- Open Access
- Authors : Monali Mahadev Bhagwat , Sandeep Chavan
- Paper ID : IJERTV10IS100111
- Volume & Issue : Volume 10, Issue 10 (October 2021)
- Published (First Online): 30-10-2021
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Analysis of Tracking of Project by Earned Value Management Method in High Rise Building
1PG Scholar, Miss. Monali Mahadev Bhagwat
Department of Civil Engineering,
Tatyasaheb Kore Institute of Engineering and Technology, Warananagar, India
2Asst. Prof. Sandeep Chavan
Department of Civil Engineering,
Tatyasaheb Kore Institute of Engineering and Technology, Warananagar, India
Abstract Earn value management is a project accomplishment approach that has been suitable for utilization in project management. Baseline plan can be calculated using EVM to check the progress of the project. EVM operation help in giving achievement standard to the assessment of evolution report of project and it likewise go about as a command gadget to deal with budget and time. The present study deals with planning, scheduling and performance of project process along with it also discusses main parameters involving in the calculation of earned value analysis in cost and time management of civil construction project. the main objectives of manuscript is compare the project tracked by MSP and EVM with conventional tracking method using real time case study of G+15 story building by MSP software.
KeywordsEVM, Tracking, MSP Software, Planning, Schedulling.
-
INTRODUCTION
Construction industry is an important industry at both the global level and national level. It is second largest sector in India. It provides huge employment to the people and plays very significant role in country economy. Project delay is most common problems in the construction industry. In growing countries challenge overruns is a serious in which implementation of challenge faces many doubts. It outcomes in wastage of scare resource of finance, delay in providing facilities, development and too make costlier in construction. With globalization and technology determined economic growth all over the world, a scientific and systematic approach to project organization becomes imperative to make certain that project objectives are attain within the constraints of time and resources EVM is the procedure of measuring presentation of project employment against a baseline plan. EVM application allows in offering overall performance preferred for the assessment of advancement report of project & it also act as a manipulate tool to take care of time & cost schedule through responsibility described in OBS. It provide better performance picture of project and gives better forecast of the final completion cost
-
LITERATURE REVIEW
-
Three-Variance Approach for Updating Earned Value Management
The project management triad has scale, time, and cost. In this study, schedule variations and schedule performance indicators, in traditional dual-variance management (EVM), were shown not for real-time performance indicators, and it is
suggested that the physical body definitions as work variables (WV) and performance indicators be restored. It is found that the performance of the work may be equal to the performance of the same period before the scheduled project time in certain circumstances. However, the same is not always true, especially if the project is over. A performance measurement earned time (ETM) method is presented in this study, which can serve as an alternative to measuring project time upon completion. Finally, it is suggested that the independent performance measurement, WV, be added to EVM, and that a three-pronged approach be used to analyze work conditions, time, and costs in relation to a given project.
-
Estimated Cost at Completion: Integrating Risk into Earned Value Management
Earned Value Management (EVM) is the industry's standard for monitoring the performance of ongoing projects. The operating basis is set in the planning phase to measure any time and cost errors during the project. Based on current progress, it is estimated when completed (EAC). Traditionally, EVM focuses exclusively on project planning (SPI) and cost (CPI), and does not address other important aspects of health and safety, stakeholder satisfaction, and quality. Despite its high volatility, EVM forecasts are still influenced by project risk and uncertainty, leading to a conflict between the results of the EAC obtained by standard formulas. In order to measure a better EAC, a framework is developed that incorporates various key performance indicators in the risk performance indicator (RPI). Using SPI, CPI, and RPI, an integrated model is developed and several case studies are conducted to validate it. The findings show a better EAC compared to traditional methods. Introducing performance indicators to measure key project aspects will provide participants with a better monitoring and decision-making tool.
-
Study of the Stability of Earned Value Management Forecasting
In this paper, the authors focus on establishing mechanisms for predicting the value of earned value management (EVM). The contribution was tripled. First, a new condition for measuring stability that does not suffer as a result of a psychological malfunction that is historically used is proposed. Second, the stability of time and cost forecasting methods are compared and compared using computerized tests on a variety of data sets. In all of these tests, predictive accuracy is also reported, which helps to trade between accuracy and stability. Finally, the demonstration shows that the mathematical strength of the novel can be applied to real
worlds using two real projects. The results of these legal guarantees are found to be highly correlated with computer results.
-
-
RESEARCH METHODOLOGY
Fig. 1. Flowchart of Methodology
-
PREPARE YOUR PAPER BEFORE STYLING
-
Earned Value Analysis-Process
Value Earn is a system management system that uses continuous activity to show what will happen in the future. EVA uses costs as a standard measure of project costs & schedule performance. Allows cost estimates by currency, hours, working days, or other similar item that can be used as the same amount of project-related amounts. EVA uses the following project parameters to evaluate project performance:
-
Planned Value
-
Earned Value
-
Actual Value
As mentioned, there are several ways to calculate the EV, PV and AC of a work package in work. A comparison of those statistics can be used to identify performance and progress inadequate or sophisticated specific work packages, project manager and team can expect supportive actions. Cost and schedule performance should be measured and evaluated with consistency and severity with the magnitude of the performance risk as required by project management. The analysis should be progressive and follow the principle of management by exception. The variance limit should be set at the planning stage and used to guide the examination of performance.
-
-
Concepts & Terminologies Related to Earned Value Management
Value management systems gives different variations that can be analyzed to provide the current status of the project, initiate corrective action also predict future trends measure: Planned Value (PV), Actual Price (AC) and Acquired Value (EV). From the three measures, project performance indicators are formed.
-
BCWS (PV) Budgeted Cost of Works Scheduled It is the baseline for the analysis, cumulated planned
costs related to time of their incurrence; Figure 1 shows the graph of BCWS vs. Time
-
BCWP(EV) Budgeted Cost of Work Performed It is a measure of physical progress of works expresed by cumulated planned cost of works actually done related to time, it is also called Earned Value (like the method it is used by);
-
ACWP (AC) Actual Cost of Work Performed A cumulated amount payable for work done related to time;
-
BAC Budget at Completion The total planned cost of the whole project, it equals BCWS at the planned finish;
-
T Planned duration of the project.
-
SV: Schedule Variance (EV-PV)
-
A comparison of amount of work performed during a given period of time to what was scheduled to be performed.
-
A negative variance means the project is behind schedule
-
-
CV: Cost Variance (EV-AC)
-
A comparison of the budgeted cost of work performed with actual cost.
-
A negative variance means the project is over budget
-
SPI: Schedule Performance Index
-
If means project is behind schedule
-
CPI: Cost Performance Index
-
If means project is over budget
-
CSI: Cost Schedule Index
-
The further CSI is from 1.0, the less likely project recovery becomes. Estimate at completion
-
-
-
Case Study
TABLE I. CASE STUDY INFORMATION
Name of the Project
Elixa Park
Client
Sachin Shinde, Kolhapur
Builder
Ajay Singh V. Desai, Builders and Developers, Kolhapur 416004
Total duration
1400 Day
Built up Area per Floor
643.82 sq.m = 6927.50 sq.ft
Rate per sq. ft
2850 per sq.ft
Start date
01 Jan 2018
End date
29 Oct 2021
Fig. 2. Plan of Project
-
-
RESULT AND DISCUSSION
-
Conventional Model Results
-
Earned Value Overtime Report
TABLE II. EARNED VALUE OVERTIME REPORT
Year
Quarter
Earned Value
Planned Value
AC
2018
Q1
61493405.1
61540959.66
61493405.1
Q2
103701832.6
103749387.1
103701832.6
Q3
116020816.9
116068371.5
116020816.9
Q4
133471552
133519106.5
133471552
2018 Total
133471552
133519106.5
133471552
2019
Q1
145859361.1
147058926.4
145859361.1
Q2
156234168
157433733.3
156234168
Q3
164347322.7
165546888.1
164347322.7
Q4
173785638.3
174985203.6
173785638.3
2019 Total
173785638.3
174985203.6
173785638.3
2020
Q1
181675846.7
182875412.1
181675846.7
Q2
189596239
190958371
189596239
Q3
252731059.7
254093191.7
252731059.7
Q4
264611082
265973213.9
264611082
2020 Total
264611082
265973213.9
264611082
2021
Q1
276564556.4
277926688.4
276564556.4
Q2
287506496.1
288868628.1
287506496.1
Q3
293348797.5
294710929.5
293348797.5
2021 Total
293348797.5
294710929.5
293348797.5
Grand Total
29,33,48,797.5
29,47,10,929.5
29,33,48,797.5
-
Cash Flow
Fig. 3. Earned Value Overtime Report
TABLE III. CASH FLOW REPORT FOR PROJECT
Year
Quarter
Cost
Cumulative Cost
2018
Q1
61540959.7
61540959.66
Q2
42208427.5
103749387.1
Q3
12318984.3
116068371.5
Q4
17450735.1
133519106.5
2018 Total
133519107
133519106.5
2019
Q1
13392495
146911601.5
Q2
10522131.8
157433733.3
Q3
8113154.75
165546888.1
Q4
9438315.55
174985203.6
2019 Total
41466097.1
174985203.6
2020
Q1
7890208.45
182875412.1
Q2
8082958.9
190958371
Q3
63134820.7
254093191.7
Q4
11880022.3
265973213.9
2020 Total
90988010.3
265973213.9
2021
Q1
11953474.5
277926688.4
Q2
10941939.7
288868628.1
Q3
8397213.77
297265841.9
Q4
933122.694
298198964.6
2021 Total
32225750.6
298198964.6
Grand Total
29,81,98,965
29,81,98,964.6
-
Budget Cost
Fig. 4. Cash Flow of Project
TABLE IV. BUDGET COST FOR PROJECT
Year
Quarter
Baseline Cost
Cost
Actual Cost
2018
Q1
61540959.66
61540959.66
61493405.1
Q2
42208427.46
42208427.46
42208427.46
Q3
12318984.35
12318984.35
12318984.35
Q4
17450735.07
17450735.07
17450735.07
2018 Total
133519106.5
133519106.5
133471552
2019
Q1
13539819.91
13392494.95
12387809.12
Q2
10374806.88
10522131.84
10374806.88
Q3
8113154.751
8113154.751
8113154.751
Q4
9438315.549
9438315.549
9438315.549
p>2019 Total 41466097.09
41466097.09
40314086.3
2020
Q1
7890208.449
7890208.449
7890208.449
Q2
8082958.904
8082958.904
7920392.274
Q3
63134820.68
63134820.68
63134820.68
Q4
11880022.27
11880022.27
11880022.27
2020 Total
90988010.31
90988010.31
90825443.68
2021
Q1
11953474.48
11953474.48
11953474.48
Q2
10941939.7
10941939.7
10941939.7
Q3
8397213.767
8397213.767
7691873.144
Q4
933122.6935
933122.6935
762655.7395
2021 Total
32225750.64
32225750.64
31349943.06
Grand Total
29,81,98,964.6
29,81,98,964.6
29,59,61,025
Fig. 5. Budget Cost For Project
-
Budget Work
TABLE V. BUDGET WORK FOR PROJECT
Year
Quarter
Baseline Work
Work
Actual Work
2018
Q1
328
328
311.5
Q2
712
712
712
Q3
1253.15
1253.15
1253.15
Q4
1540.856
1540.856
1540.856
2018 Total
3834.006
3834.006
3817.506
2019
Q1
1462.911
1438.761
1140.911
Q2
1066.433
1090.583
1066.433
Q3
1041.75
1041.75
1041.75
Q4
743.3
743.3
743.3
2019 Total
4314.394
4314.394
3992.394
2020
Q1
903.6
903.6
903.6
Q2
807.85
807.85
742.85
Q3
833.65
833.65
833.65
Q4
1111
1111
1111
2020 Total
3656.1
3656.1
3591.1
2021
Q1
1083.872
1083.872
1083.872
Q2
1420.828
1420.828
1420.828
Q3
773.75
773.75
661.05
Q4
185.55
185.55
88.91667
2021 Total
3464
3464
3254.667
Grand Total
15,268.5
15,268.5
14,655.67
-
Resource Work Availability Report
Fig. 6. Budget Work For Project
TABLE VI. RESOURCE WORK AVAILABILITY REPORT
Year
Quarter
Work Availability
Work
Remaining Availability
2018
Q1
190944
312
190632
Q2
190944
688
190256
Q3
190944
1232
189712
Q4
193392
1512
191880
2018 Total
766224
3744
762480
2019
Q1
188496
1440.167
187055.8333
Q2
190944
1048.317
189895.6833
Q3
190928
944
189984
Q4
193392
808
192584
2019 Total
763760
4240.483
759519.5167
2020
Q1
190944
856
190088
Q2
190944
792
190152
Q3
193392
856
192536
Q4
193392
1088
192304
2020 Total
768672
3592
765080
2021
Q1
188496
1008
187488
Q2
190944
1416
189528
Q3
193392
784
192608
Q4
61200
200
61000
2021 Total
634032
3408
630624
Grand Total
29,32,688
14,984.48
29,17,703.517
Fig. 7. Resource Work Availability Report
-
-
Tracking 1 Project Result (Date 12-November 2018)
TABLE VII. EARNED VALUE ANALYSIS IN TRACKING 1 PROJECT
Year
Quarter
Earned Value
Planned Value
AC
2018
Q1
61493405.1
61540959.66
61493405.1
Q2
103701832.6
103749387.1
103701832.6
Q3
116020816.9
116068371.5
116020816.9
Q4
118861184
118908738.5
118861184
2018 Total
118861184
118908738.5
118861184
Grand Total
11,88,61,184
11,89,08,738.5
11,88,61,184
Fig. 8. Earned Value Analysis in Tracking 1 Project
-
Tracking 2 Project Result (Date 11-September 2020)
TABLE VIII. EARNED VALUE ANALYSIS IN TRACKING 2 PROJECT
Year
Earned Value
Planned Value
AC
2018
133471552
133519106.5
133471552
2019
173785638.3
174985203.6
173785638.3
2020
251549735.4
252911867.4
251549735.4
Grand Total
25,15,49,735.4
25,29,11,867.4
25,15,49,735.4
Fig. 9. Earned Value Analysis in Tracking 2 Project
6. Final Values for EVM Element
TABLE IX. VALUES FOR EVM PERFORMANCE INDICATOR
EVM Performance Indicator
1st Tracking
2nd Tracking
Conventional Method
SV
-47554.5
-1362132
-1362132
CV
0
0
0
SV%
-0.040
-0.539
-0.462
CV%
0
0
0
SPI
0.9996
0.9946
0.9954
CPI
1.0
1.0
1.0
TABLE X. VALUES FOR EVM FORECASTING PARAMETER
EVM Performance Indicator
1st Tracking
2nd Tracking
Conventional Method
EAC
29,81,98,964.6
29,81,98,964.6
29,81,98,964.6
VAC
0
0
0
TSPI
1.00
1.030
1.391
TCPI
1.00
1.00
1.00
-
Value of schedule performance indicators i.e. SV < 0 and SPI < 1
-
It indicates that, Project is running behind the schedule.
-
Value of cost performance indicators CV = 0 and CPI = 1
-
It indicates that Project is running according to budget.
-
Value of cost forecasting parameters i.e. TCPI =1 and VAC = 0 , it interprets that the remaining work and money left from budget are in good coordination; And if it continues properly, then chances of budgeted timely completion are almost 100%.
-
Value of schedule forecasting parameters i.e. TSPI = 1.391 , it interprets that the coordination between remaining work and the time left from scheduled time is highly lacking; And in order to bring it back on track, crew members have to work 139% more than normal 100%
-
-
CONCLUSION
-
Earned value management provides information for the project work package in decision making.
-
Tracking of construction project using earned value
management is useful recognizing the risk factors of the project and to forecast the potential problem in order to face the remaining project work. It also helps the project team in decision making & to be proactive in managing their projects as well as find out progress of performance in construction projects.
-
Tracking is provides practical level knowledge to the contractors about project and proves most helpful to any
project manager who has made a firm commitment to complete the entire feature within a definite schedule and for a restricted amount of funds.
-
The efficiency of project is demonstrated by SPI is 0.995
which is less than 1 hence the project is performed less efficiently and running at about 99% of the planned schedule.
-
Schedule variance of the project is -1362132 Rs. The negative sign determine the project is lagging behind the original schedule.
-
CPI indicates the project efficiency of project utilization.
In our case study CPI is 1 means project is running according to the budget.
-
Cost Variance of the project is Rs 0 because of actual cost and earned value of our project is same.
-
The study shows important, implementation and unique features of EVM that benefits project managers and
ultimately results in project success.
-
In this study 1.41% of cost is reduced or saving with respect calculated planned estimated cost using EVM method.
-
Final Results
TABLE XI. VALUES FOR EVM BASIC ELEMENT
EVM Basic Eleme nt |
1st Trackin g (Rs.) |
2nd Tracking (Rs.) |
Conventio nal Method (Rs.) |
Saving Cost by EVM (Rs.) |
% Savi ng Cost EV M |
Estimat ed Cost (before start the project ) |
29,75,3 3,647.7 |
29,75,33,64 7.7 |
29,75,33,6 47.7 |
||
Total Duratio n of Project |
1400 |
1400 |
1400 |
||
Remai ning Duratio n |
1054 Day |
384 Day |
– |
||
EV |
11,88,6 1,184 |
25,15,49,73 5.4 |
293348797 .5 |
4184850. 18 |
1.41 |
PV |
11,89,0 8,738.5 |
252911867. 4 |
294710929 .5 |
2822718. 18 |
0.95 |
AC |
11,88,6 1,184 |
25,15,49,73 5.4 |
293348797 .5 |
4184850. 18 |
1.41 |
Cash Flow Cumul ated Cost |
29,81,9 8,964.6 |
29,81,98,96 4.6 |
298198964 .6 |
REFERENCES
-
A. Naderpour, M. Mofid, Improving Construction Management Of An Educational Center By Applying Earned Value Technique, Science Direct, Vol – 14, Pp No- 1945-1952, 2011.
-
Agata Czarnigowska, Earned Value Method as a Tool for Project Control, Vol. 3, Pp. 15-32, 2008.
-
Byung-Cheol Kim, M.ASCE, Probabilistic Evaluation of Cost Performance Stability in Earned Value Management, J. Manage. Eng., Vol. 32, No.1, 2016.
-
Byung-Cheol Kim, M.ASCE and Hyung-Jin Kim, Sensitivity of Earned Value Schedule Forecasting to S-Curve Patterns, Journal Construction of Engineering Management, Vol. 140, Issue 7, 2014.
-
Chia-Jui Chang1 and Szu-Wei Yu, Three-Variance Approach for Updating Earned Value Management, © ASCE, J. Constr. Eng. Manage., Vol. 144, No. 6, 2018.
-
Daniel R. McConnell, M. ASCE, Earned Value Technique for Performance Measurement, J. Manage. Eng., Vol. 1, Issue 2, Pp. 79- 94, 1985.
-
Fernando Acebes, Javier Pajares, et. al., Beyond Earned Value Management: A Graphical Frameworkfor Integrated Cost, Schedule and Risk Monitoring, Procedia Social and Behaviour Sciences, Vol. 74, Pp.181-189, March 2013.
-
Jordy Batselier1 and Mario Vanhoucke, Empirical Evaluation of Earned Value Management Forecasting Accuracy for Time and Cost,
© ASCE, J. Constr. Eng. Manage., Vol. 141, No.11, 2015.
-
Mathieu Wauters and Mario Vanhoucke, Study of the Stability of Earned Value Management Forecasting, © ASCE, J. Constr. Eng. Manage., Vol. 141, No. 4, 2015.
-
Roger D.H. Warburton, Denis F. Cioffi, Estimating A Project's Earned and Final Duration, International Journal Of Project Management, Vol. 34, Pp. 1493-1504, Nov. 2016.