ATC Enhancement Through Optimal Location and Sizing of FACTS Devices Using BB-BC Algorithm

DOI : 10.17577/IJERTV2IS3394

Download Full-Text PDF Cite this Publication

Text Only Version

ATC Enhancement Through Optimal Location and Sizing of FACTS Devices Using BB-BC Algorithm

S. Sakthivel

Associate Professor

Department of Electrical and Electronics Engineering

V.R.S. College of Engineering and Technology Villupuram, Tamil Nadu, India.

P. Mathiazhagi

UG Scholar

Department of Electrical and Electronics Engineering

V.R.S. College of Engineering and Technology Villupuram, Tamil Nadu, India.

T. K. Archana

UG Scholar

Department of Electrical and Electronics Engineering

V.R.S. College of Engineering and Technology Villupuram, Tamil Nadu, India.

ABSTRACT

In an open power market, sufficient transmission capability should be made available for satisfying the demand of increasing power transactions. Certain methodologies are to be developed to enhance the power handling capacity of existing transmission lines. In this work, power flow pattern is changed by transformer tap settings and reactance of TCSCs to enhance ATC of a system. Flexible AC transmission System (FACTS) devices are inserted in electrical systems to enhance power transfer capability. Thyristor controlled series compensator (TCSC) is highly helpful in enhancing the power carrying capacity of a line by adjusting its reactance. The location and sizing of TCSC is the major issue in optimizing the benefits. The recently developed metaheuristic algorithm of Big Bang-Big Crunch (BB-BC) algorithm is proposed for optimizing the location and size of TCSC devices. The algorithm is with less number of parameters and can be easily implemented for practical applications. The proposed algorithm is tested on the standard IEEE 30 bus system and results obtained are really satisfactory.

  1. INTRODUCTION

    Power system networks across the world are undergoing tremendous changes to meet the growing power demand and to improve the quality of power supply. Deregulation of electric power system networks is one such changes and it ensures cheap power to the consumers. Deregulation poses several challenges that are to be solved. Insufficient transmission capability is the major challenge to be addressed [1]. Usually, there is mismatch between construction of power plants and transmission systems [2]. This is due to several socio-

    economic reasons. Sufficient transmission capability may be provided by enhancing the capability of existing transmission lines.

    One of the possible ways to improve the capability of a transmission line is to use FACTS devices [3]-[4]. The insertion of FACTS devices extends the possibility that current through a line can be controlled at a reasonable cost, enabling large potential of increasing the capacity of existing lines, and use of one of the FACTS devices to enable corresponding power to flow through such lines under normal and contingency conditions. Several studies [5] have found that FACTS technology not only provides solutions for efficiently increasing transmission system capacity but also increases ATC, relieve congestion, improve reliability and enhances operation and control.

    The benefits of FACTS devices are maximized by optimizing their location and parameters [6]. However, it is hard to determine the optimal location and sizing of FACTS devices. Therefore a suitable optimizing technique is necessary. Recently several optimization algorithms are proposed and exploited for many power system operation optimization [7]-[8].

    A method based on continuation power flow [9] incorporating limits of reactive power flows, voltage limits as well as voltage collapse and line flow limits is described. However, with this method the computational effort and time requirement are large. For very large systems, the method may be quite cumbersome. The localized linearity of the system is assumed and additional load required to hit the different limits are separately calculated and the minimum of all these is taken as ATC.

    The task of calculating ATC is one of the main concerns in power system operation and planning. ATC is determined as a function of increase in power transfers between different systems through prescribed interfaces. Methods available for ATC calculations include Repeated Power Flow (RPF) and Continuation Power Flow (CPF) based methods [10]-[11], Sensitivity based methods [12] and Optimal Power Flow (OPF) based methods [13].

    ATC can also be calculated by using the power flow distribution factors. The distribution factors may be calculated using AC power flow or DC power flow solutions. The DC power transfer distribution factors (DCPTDFs) are derived based on DC load flow assumptions and hence are provide less accurate results [14]. The AC power transfer distribution factors [15]-

    [16] (ACPTDFs) are more accurate and provides acceptable ATC values.

    FACTS devices are highly useful in enhancing ATC of a power system. Series connected FACTS devices are more suitable than shunt connected FACTS devices for ATC enhancement. TCSC is a series connected FACTS device which is used in this work ATC enhancement. Insertion of TCSC can increase ATC when it is located in any line. But the benefits of TCSC can be maximized by optimizing its location and size [17]-[18]. The BB- BC algorithm is exploited in this work for the optimization of TCSC parameters.

  2. MODELLING OF TCSC DEVICE

    TCSC is a low cost but rapid response FACTS controller and is a series connected FACTS device that decreases or increases the effective line reactance, by adding a capacitive or inductive reactance correspondingly. TCSC is highly suitable for line flow control by changing the transfer reactance of the line. The TCSC is modelled as a variable reactance, where the equivalent reactance of line Xij is defined as:

    = + 1

    where, Xline is the transmission line reactance before insertion of TCSC, and XTCSC is the TCSC reactance. The degree of the applied compensation of the TCSC usually varies between 20% inductive and 80% capacitive to avoid over compensation (0.8XLine XTCSC 0.2XLine ) . The load flow studies model of a TCSC is shown in figure 1.

    Bus i

    XL

    XTCSC

    Bus j

    Bi Bj

    Fig 1. Model of TCSC

    The addition of TCSC changes only the elements corresponding to the buses i and j of the admittance matrix and therefore modelling of TCSC for load flow studies is simple.

  3. ATC ENHANCEMENT PROBLEM STATEMENT

    1. ATC

      ATC is the transmission capability available for further transactions in a deregulated power market. ATC is a measure of the transfer capability remaining in the physical transmission network for further commercial activity over and above the already committed uses. It can be expressed as follows:

      ATC = TTC Existing Transmission Commitments 2

      Where, Total Transfer Capability (TTC) is defined as the amount of electric power that can be transferred over the interconnected transmission network or particular path or interface in a reliable manner while meeting all of a specific set of defined pre and post contingency conditions. ATC at the base case, between bus m and bus n using line flow limit (thermal limit) criterion is mathematically formulated using ACPTDF as given in the below equation:

      = min , , 3

      Where Tij, mn denotes the transfer limit values for each line in the system. It is given by the following equation:

      0

      ; , . > 0

      , =

      ,

      ; , = 0

      4

      0

      ; , < 0

      ,

      Where the following holds true:Pijmax is the MW power limit of a line between bus i and j. Pijo is the base case power flow in line between bus i and j.NL is the total number of lines. ACPTDFij,mn is the power transfer distribution factor for the line between bus i and j when a transaction is taking place between bus m and n. ACPTDF as given in equation (3) is operating point dependent and was computed using Jacobian inverse. ACPTDFs remain fairly

      constant for reasonable variations in power injections.

    2. ACPTDF Formulation

      ACPTDF is based on the results of AC power flow solutions. ACPTDF values provide a linearized approximation of how the flow on the transmission lines and interfaces change in response to transaction between the seller and the buyer. Considering a bilateral transaction tk between a seller bus m and buyer bus n, line l connected between bus i bus j carries a part of the transacted power. For a change in real power in the transaction between the above buyer and seller by tk MW, if the change in a transmission line quantity ql is q1 , power transfer distribution factors can be defined as follows:

      ,

      =

      5

    3. Objective function

      The objective of this work is to increase the total transfer capability a power system for realizing more number of power transactions by changing the power flow pattern.

      Equality constraints

      Power balance equations

      cos = 0 6

      =1

      sin = 0

      =1

      7

      Where, and are the real power generation and load at bus i; and are the reactive power generation and load at bus i.

      Inequality constraints

      Line real power flow limit

      , 8

      TCSC reactance limit

      max 9

      Bus voltage magnitude limit

      10

  4. BB BC ALGORITHM

    1. Overview

      A new nature inspired optimization technique which has low computational time and high convergence speed called BB-BC is introduced recently [17]-[18]. It has two phases,

      1. Big bang phase and 2. Big crunch phase.

      In Big Bang phase, candidate solutions are randomly distributed over the search space and in the Big Crunch phase, randomly distributed particles are drawn into an orderly fashion.

      The Big Bang-Big Crunch optimization method generates random points in the Big Bang phase and shrinks these points to a single point in the Big Crunch phase after a number sequential Big Bangs and Big Crunches.

      The Big Crunch phase has a convergence operator that has many inputs but only one output, which is named as the centre of mass, since the only output has been derived by calculating the centre of mass. The point representing the centre of mass is denoted by Xc and is calculated according to the following equation.

      1

      = =1

      1

      =1

      11

      Where Xi is the ith candidate in an D-dimensional search space, f(Xi) is a fitness function value of this point, NP is the population size in Big Bang phase.

      After the Big Crunch phase, the algorithm creates new candidates to be used as the Big Bang phase of the next iteration step. This can be done in various ways, the simplest one being identifying the best candidate in the population. In this work, the new candidates are generated around the centre of mass and knowledge of centre of mass of previous iteration is used for better convergence. The parameters to be supplied to normal random point generator are the centre of mass of the previous step and the standard deviation. The deviation term can be fixed, but decreasing its value along with the elapsed iterations produces better results.

      = +

      12

      Where r is a normal random number, is a parameter limiting the size of the search space, Xmax and Xmin are the upper and lower limits, and t is the iteration step. Since normally distributed numbers can be exceeding ±1, it is necessary to limit the population to the prescribed search space boundaries. This narrowing down restricts the candidate solutions into the search space boundaries.

    2. BB-BC applied to ATC maximization:

      Big Bang Big Crunch algorithm involves the steps shown below in reactive power flow control

      Step 1: Form an initial generation of NP candidates in a random manner respecting the limits of search space. Each candidate is a vector of all control variables, i.e. [Tk, XTCSC]. There are 4 Tks and 2 XTCSC in the IEEE-30 system and hence a candidate is a vector of size 1×6.

      Step 2: Calculate the fitness function values of all candidate solution by running the NR load flow. The control variable values taken by different candidates are incorporated in the system data and load flow is run. The total line loss corresponding to different candidates are calculated.

      Step 3: Determine the centre of mass which has global best fitness using equation (11). The candidates are arranged in the ascending order their fitness (fitness) and the first candidate will be the candidate with best fitness (minimum loss).

      Step 4: Generate new candidates around the centre of mass by adding/subtracting a normal random number according to equation (12). It should be ensured that the control variables are within their limits otherwise adjust the values of r and .

      Step 5: Repeat steps 2-4 until stopping criteria has not been achieved.

      Start

      Initialize the population within the limits

      Initialize the population within the limits

      Calculate the fitness of each agent

      Calculate the fitness of each agent

      Gen=Gen+1

      Gen=Gen+1

      Identify the centre of mass

      Form the new agents around the centre of mass

      Form the new agents around the centre of mass

      Run NR load flow and calculate the fitness

      Run NR load flow and calculate the fitness

      Is gen<= max gen?

      Print the global best

      Print the global best

      Stop

      Figure 2. Flow chart for BB-BC algorithm

  5. RESULTS AND DISCUSSIONS

    The proposed BB-BC algorithm based ATC enhancement problem is tested on the standard IEEE-30 bus test system [19]. System data are on 100MVA base. Bus 1 is taken as the reference bus. The base load condition is considered. The algorithm is coded in MATLAB

    7.6 language tool. The test system has the following parameters.

    Table 1. System parameters

    Sl.No

    Variables

    Quantity

    1

    Buses

    30

    2

    Branches

    41

    3

    Generators

    6

    4

    Shunt capacitors

    2

    5

    Tap-Changing transformers

    4

    The system has 4 transmission lines with tap changer transformers. For insertion of TCSC only the lines without tap changer transformer are taken as candidate locations. ATC enhancement is done by adjusting tap positions of the 4 transformers and reactmce of 2 TCSCs.

    Figure 3. Single line diagram of the test system

    Two bilateral transactions are considered for proving the efficiency the proposed BB-BC based algorithm for ATC enhancement. The first transaction is from generator bus 2 to load bus 29 and the second transaction is from generator bus 5 to load bus 24. The results obtained in these two transactions are discussed below.

    Transaction-1: Bus 2-Bus 29

    Bus 2 is the GENCO and bus 29 is the DISCO in this transaction. 10 MW power transaction is considered. ATC available before optimization was only 1.1239 MW. This is a low value of ATCof the system and needs to be enhanced. ATC is enhanced by adjusting the transformer tap positions and properly setting the values for TCSC parameters.

    The BB-BC algorithm is run with 50 individuals and for 200 iterations. The algorithm takes line 22-24 and line 4-6 as suitable locations for ATC enhancement. Table 2 compares the ATC values before and after insertion of TCSCs. ATC of the system is improved from 1.1239 MW to 1.74 MW.

    Table 2. Optimal values of transformer tap settings (Bus 2-Bus 29)

    Sl no

    Transformer tap

    Before

    After

    1

    T6-9

    1.078

    1.0306

    2

    T6-10

    1.069

    1.0567

    3

    T4-12

    1.032

    1.1000

    4

    T28-27

    1.068

    0.9000

    Table 3 indicates the size and location of the two TCSCs used. In this case both TCSCs are operated in capacitive mode.

    Table 3. Optimal settings of FACTS devices (Bus 2-Bus 29)

    Sl. No

    Transaction Between buses

    ATC

    without TCSC

    ATC

    with TCSC

    Location of TCSCs

    Degree of compensation

    TCSC1

    TCSC2

    TCSC1

    TCSC2

    1

    2-29

    1.1239

    1.7400

    21-23

    1-3

    -0.4829

    -0.7176

    ATC enhancement results in changed power flows through the lines. Table 4 compares the power flow before and after optimization. Line 1 is relieved much from nearly overloaded condition and the underutilized lines are forced to carry increased power. Line flow limits of all the lines are respected.

    Table 4. Line power flows (Bus 2-Bus 29)

    Line number

    Flow (before)

    Flow (after)

    MVA

    limit

    Line number

    Flow (before)

    Flow (after)

    MVA

    limit

    1

    121.130

    97.524

    130

    22

    7.105

    6.205

    16

    2

    60.881

    83.129

    130

    23

    3.827

    2.958

    16

    3

    29.841

    14.670

    65

    24

    5.689

    -6.549

    32

    4

    56.957

    77.797

    130

    25

    7.974

    8.870

    32

    5

    46.125

    40.743

    130

    26

    3.459

    5.149

    32

    6

    40.853

    28.732

    65

    27

    19.733

    18.229

    32

    7

    48.207

    60.256

    90

    28

    9.797

    5.187

    32

    8

    0.977

    -4.206

    70

    29

    2.041

    0.563

    32

    9

    21.967

    27.235

    130

    30

    7.592

    4.098

    16

    10

    14.403

    14.160

    32

    31

    9.705

    5.164

    16

    11

    14.569

    12.513

    65

    32

    6.311

    1.441

    16

    12

    12.193

    10.723

    32

    33

    7.094

    -2.155

    16

    13

    20.000

    -20.000

    65

    34

    3.559

    3.547

    16

    14

    34.569

    32.513

    65

    35

    3.416

    -6.011

    16

    15

    30.098

    23.662

    65

    36

    29.013

    27.470

    65

    16

    20.000

    -20.000

    65

    37

    19.826

    11.842

    16

    17

    8.854

    7.585

    32

    38

    12.573

    9.334

    16

    18

    20.797

    17.429

    32

    39

    1.298

    1.544

    16

    19

    9.247

    7.448

    32

    40

    4.379

    4.136

    32

    20

    2.534

    1.305

    16

    41

    24.751

    23.466

    32

    21

    5.603

    3.889

    16

    —-

    —–

    ——

    The optimization is carefully achieved that the change in power flow pattern does not result in much increased line losses.

    Transaction 2: Bus 5-Bus 24

    This bilateral transaction is between GENCO 5 and DISCO 24. ATC before insertion of TCSC was 2.2251 MW. Optimization of control parameter values (table 5) maximized the ATC to 3.5287 MW.

    Table 5. Optimal values of transformer tap settings (Bus 5-Bus 24)

    Sl no

    Transformer tap

    Before

    After

    1

    T6-9

    1.078

    1.0730

    2

    T6-10

    1.069

    1.0923

    3

    T4-12

    1.032

    0.9592

    4

    T28-27

    1.068

    1.0986

    In this case one TCSC is in capacitive mode and the other one is in inductive mode. Table 6 shows the optimal location and size of TCSCs.

    Table 6. Optimal settings of FACTS devices (Bus 5-Bus 24)

    Sl. No

    Transaction Between buses

    ATC

    without TCSC

    ATC

    with TCSC

    Location of TCSC

    Degree of compensation

    TCSC1

    TCSC2

    TCSC1

    TCSC2

    1

    5-24

    2.2251

    3.5287

    3-4

    1-3

    0.1927

    -0.4823

    Line MVA flows are compared in table 7. Line 1 carries only 77.076 MVA against 121.130 MVA after optimization. This is a much relief for the line from congestion and it is left with sufficient capability. This relief ensures adequate transmission corridor and still more transaction are also possible.

    Table 7. Line power flows (Bus 5-Bus 24)

    Line number

    Flow (before)

    Flow (after)

    MVA

    limit

    Line number

    Flow (before)

    Flow (after)

    MVA

    limit

    1

    121.130

    77.076

    130

    22

    7.105

    7.570

    16

    2

    60.881

    67.615

    130

    23

    3.827

    4.270

    16

    3

    29.841

    27.650

    65

    24

    5.689

    -5.256

    32

    4

    56.957

    63.338

    130

    25

    7.974

    7.527

    32

    5

    46.125

    67.315

    130

    26

    3.459

    2.983

    32

    6

    40.853

    39.371

    65

    27

    19.733

    17.496

    32

    7

    48.207

    50.832

    90

    28

    9.797

    7.618

    32

    8

    0.977

    -18.869

    70

    29

    2.041

    -0.144

    32

    9

    21.967

    2.368

    130

    30

    7.592

    7.930

    16

    10

    14.403

    11.586

    32

    31

    9.705

    7.554

    16

    11

    14.569

    11.341

    65

    32

    6.311

    4.382

    16

    12

    12.193

    10.083

    32

    33

    7.094

    1.769

    16

    13

    20.000

    -20.000

    65

    34

    3.559

    3.558

    16

    14

    34.569

    31.341

    65

    35

    3.416

    -1.807

    16

    15

    30.098

    31.611

    65

    36

    29.013

    15.180

    65

    16

    20.000

    -20.000

    65

    37

    19.826

    6.228

    16

    17

    8.854

    9.220

    32

    38

    12.573

    7.141

    16

    18

    20.797

    21.347

    32

    39

    1.298

    3.715

    16

    19

    9.247

    9.843

    32

    40

    4.379

    1.566

    32

    20

    2.534

    2.886

    16

    41

    24.751

    13.649

    32

    21

    5.603

    6.130

    16

    —-

    —–

    ——

  6. CONCLUSIONS

This work proves the effectiveness of the BB-BC algorithm in ATC enhancement incorporating TCSC devices. ATC of the system is enhanced by changing the power flow pattern by inserting TCSCs and adjusting tap positions of transformers. It is obvious from the numerical results that the ATC improvement is very much encouraging. The system operator can use this method to facilitate more power transfer agreements for the future power markets. Further, all the lines in the system are left with sufficient ATC and therefore the

system becomes capable of transmitting increased amount of power flows and with sufficient security.

In a deregulated environment, the very purpose of supplying power to consumers at competitive price can be ensured. Moreover, the BB-BC algorithm is simple, has less number of parameters and it can be implemented easily.

REFERENCES

  1. B.V. Manikandan, S. Charles Raja, P. Venkatesh, Available Transfer Capability Enhancement with FACTS Devices in the Deregulated Electricity Market, Journal of Electrical Engineering & Technology, Vol. 6, No. 1, pp. 14-24, 2011.

  2. E. Hirst, U.S. Transmission Capacity: Present Status and Future Prospects, Edison Electric Institute and Office of Electric Transmission and Distribution, U.S. Department of Energy, 2004.

  3. K. S. Verma, S. N. Singh, H. O. Gupta, Facts Devices Location for Enhancement of TTC, Power Engineering Society Winter Meeting, IEEE. 2, pp. 522-527, 28 January- 1 February.

  4. H. Sawhney, B. Jeyasurya, Application of Unified Power Flow Controller for Available Transfer Capability Enhancement, Electric Power Systems Research, Vol. 69, No. 2-3, pp. 155-160, 2004.

  5. J. Weber, Efficient Available Transfer Capability Analysis using Linear Methods,

    PSERC internet seminar, UL, USA, Nov 7, 2000.

  6. S. Gerbex, R. Cherkaoui and A.J. Germond, Optimal Location of Multi-type FACTS devices by Means of Genetic Algorithm, IEEE Transactions on Power Systems, Vol. 16, No. 3, pp. 537-544, 2001.

  7. Acharya N, Mithulananthan N. Locating Series FACTS Devices for Congestion Management in Deregulated Electricity Markets, Electric Power System Research, Vol. 77, pp. 35260, 2007.

  8. M. Saravanan, S.M.R. Sulochanal, P.Venkatesh and J.P.S.Abraham, Application of Particle Swarm Optimization Technique for Optimal Location of FACTS Devices Considering Cost of Installation and System Loadability, Electric Power Systems Research, Vol. 77, No. 3-4, pp. 276-283, 2005.

  9. A. M. Leite da silva, J. G. C. Costa, L. A. F. Manso and G. J. Anders, Evaluation of Transfer Capabilities of Transmission Systems in Competitive Environments, Electrical Power and Energy systems, Vol. 26, No. 4, pp. 257-263, 2004.

  10. H. D. Chiang, A. J. Flueck, K. S. Shah, N. Balu, CPFLOW: A Practical Tool for Tracing Power System Steady State Stationary Behaviour due to Load and Generation Variation, IEEE Transactions on Power Systems, Vol. 10, pp.623-634, May 1995.

  11. G. C. Ejebe, J. Tong, G.C.Waight, J.G. Frame, X. Wang and W.F.Tenney, Available Transfer Capablity Calculations, IEEE Transactions on Power systems, Vol. 113,No. 4, pp.1521-1527, November 1998.

  12. G. C. Ejebe, J. G. Waight, M. Santos-Nieto, and W. F. Tinney, Fast Calculation of Linear Available Transfer Capability, IEEE Transactions on Power Systems, Vol. 15, pp. 11121116, Aug. 2000.

  13. G. Hamoud, Assessment of Available Transfer Capability of Transmission Systems,

    IEEE Transactions on Power systems, Vol.15, No. 1, pp.27-32., February 2000.

  14. R. D. Christie, B. F. Wollenberg, I. Wangstien, Transmission Management in the Deregulated Environment, Proc. of the IEEE, Vol. 88, No. 2, pp. 170-195, Feb. 2000.

  15. A.Kumar, S.C. Srivatsava, AC Power Distribution Factors for Allocating Power Transactions in a Deregulated Environment, IEEE Power Engineering Review, pp. 42-43, 2002.

  16. A. Kumar, S. C. Srivatsava, S. N. Singh, ATC Determination in a Competitive Electricity Market using AC Distribution Factors, Electrical Power components and Systems, Vol. 32, No. 9, pp. 927-939, 2004.

  17. K. Erol Osman, Ibrahim Eksin, New optimization method : Big Bang-Big Crunch,

    Elsevier, Advances in Engineering Software 37, pp. 106111, 2006.

  18. S. Sakthivel, D. Mary, Reactie Power Optimization Incorporating TCSC Device through Big Bang-Big Crunch Algorithm for Voltage Stability Limit Improvement, Wulfenia Journal, Vol. 19, No. 10, 2012.

  19. Power Systems Test Case, 2000, The University of Washington Archive, http://www.ee.washington.edu/research/pstca.

Author Biographies

S. Sakthivel received the Degree in Electrical and Electronics Engineering in 1999 from Madras University and Master Degree in Power Systems Engineering in 2002 from Annamalai University. He is pursuing the Ph.D., Degree in Electrical Engineering faculty from Anna University of Technology, Coimbatore, India. He is presently working as an Associate Professor in Electrical and Electronics Engineering at V.R.S.College of Engineering and Technology, Villupuram, Tamil Nadu, India. His research areas of interest are Power System control,

Optimization techniques, FACTS, Economic load dispatch, Power system deregulation and Voltage stability improvement.

P. Mathiazhagi is an undergraduate student with the Department of Electrical and Electronics Engineering at VRS College of Engineering and Technology, Villupuram, Tamil Nadu, India. Optimal power flow using evolutionary algorithms is her important area of interest.

T. K. Archana is an undergraduate student in the Department of Electrical and Electronics Engineering at VRS College of Engineering and Technology, Villupuram, Tamil Nadu, India. She is interested in power system operation optimization by using intelligent techniques.

Leave a Reply