119%

      53%

      714,000

      850,000

      377,740

      -472,260

      -336,260

      0.4444

      0.5290

      C

      Office works

      1

      Supply and fixing plasterboard

      m2

      558,000

      3,100

      180

      190

      177.4

      106%

      99%

      558,000

      589,000

      549,940.0

      -39,060.0

      -8,060

      0.9337

      0.9856

      2

      Supply and fixing of the floor tiles

      m2

      978,200

      2,920

      335

      335.0

      286

      100%

      85%

      978,200

      978,200

      835,120.0

      -143,080.0

      -143,080

      0.8537

      0.8537

      3

      Interior wall paint

      m2

      182,400

      120

      1,520

      1,440.0

      1,125

      95%

      74%

      182,400

      172,800

      135,000.0

      -37,800.0

      -47,400

      0.7813

      0.7401

      4

      Supply and fixing aluminum doors

      m2

      558,000

      12,400

      45.0

      39.5

      35.4

      88%

      79%

      558,000

      489,800

      438,960.0

      -50,840.0

      -119,040

      0.8962

      0.7867

      D

      Allowance funds

      Roof works

      1

      Demolition of the old wooden roof

      m2

      221,850

      435

      510

      510

      414.5

      100%

      81%

      221,850

      221,850

      180,307.5

      -41,542.5

      -41,543

      0.8127

      0.8127

      2

      Reinforced concrete leveling layer

      (applied on the roof)

      m3

      1,688,940

      10,236

      165

      175

      125

      106%

      76%

      1,688,940

      1,791,300

      1,279,500

      -511,800

      -409,440

      0.7143

      0.7576

      3

      Demolition and removal of the old

      concrete layer under the roof

      m2

      405,125

      231.5

      1,750

      1,750

      414.5

      100%

      24%

      405,125

      405,125

      95,957

      -309,168

      -309,168

      0.2369

      0.2369

      4

      Supply and fixing of

      reinforcement rebars

      ton

      210,800

      124,000

      2

      2

      0.0

      100%

      0%

      210,800

      210,800

      -210,800

      -210,800

      0.0000

      0.0000

      5

      Supply and fixing of the plasterboard under the ceiling

      m2

      1,271,000

      3100

      410

      370

      294

      90%

      72%

      1,271,000

      1,147,000

      912,020

      -234,980

      -358,980

      0.7951

      0.7176

      E

      Other works

      m3/m2 m/ton

      84,120,919

      100%

      100%

      84,120,919

      84,120,919

      84,120,919

      0

      0

      1.0

      1.0

      Summary

      103,258,474

      103,258,474

      102,541,734

      97,442,994.1

      -5,098,740

      -3,295,022

      0.95

      0.94

      The difference is 2500 m3 – 1111 m3 = 1389 m3. From the calculation of PROING® computer software, Cost Performance Index for this type of work is CPI = 0.444< 1. This value indicates that the amount paid is higher than the real value of the works, where the volume of work performed is smaller than the one presented in the Measurement Sheet.

      Figure 3.1 Frontal view of the building

    • Reinforced concrete leveling layer (applied on the roof). The Allowance Fund Statement presents 175 m3 and the Measurement Sheet presents in an analytical way a total volume of 175m3. From the verification on the ground and the technical design of the project in electronic version, the photos and the Measurement Sheet, it results that are constructed a volume of 125 m3 of Reinforced concrete leveling layers. During the construction of the concrete roof, it is not used reinforced concrete leveling layer t = 10 cm (applied on the roof), as a consequence, there is a difference of 50 m3. The difference in volume is 175 m3 – 125 m3 = 50 m3. From the calculation of PROING® computer software, Cost Performance Index for this work is CPI = 0.71< 1. This value indicates that the amount paid is higher than the real value of the works, where the volume of work performed is smaller than the one presented in the Measurement Sheet.

    performance cost index CPI = 0.95 <1, the cost of the entire process of restoration is higher than the real cost, where the volume of work performed is smaller than the volume paid according to the Final Statement.

    Cost Variance between the realized work value and the declared value of the works in the Final Statement, of the entire project is CV = 5,098,740 ALL.

  4. CONCLUSIONS

    1. Calculation of Performance indexes by using the Earned Value Method enables the measurement of the performance for the entire works that are performed in the object. The performance indexes can be calculated when the works are finished, but also in a certain point in time T (time now) when the works are being performed.

    2. The use of the computer software PROING®, by integrating Earned Value Method (EVM), is an efficient and flexible tool that calculates rapidly and automatically the performance indexes of an executed project.

    3. The use of EMV during the execution phase enables the creation of a management system, where its use, increases the level of involvement of all the stakeholders of the project.

    4. The application of EVM improves the ability of the staff to identify and correct in all the construction processes the exposure to risks, where eventually in the processes that have had a poor performance, the impact of risks has been high.

    5. By using the Earned Value Method in some projects, it is possible the creation of a database, where we can make comparisons between the performance indexes of a project that is in process and a finished project.

    6. The use of the computer software PROING® enables simultaneous management of several engineering projects, by using the same human and financial resources.

    Figure 3.2 Roof leveling layer

    From the results obtained from the calculation of performance index for each construction work, it is concluded that performance in respect to the plan of the entire process of restoration of the building is SPI = 0.94 <1, which indicates that the forecast regarding the timing of completion has been smaller than expected. Also, the committed volumes are lower than those forecasted in the project. With regard to

  5. REFERENCES

  1. American National Standard ANSI-PMI, "A Guide to the Project Management Body of Knowledge", (2008) pg.179-187, pg.116-122.

  2. Guido Capaldo, Antonello Volpe, "Project Management" 2012, pg.175- 177, pg.181-182.

  3. Gianluca di Castri, "Project Management for Edilizia", (2009) pg.104- 118, pg.191-208.

  4. E.Franchi, G.Mancuso, P.D.Patrone, F.Petrilli, R.Repetto, G.Valvo, "Lessons of Project Management" 2013, pg.67-76.

  5. Sagar K. Bhosekar, Gayatri Vyas, "Cost Controlling Using Earned Value Analysis in Construction Industries", International Journal of Engineering and Innovative Technology (IJEIT) Vol.1 I.4 2012 pg.325.

  6. José Ignacio Muñoz Hernández, José Ramón Otegui Olaso, Julen Rubio Gómez, Chapter 7 "Technical Performance Based Earned Value as a Management Tool for Engineering Projects", Book "Engineering Management" 2013, edited by Fausto Pedro Garcia Marquez and Benjamin Lev, pg.143-146.

  7. Caron, Management of Major Engineering Projects 2009, pg.191-209

  8. Architecture and Engineering Design Project – Revised Albafilm 2012, Ark.Shpresa Prifti, Ark.Ermal Musai, Documents of Object "Restoration of Kinostudio Complex, 2014

Leave a Reply