Application of Earned Value Analysis in Analysing Project Performance

DOI : 10.17577/IJERTV5IS090341

Download Full-Text PDF Cite this Publication

Text Only Version

Application of Earned Value Analysis in Analysing Project Performance

Shyama Salikuma

    1. Student (Structural Engg & CM) Dept. of Civil Engg , IIET Nellikuzhy, Kothamangalam

      Ms. Minu Anna Johny Assistant Professor, Dept. of Civil Engg, IIET

      Abstract Efficient Management of projects in construction industries are becoming a challenge with the passing time. It has become a concern for the project managers to make sure that the project is on schedule and within budget. EVA evaluates the project performance by integrating both cost and time aspects thereby measuring the overall progress. This paper discusses how EVA is introduced to a real time project on Road Works. It helps to identify the schedule and/or cost overruns beforehand and thereby giving an opportunity to managers in identifying and controlling problems. This study addresses both the costs and the benefits of earned value. The earned value concepts and the related criteria are considered.

      KeywordsEVA, Road Works, schedule overruns, cost overruns

      Earned Value

      Earned Value (EV) is a snapshot of work progress at a given point in time. Also known as the Budgeted Cost of Work Performed (BCWP),it reects the amount of work that has actually been accomplished to date (or in a given time period), expressed as the planned value for that work.

      Actual Cost

      Actual Cost (AC), also known as the Actual Cost of Work Performed (ACWP), is an indication of the level of resources that have been expended to achieve the actual work performed to date (or in a given time period).

      1. INTRODUCTION

        Feedback is critical to the success of any project. Timely and targeted feedback can enable project managers to identify problems early and make adjustments that can keep a project on time and on budget. Earned Value analysis is a method of performance measurement. Earned Value Management (EVM) has proven itself to be one of the most effective performance measurement and feedback tools for managing projects. It enables managers to close the loop in the plan-do- check-act management cycle. EVM has been called management with the lights on because it can help clearly and objectively illuminate where a project is and where it is going as compared to where it was supposed to be and where it was supposed to be going.EVM provides organizations with the methodology needed to integrate the management of project scope, schedule, and cost.

        1. Concept of EVA

          Earned Value Management (EVM) relies on three key data points:

          • Planned Value

          • Earned Value

          • Actual Cost Planned Value

        Planned Value (PV) describes how far along project work is supposed to be at any given point in the project schedule.It is

        Also known as Budgeted Cost of Work Performed (BCWP)

        Fig 1 : Standard Earned Value Analysis Graph

        Schedule Variance (SV) is the difference between the planned value of the work scheduled and the value of the work accomplished for the same time phase. It displays objectively how much the project is ahead or behind schedule.

        SV= EV PV (1)

        SV > 0, ahead of schedule SV < 0, behind of schedule

        Cost Variance (CV) is defined as the difference between the values of the work accomplished and the actual cost incurred to perform the work; and utilizing this parameter, the percentage of cost overrun or under run can be calculated.

        CV= EV AC (2)

        CV > 0, under budget CV < 0, over budget

        Schedule Performance Index (SPI) is an index showing the efficiency of the time utilized on the project.

        SPI = EV/PV (3)

        SPI > 1, efficiency in utilizing the time allocated to the project is good

        SPI < 1, efficiency in utilizing the time allocated to the project is poor

        Cost Performance Index (CPI) is an index showing the efficiency of the utilization of the resources allocated to the project.

        CPI = EV/AC (4)

        CPI > 1, efficiency in utilizing the resources allocated to the project is good

        CPI < 1, efficiency in utilizing the resources allocated to the project is poor

        Budget at Completion (BAC) is the cost of total estimated work in the plan, located at the end of the PV curve.

        Estimate to Complete (ETC) is the estimated cost required to finish all the remaining work, calculated when the past estimating assumptions become invalid and a need revised estimates.

        ETC = (BAC EV) / CPI (5)

        Estimate at Completion (EAC) is the projected final cost required to finish the complete work and based on a statistical prediction using the performance indices.

        EAC = BAC / CPI

        Variance at Completion (VAC) is the variance on the total budget at the end of the project. It is the difference between what the project was originally planned to cost, versus what it is now estimated to cost.

        VAC = BAC EAC (7)

        Time Estimate at Completion (EACt) (When are we likely to nish work?)

        Using the Schedule Performance Index (SPI) and the average Planned Value (PV) per unit of time, the project team can generate a rough estimate of when the project will be completed, if current trends continue, compared to when it was originally supposed to be completed

        EACt = (BAC/SPI)/ (BAC/months) (8) To-Complete Performance Index (TCPI)

        (How efciently must we use our remaining resources?)

        Another very useful index is the To-Complete Performance Index (TCPI), which helps the team determine the efciency that must be achieved on the remaining work for a project to meet a specied endpoint, such as the Budget at Completion (BAC) or the teams revised Estimate at Completion (EAC).

        • To determine if the cost, schedule, and work accomplished are progressing in accordance with the plan.

        • To identify potential problem areas creating delays and cost over-runs and take necessary actions for their rectification.

      2. SCOPE

        • Paper focuses on the EVA done on a real time project on Road Works.

        • Scope of the research is to throw light on the existing developed technique on EVA using MSP to measure and forecast project performance.

        • Paper does not take in to consideration certain aspects like Risk Analysis, Quality or Technical Performance of project.

        • EVA parameters, variances and indices helped the project perform better by providing early warning to detect deficient or endangered progress.

      3. METHODOLOGY

        The methodology of this paper is shown in the following flow diagram

        Literature Review and elaborate study on Earned Value Management System.

        Literature Review and elaborate study on Earned Value Management System.

        Data collection for different road works based on Cost and Schedule.

        Data collection for different road works based on Cost and Schedule.

        Defining Work Breakdown Structure

        Defining Work Breakdown Structure

        Estimating the resources required by calculating material consumption, preparing detailed rate analysis etc.

        Estimating the resources required by calculating material consumption, preparing detailed rate analysis etc.

        Assigning resources to each activity and tracking the project in MSP

        Assigning resources to each activity and tracking the project in MSP

        Performing Earned Value Analysis

        Performing Earned Value Analysis

        Conclusions based on the results obtained

        Conclusions based on the results obtained

        II. OBJECTIVE

        Deviations identified and warning signals formulated.

        Deviations identifid and warning signals formulated.

          • To provide an efficient management control system for the firm whose projects are being considered for this thesis.

        • To provide an opportunity for the PM to make sure that the project is on time and on budget.

        The first step is collecting the existing research papers and analyzing in details the work done on earned value analysis also collecting maximum details about the same from the internet. Followed by an elaborate study.

        Second step includes visiting a reputed firm and collecting cost and schedule data of some ongoing projects required for this thesis work so that EVA could be done and conclusions useful for the firm could be drawn.

        Third step is defining the Work Breakdown Structure. This could be done with the help of BOQ obtained from the firm.

        Fourth step consist of preparing the Material Consumption sheet, Detailed Rate Analysis sheet etc. Help is taken from DSR, DAR and RA bills.

        Fifth step includes use of software called MSP.Activities are defined and durations are provided. Then Resources and related cost are assigned, Baselines are created and scheduling is done.

        Sixth step is the application of EVA so as to analyse the project performance.

        Seventh step consist of obtaining the results and drawing conclusions. It is identified whether the project is over or under budget, behind or ahead of schedule, good or poor performance.

        Last but not the least deviations are taken into consideration and PMs are given potential warnings so that necessary actions could be taken before it becomes too late.

      4. APPLICATION OF EVA

        Earned Value Analysis is done on a road work project in Mumbai. The contract for this work is taken by a reputed firm named Swastik Infra Logics India Pvt Lmt.The work is in progress and earned value analysis is done at a certain point of time. Based on the analysis result, the efficiency with which the work is done and the rate at which the work will get completed is obtained. It also shows whether the firm will make profit or loss if work is continuing at the present manner with respect to what was originally planned.

        1. Planning And Scheduling

          The first stage of project is Planning. Proper planning consists of identifying each activities and assigning proper durations to each.

          Duration = Total quantity of work

          (Quantity of work done by labour, equipment, material)

          Scheduling which is the second stage is the process of determining the sequential order of activities and assigning planned duration.

        2. Detailed Rate Analysis And Material Consumption

          Rate Analysis

          In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item. This process of determining the rates of an item is termed as analysis of rates or rate analysis.

          The rate of particular item of work depends on the following:

          1. Specifications of works and material about their quality.

          2. Quantity of materials and their costs.

          3. Cost of labours and their wages.

          4. Location of site of work and the distances from source and conveyance charges.

          5. Overhead and establishment charges

          6. Profit

            Material Consumption Report

            Material consumption is calculated in order to determine the exact quantities of raw materials required for each items in the project and to determine the overall cost inquired by materials.

            The materials consumption report is a document used to summarize the goods used during a specific accounting period.

            This also helps in determining the percentage of cost that would be acquired by materials in the total budget of the required project .

        3. Detailed Application In Project

        Name of work: Resurfacing of internal roads in Sectors 1, 7, 8, 9, 10 & 13 at New Panvel (West), Navi Mumbai.

        Estimated cost of Work as per Tender: Rs. 6, 39, 11,103.45

        Completion Period: 15 months (Including monsoon)

        1. Creating WBS, inputting activity durations, Start- Finish dates and Predecessors in MSP

        2. Preparing Detailed Rate Analysis and Material Consumption

        3. Identifying and Assigning the resources and expenses to each tasks

        4. Performing Earned Value Analysis

        5. Results and conclusions

        Parameters

        Results

        C.V (Rs)

        12,77,247.14

        C.V %

        29

        S.V (Rs)

        1,53,375.14

        S.V %

        4

        CPI

        1.4

        SPI

        1.04

        BAC (Rs)

        6,57,82,615.04

        EAC (Rs)

        4,68,90,535.41

        VAC (Rs)

        1,88,92,082.63

        EAC(t) (month)

        14.43

        TCPI

        0.98

        This Project has a favorable C.V % = 29%.This means that the project is 29% under budget for the work performed.

        The Project has a favorable S.V% = 4%.This indicates that the project is 4% ahead of schedule.

        The Project has a favorable CPI of 1.4. This means that for every rupee spent, 1.4 rupee in earned value is accomplished.

        This Project has a favorable SPI of 1.04. This means that for every rupee worth of project planned to accomplished,

        1.04 rupee worth of work is accomplished.

        The project is estimated to get completed in 14.43 months if the current consistence of work is followed.

        VAC is Rs.18892082.63 which is the profit the contractor is predicted to make.

        Then project has a TCPI of 0.98 which means that the remaining resources must be used at an efficiency of 0.98 worth of every one rupee spent.

      5. CONCLUSION

Practicing Earned Value Management (EVM) can help project stay on time and on budget. It often produces valuable insight to organizations. However, many find it difficult to empirically quantify the financial benefit of implementing EVMS.For a project controls organization, EVMS can provide valid benefits like the integration of work, schedule, and cost; early warning signals through CPI and SPI; and an index- based method to forecast the final cost of the project.

Some of the benefits of EVA needed for effective project management which we can understand from this thesis are:

  • Biggest benefit to implementing EVM is that it is a single system that can track the project in terms of work, time and money; Project managers do not have to learn multiple systems.

  • EVM can measure the amount of work actually completed; forecast the cost and completion date; compare the actual performance of the project versus the plan; and track the project's budget in real time.

  • Variance is an examination used in EVM of what caused a difference between the projected baseline and the actual performance.

  • The variance can show how far away the project is from "normal." It can also help track down the root of the problem.

  • Performance Indices helps determine the current status of the project, be early warning signals if the project goes off track and estimate the total cost and time frame.

  • The SPI measures all of the work completed on the project and calculate whether the project will meet, beat or miss its planned finish date.

  • The CPI measures cost efficiency for the work completed. Simply put, it can tell you if your project is under or over budget at any point during the process.

  • When the results obtained show that changes are needed, the project manager can adjust the work or budget to help bring he future performance of the project back in line with projections.

  • EVM allows for changes to be made in a flexible, timely manner at any point during the project's development and implementation.

REFERENCES

  1. Hong Long Chen, Wei Tong Chen and Ying Lien Lin, Earned value project management: Improving the predictive power of planned value International Journal of Project Management, Science Direct, January 2016, Vol.34, PP 22-29.

  2. Sandhya Suresh, Ganapathy Ramasamy N Analysis of Project Performance Using Earned Value Analysis International Journal of Science, Engineering and Technology Research , April 2015 ,Vol. 4, PP 1080-1085.

  3. B. Prakash Rao,Jacob Cherian Earned Value Analysis On An Ongoing Residential Building Project In Bangalore, India, International Research Journal of Engineering and Technology, June 2015,Vol. 02 , PP 317-319.

  4. Arun Dhawale, Vaishnavi Tuljapurkar Cost Control and Tracking of A Building by Earned Value Method International Journal of Technical Research and Applications, April 2015, Vol.3, PP 15-22.

  5. Amitkumar R. Jamdar, Pranay R. Khare EVMS for Cost Management of Residential Projects International Journal for Scientific Research & Development, 2015, Vol.06, PP 4-6

  6. Fernando Acebes, José Manuel Galán and Adolfo López- Paredesa, Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring Procedia – Social and Behavioral Sciences,

    ,Science Direct 2013,Vol.74, PP 181-189.

  7. Sagar K. Bhosekar, Gayatri Vyas, Cost Controlling Using Earned Value Analysis in Construction Industries International Journal of Engineering and Innovative Technology, April 2012,Vol.1, PP 324-332

Leave a Reply