Axle Line Capacity up-gradation by Process Planning

DOI : 10.17577/IJERTV3IS080244

Download Full-Text PDF Cite this Publication

Text Only Version

Axle Line Capacity up-gradation by Process Planning

Kamlesh Kumar Singp, Rajendra Kumar2, Rajat Upadhyaya3

1Associate Professor and Head, Department of Foundry Technology, National Institute of Foundry and Forge Technology, Ranchi, India

2,3Was M.Tech Student, National Institute of Foundry and Forge Technology,

Ranchi, India

Abstract: The demand of automobile components is increasing at a faster rate due to heavy demand of vehicles. Thus the capacity up-gradation is the basic need of manufacturing and assembly units of automobile components. The axle is the most important part of the vehicle. To increase the capacity of axle assembly, first the capacity assessment of the existing equipments was done. It was needed to introduce some more equipment either in the existing assembly line (extension line) or may be put parallel to the existing line (parallel line). These two lines are compared in terms of investment cost, number of manpower, flexibility, ease of implementation etc. and the parallel line layout is recommended. The planning was also made for assembly of 100 axles/shift for multi models LCV, MCV and HCV.

Keywords: Axle; Extension line; parallel line; process planning; capacity up-gradation; process layout; line balancing; Light Commercial Vehicle

LCV;MediumCommercialVehicleMCV;HeavyCommercialVehic leHCV.

  1. INTRODUCTION

    The capacity up-gradation is the basic need of each and every industry. This can be achieved by process planning, either by new set up or by implementing the different techniques and sorting out the bottlenecks of the existing set-up in the company. The capacity up-gradation planning is done for the fulfillment of the forecasted market demand. Planning helps in identifying the resource problem and minimizes redundancies of effort [1-11]. The major problem being faced by almost all automobile industries is the line balancing of the multi-model [12-14]. An efficient line balancing technique seeks to generate a balanced workload at multiple stations, while simultaneously reducing equipment and labors requirement [11]. Line balance helps to reduce the bottlenecks, quick identifying the constraints, reduce work overload, improve workflow etc.

    This study is being carried out for the up-gradation of Axle Line of an automobile company. This company manufactures multi Axles for Heavy Commercial Vehicle (HCV), Medium Commercial Vehicle (MCV) & Light Commercial Vehicle (LCV). Its working hour is 450 min/shift. Existing capacity of the plant was 60/shift i.e. the vehicle can be produced after every 7.5 min. Thus the cycle

    time for 60/shift is 7.5 min. and for 100/shift will be 4.5 min. Such a large increment from existing 60/shift to

    100/shift of axle assembly requires in depth study of the existing set-up. First of all, the capacity assessment of all the existing equipment was done. With this, the bottleneck for 100/shift have been identified. If the cycle time is less or equal to 4.5 minutes, the equipment will be able to produce 100 /shift. For that some additional facilities may be required e.g. machine equipments, material handling, jigs/fixture, assembly tools, line side storage & supply. Any assembly automobile company is being divided into following sub groups-

    1. Axle Line

    2. Transmission line

    3. Engine Line

    4. Cabin Line

    5. Chassis Line

    In this study emphasis is given on the capacity up- gradation of Axle line from 40/shift to 100/shift.

  2. AXLE AND AXLE LINE ASSEMBLY

    Axle is the most important component of the vehicle. It is considered as its legs and it carries complete weight of the vehicle. The weight carrying portions of the axles, whether it may be front or rear, is considered as beam supported at the ends, loaded at two intermediate points and subjected to the following loads [15-16]:

    • The vertical load at the spring centers due to the weight of the vehicle.

    • A fore and aft load at the wheel center due to driving or braking effort.

    • The torque reactions due to drive or brakes.

    • A side thrust at the radius of the tier due to centrifugal force when rounding a curve.

    The multi axle consists of three axles – Front axle, Rear Axle and Tag Axle (Dummy axle). The axle line is divided in five-sub groups-

    1. Washing Station 2)Slat conveyor 3)Hub line 4)Differential Line 5)Painting Line

      Slat conveyor is the main line of the Axle line Assembly [17-22]. Higher Axle Loads and Higher Speeds are contrary to each other. The problems that industry faces include not only multi-period

      problems, but also managing the assortment for multiple generations of products. It is futile to attempt both (High Speeds and High Axle Loads) on existing mixed traffic network. In order to determine the direction of the organization, it is necessary to understand its current position and the possible avenues through which it can pursue a particular course of action. Strategies to create additional capacity and increasing average speeds by optimum use of existing network and selectively constructing new conventional lines [23-26]. For capacity up gradation, two options will arise either the new conveyor will be set up parallel or it is to be extended after modification. By considering these two options of slat conveyor line, cost/axle was calculated.

  3. CAPACITY ASSESSMENT OF THE EXISTING EQUIPMENT

Capacity assessment of the existing equipments was done for the requirement of the additional facilities. For the calculation of output per shift the required data were noted from the company and calculation were made. A typical calculation for 62 vehicle is shown for different equipment. The process of calculation for different equipments is described:

    1. Capacity assessment of the Slat Conveyor

      1. Based on Manpower

        Throughput time of Slat Conveyor for 62 model = 107 min.

        Pitch of the fixture=0.25 meter

        Distance between the Station = 2.5 meter Length of the conveyor=17.5 meter

        No. of the effective Station = {(17.5/2.5)-1} = (7-1) = 6 Therefore, the maximum number of manpower = 62=12 (two persons at each station).

        Utilization of the manpower /vehicle=Throughput time/No. of Manpower=107/12=8.9

        Output /shift=Total working time per shift/Utilization of manpower per vehicle

        =450/8.9= 50.56

        ii Based on Speed Speed of the Conveyor= 1m/min.

        Number of the axle for 62 model =3

        Pitch between the vehicles= No. of axle pitch between fixtures = 32.5 meter =7.5 meter

        Length of the effective station = 2.5 meter

        Therefore time for assembly of one vehicle =7.5 minutes

        Table 1: Capacity Assessment of the Slat conveyor

        Parameters\ model

        10:

        59

        10:70

        10:90

        MCV

        HCV

        6X2

        THROUGHPUT

        TIME (In mins.)

        36

        35

        37

        54

        78

        107

        Pitch of the conveyor (m)

        0.25

        0.25

        0.25

        0.25

        0.25

        0.25

        Pitch of the Fixture (m)

        2.5

        2.5

        2.5

        2.5

        2.5

        2.5

        No. of the Effective Station

        6

        6

        6

        6

        6

        MANNING

        Max No. of Manpower

        12

        12

        12

        12

        12

        12

        Utilization of

        Manpower/ Vehicle (mins.)

        3.0

        2.9

        3.1

        4.5

        6.5

        8.9

        Out Put / Shift

        150

        155

        145

        100

        69

        51

        SPEED

        Max. Speed

        (m/min.)

        1

        1

        1

        1

        1

        1

        Pitch of one vehicle

        5

        5

        5

        5

        5

        7.5

        Time for one

        Vehicle

        5

        5

        5

        5

        5

        7.5

        Max. Out Put / Shift

        90

        90

        90

        90

        90

        60

        Maximum output per shift = Total working time per shift/time taken to assemble one

        Vehicle = 450/7.5 = 60

        Similarly, for other types of models, calculations were made and the results were included in Table 1.

    2. Capacity of the washing machine

There are two washing machines

i Main Washing machine for Slat conveyor ii Washing machine for Hub and Drum Line i Main Washing Machine

No. of trays used for washing one 6 2 vehicle = 5

Cycle time for one tray= 1.5 min. (As per specification of the washing machine)

Time taken to start the washing machine= 0.14 min.

Total Time involved for washing machine= 1.5

5+0.14=7.64 min.

Maximum capacity of the washing machine = Time per shift /total time for the machine

=450/7.64=58.9

Similarly, the calculation is done for different models of main washing machine and Hub-Drum Washing machine and the results are shown in Table 2(a) and Table 2 (b) respectively.

6

Capacity of

Greasing Application(Manual)

125

125

125

121

69

46

7

Capacity of Painting Only (Manually)

134

134

134

134

108

69

8

Capacity of Paint Booth

122

122

122

122

99

63

9

Capacity of Loading Gantry for Hub-

Drum Washing

152

152

152

152

114

76

10

Capacity of Unloading Gantry for Hub- Drum

Washing

148

195

195

139

139

102

11

Capacity of Loading Gantry for Main

Washing

97

97

97

97

97

79

12

Fixture For Differential Case & Case – Crown Wheel Assly (Separate

Fixture)

126

126

95

95

36

36

13

Fixture for Differential Final

Assly (separate fixture)

89

89

89

89

59

51

Table 2(a): Capacity Assessment of the Main Washing Machine

Parameters\ model

10:

59

10:70

10:90

MCV

HCV

6X2

No. of Tray Used for one Vehicle

4

4

4

4

4

5

Cycle Time (min.)

1.5

1.5

1.5

1.5

1.5

1.5

Starting Time (min.)

0.14

0.14

0.14

0.14

0.14

0.14

Total Time / Vehicle (min)

6.1

6.1

6.1

6.1

6.1

7.6

Maximum Capacity of Washing

73.3

73.3

73.3

73.3

73.3

58.9

Parameters\ model

10:

59

10:70

10:90

MCV

HCV

6X2

No. of Tray

Used for one Vehicle

4

4

4

4

4

6

Cycle Time

(min.)

1.5

1.5

1.5

1.5

1.5

1.5

Total Time / Vehicle (min)

6.0

6.0

6.0

6.0

6.0

9.0

Maximum

Capacity of Washing

75.0

75.0

75.0

75.0

75.0

50.0

Table 2(b): Capacity Assessment of the Hub Drum Washing Machine

The capacity assessments for the other equipments were also done. A summary sheet for the different models is prepared and is shown in Table 3. From Table 3, it is observed that the capacity of unloading Gantry for Hub- Drum Washing machine was approaching for 100/shift, but the capacity of other equipments was much below the required 100/shift.

Table 3: Summary Sheet of Capacity of the equipments

Therefore, it can be concluded that from the existing equipments, it was impossible to upgrade for 100/shift. For achieving the required goal, it is utmost important to include some additional equipments. Due to the addition of the equipment, there will be change in axle layout. The equipments may be either added in the existing line, making it as an extension or may be put parallel to the existing line and it may be called as a parallel line. Then there is a need for estimation of cost for these two lines.

    1. EXTENSION LINE VS. PARALLEL LINE

      The existing Axle Assembly line can be sub divided in two groups:

      1. Main Line

        Capacity of Press for Diff. Line

        Sl.No.

        Parameters\ model

        10:59

        10:70

        10:90

        MCV

        HCV

        6X2

        1

        Capacity Assessment of the Slat Conveyor —

        Man- Power

        150

        155

        145

        100

        69

        51

        Speed

        90

        90

        90

        90

        90

        60

        2

        Capacity of Washing Machine

        Main Washing Machine

        73

        73

        73

        73

        73

        59

        Hub- Drum Washing Machine

        75

        75

        75

        75

        75

        50

        3

        369

        369

        223

        223

        75

        75

        4

        Capacity of Press for Integrated Hub

        Line(HCV as Base Model)

        398

        395

        388

        157

        86

        53

        5

        Fixture for Shim Selection

        0

        0

        381

        0

        54

        36

      2. Sub Assembly Line Main Line can be further divided into three groups:

        1. Main Washing machine

        2. Slat conveyor

        3. Painting There are two sub assembly lines:

          1. Hub Drum Line

          2. Differential Line

          At the time of change of Axle Line Layout, the length of the Slat conveyor can be increased and this option may be called as an extension line. If another Slat conveyor is set up parallel to the existing slat conveyor then this option may be called as parallel line.

    2. Estimation of the cost

      The calculation of the cost is done for above two proposed assembly line (extension line and parallel line). The cost comprises:

      1. Cost of plant and machinery

      2. Cost of power consumption

      3. Cost of manpower

      4. Cost of consumables

      1. Cost of Plant and Machinery

        The cost of Plant and Machinery consists of:

        1. Land & Building Costs

        2. Equipment Costs

        3. Assembly costs

        4. Material Handling Cost

        5. Jigs and Fixture Cost

        6. Cost for Quality control facilities

        7. Line Side Storage

        8. Stores Investment etc.

        Since the cost of the existing equipment is much higher than the price at the time of purchase. Therefore, for the calculation of the cost of plant and machinery a multiplying factor of 1.5 is taken.

      2. Cost of power consumption

        For the calculation of cost of power consumption the connected load/unit is known from the specification of the equipment.

        Working hour per day = 16 Load Factor=0.3

        Quantity of the equipment=y (say)

        Rise of units per day=Connected load per unit × Load Factor × Working hours per

        day × Quantity of the equipment Cost of power per day = Rise of units per day ×cost per unit.

        Cost of power per shift = Cost of power per day/2

        The calculation of the cost of power consumption was made.

      3. Cost of Manpower

        Manpower consists of two types

        1. Permanent

        2. Temporary (casuals, apprentice, etc.)

        Let X is the total manpower involved in assembly. Let the permanent member is Y and the temporary member is

        Z.

        Cost of manpower is calculated as no. of manpower × Rate per annum in Lacs.

        Cost of manpower per day = Total cost of manpower per annum / 365

        Cost of manpower per shift = Cost of manpower per day / 2 The calculation of the cost of manpower was made.

      4. Cost of Consumables

        Cost of consumables is the variable cost and it varies with the number of vehicles produced. The cost of consumables per vehicle will remain unchanged either for parallel or extension line assembly.

        For the above calculation, the following assumptions were taken: Depreciation rate for building is taken as 3.34%.

        Depreciation rate for plant and machinery is taken as 7.24%.

        Interest on total investment is taken as 10.0%. Rate of maintenance cost for buildings = 1%.

        Rate of maintenance cost for plant and machinery = 5%. Rate of insurance cost on investment = 0.14%

        The summary sheets of the above cost calculation are shown in Table 4.

    1. Calculation of the Manpower

      Apart from the calculation of the cost, number of manpower also plays a critical role in making decision for the type of the axle line layout. The number of manpower calculation was done separately as follows:

      Throughput time on Slat conveyor for 6 2 model=107 min.

      Output of the slat conveyor=40/shift Working hour per shift = 450 min.

      Cycle Time = Working hour per shift / Output per shift

      =107/40=11.25

      Similarly for the calculation of manpower on different station are shown in Table 5.

      In parallel conveyor, one line is set for the production of 60/shift LCV/MCV and other for 40/shift HCV/6X2 models. The manpower was allocated as per maximum throughput time. The 6 2 vehicle have three axles and thus, 40 number of 6 2 vehicles is equivalent to 60 vehicles having two axles. The highest throughput time for vehicle, which has two axles, is HCV (20:16) model. For extension the manpower for same production will be according to 120/shift HCV (20:16 model).

      Table 4: Axle Aggregate Cost Summary

      Sl. No

      Catego ry

      Uni t

      Existi ng

      Para llel

      Exten sion

      Peak

      Volum es

      16000

      6000

      0

      60000

      Cost Head

      Total Per Annu m

      Per Axle

      Total Per Annu m

      Pe r A

      xl e

      Tota l Per Ann um

      Pe r A

      xl e

      Invest ment

      1.

      Land Cost

      Rs.

      0.0

      0.0

      2.

      Buildin g

      Rs.

      98080

      00

      15952

      000

      1146

      0000

      3.

      Plant & Machin

      ery

      Rs.

      25051

      038

      38475

      096

      3971

      1540

      Total

      Invest ment

      34859

      038

      54427

      096

      5117

      1540

      A

      Deprec iation

      A.1

      Deprec iation for Buildin

      g

      %

      3.34

      %

      3.34%

      3.34

      %

      Rs.

      32758

      7.0

      20.47

      53279

      6.8

      8.

      8

      3827

      64

      6.

      38

      A.2

      Deprec iation for Plant & Machin

      ery

      %

      7.24

      %

      7.24%

      7.24

      %

      Rs.

      18136

      113.3

      27855

      46

      2875

      47

      95.2

      6

      97

      .4

      11.

      .9

      Total

      Deprec iation

      Rs.

      21412

      82.4

      133.8

      3

      33183

      93.8

      55

      .3

      3257

      879

      54

      .3

      B

      Interest

      B1.

      Interest on Total Invest

      ment

      %

      10%

      10%

      10%

      Rs.

      34859

      03.8

      217.8

      7

      54427

      09.6

      90

      .7

      5117

      154

      85

      .2

      Fixed Cost

      Rs.

      56271

      86.2

      351.7

      0

      87611

      03.4

      14

      6

      8375

      033

      13

      9

      C

      Power

      Per Annum

      Rs.

      23086

      80

      144.2

      9

      40871

      95

      68

      .1

      3309

      293

      55

      .1

      D

      Manpo wer Per

      Annum

      Rs.

      71186

      53.3

      444.9

      2

      79507

      38.2

      13

      2

      8974

      766

      14

      9

      E

      Indirec t Consu mable

      Per Annum

      Rs.

      59690

      3.1

      37.31

      22383

      86.5

      37

      .3

      2238

      386.

      37

      .3

      F

      Mainte nance Cost

      Per Annum

      Bld g.

      %

      1%

      1%

      1%

      P & M

      %

      5%

      5%

      5%

      Rs.

      13506

      31.9

      84.41

      20832

      74.8

      34

      .7

      2100

      177

      35

      G

      Insuran ce Cost on Invest

      ment

      %

      0.14

      %

      0.14%

      0.14

      %

      Rs.

      45804

      .9

      2.86

      71552.

      2

      1.

      19

      6707

      9.1

      1.

      12

      Variabl e Cost

      Rs.

      11421

      928

      713.8

      7

      16433

      071

      27

      3

      1669

      170

      27

      8

      Total

      Annual Cost

      Rs.

      28469

      787.

      1779.

      4

      41625

      321.1

      69

      3

      4175

      644

      69

      5

      Cost / Axle

      Set (2 Nos.)

      Rs.

      890

      347

      348

      Merits of the Parallel Conveyor:-

      1. Saving of the Manpower (Table 5)

      2. Production will not stop while implementation.

      3. Speed to the Pitch ratio in parallel is less while working, therefore ease of working on the Conveyor.

      4. Incase Front, Rear and Tag Axle are offloaded then assets can be fully utilized.

      Demerits of the Parallel Conveyor:

      • Larger area as compared to the Extension line. Demerits of the Extension:

      1. More manpower is required.

      2. Production stopped while implementation.

      3. Speed to pitch ratio is high therefore difficulties may take place while assembly

      4. Drainage modification may be required.

      5. Further, in extension, additional Paint booth as well as Washing machine was needed. It will increase the problem of material handling.

      The above-mentioned points discussed are given a weighted score. Rating was given to each point according to the easiness, pros and cons of implementation. The type, which has scored more, has been taken into consideration. As per basis of KT matrix (Table 6) parallel conveyor was proposed.

      Existing

      Option 1 (Parallel)

      Option 2 (Extension)

      MCV

      6×2

      Total

      Tot al (HC

      V)

      Capacity

      60

      60

      40

      120

      Cycle Time /

      Vehicle (in Mins.)

      7.50

      7.50

      11.25

      3.75

      Throughput Time (in

      Mins.)

      Main Washing

      Machine

      8.91

      8.82

      12.25

      Slat Conveyor

      78.08

      56.53

      115.09

      Painting

      9.36

      7.86

      14.41

      Differenti al

      Washing

      7.12

      6.17

      8.12

      Differenti

      al Line

      35.89

      15.05

      33.71

      Hub & Drum

      Washing

      7.02

      6.48

      10.71

      Hub Line

      34.15

      16.67

      55.21

      Knuckle

      Assly

      8.12

      Shock Abs. Bkt.

      Welding

      5.47

      5.47

      TOTAL TPT

      194

      123

      250

      194

      Manpower on 2 Shift Basis

      Table-5: Calculation of the manpower

    2. Comparison between Extension and Parallel Line

For the comparison between the parallel and extension, following parameters were taken:

  1. Aggregate cost per axle.

  2. Number of manpower.

  3. Investment

  4. Incase front, rear or tag Axle off loaded in future.

  5. Flow of Aggregates

  6. Stoppage of current production Line The merits and demerits of both options are discussed below:

    Rating Basis : 1~3 Poor, 4~6 just below requirement , 7~8 Meets Need, 9~10 Exceeds Need

    Sl

    . N

    o.

    Parame ter

    Context

    Wei ght age

    Option 1 (parallel conveyor)

    Option 2 (Extension of Conveyor)

    Rating

    Sc ore

    Rating

    Sc ore

    1

    Aggreg ate Cost/ Vehicle (Base Front and Rear Axle of 20.16)

    compreh ensive cost which includes Capital Cost (Interest & Depreciat ion), Manpow er, Power,

    Consuma bles etc.

    9

    8

    72

    8

    72

    347

    348

    2

    No. Manpo wer

    No. of Manpow er required for 60/shift

    – MCV &

    40/Shift

    6X2

    9

    8

    72

    5

    45

    80

    103

    Less manpowe

    r required

    More manpowe

    r required

    3.

    Investm ent

    Total Investme nt required (Includin g Plant & Machiner

    y & Bldg.)

    8

    6

    48

    7

    56

    Rs. 544

    Lacs

    Rs. 512

    Lacs

    Parallel conveyor can be commissi oned without stopping productio

    n

    Drain Modific ation is required

    4

    Incase front and Tag Axle off loading in

    Future

    Utilizatio n of Assets

    8

    6

    48

    4

    32

    New conveyor

    ,

    Washing M/c, Paint Booth &

    Presses

    Extende d conveyo r can not be given to vendor

    (Per Day)

    Main Washing

    Machine

    6

    2.4

    2.2

    4.6

    Slat Conveyor

    22

    15

    20.5

    35.5

    Painting

    4

    2

    3

    5.0

    Differenti

    al Washing

    1.6

    1.4

    3.0

    Differenti al Line

    10

    4

    6

    10.0

    Hub & Drum

    Washing

    2

    1.7

    1.9

    3.6

    Hub Line

    10

    4.4

    9.8

    14.2

    Knuckle

    Assly

    2

    Shock

    Abs. Bkt. Welding

    2

    2

    2

    4.0

    Total

    58

    33

    47

    80

    Table 6: KT Matrix

    In parallel layout, there may be two options existing

    1. Hub drum line and differential line are in between both conveyors.

    2. Hub drum line and differential line are aside of both conveyors.

With the hub drum line and differential line aside of both conveyor, the distance from the slat conveyor may increase. Due to this, there may be material handling problem. Therefore, for the parallel line layout the option in which Hub drum line and differential line are in between both conveyors were taken into consideration. For this option there can be two possibilities:

  1. When the Hub drums line and differential line are also parallel to each other.

  2. When the Hub drum line and differential line are face to face.

For the option, when hub drum line and differential line are parallel to each other, then there may be criss-crossing of material handling and overhead supply. The best option of layout is when hub-drum line and differential lines are face to face and in between both the slat conveyor. The parts are to be continuously supplied to the line as per its utilization. The deciding factor for the supply is the types of parts and the number of parts used per vehicle. The line side storage also depends on the ratio of the different model to be assembled on that particular day.

output of the vehicle = N/shift, and suppose the demands for the 10:50, 10:70 and 11:10 model are in the ratio of x: y: z. Let the number of parts used for 10:50, 10:70 and 11:10 models are p, q and r respectively.

Then the number of parts supplied per shift

S= x / (x+y+z) ×N × p+ y / (x+y+z) × N × q + z / (x+y+z)

× N × r

=N/(x+y+z) ×{p×x+q×y+z×r}

Let the capacity of the Bin or Trolley=w, then the supply frequency per shift = S/w

may be

given to vendor

5

Flow of Aggreg ate

Feasibilit y for the overhead supply

Layout

8

7

56

7

56

Hub and Diff. Line will be in Between Two conveyor

, Hence feeding two conveyor

is smooth

Hub line and Diff. Line working flow will be good

Restricti on in implem enting diff. line for LCV & HCV

as availabl e width was 4m

only

7

Stoppag e of current producti on line

No vehicle loss during impleme

ntation

7

6

42

3

21

Independ ent impleme ntation without disturbin g existing productio

n

Producti on Shut down required min. one week

Total

33

8

28

2

If the S/w value is very less, then the frequency can be set for few days or even for a week. If the value of S/w is more than it can be set for number of times per shift according to need.By using above formulation, the line side storage & Frequency of supply/shift for different models were calculated.In process layout, how the work was done and how much work will be done at a particular station is mentioned. The line balancing helps in maximum utilization of the manpower. The time taken to do a particular work was taken from the company, which is determined with the help of MDAT software (MOST Data

Acquisition Tool). This software is based on MOST (Maynard Operation Sequence Technique). Since there are number of sub-operation, the time allocated to the worker may not be equal to the cycle time. In this study, the process layout with line balancing for MCV 60/shift & 6

2- 40/shifts was prepared. The Line Layout prepared is summarized as follows:

There are two parallel lines for HCV model:

  1. Main Line

    1. Main Washing Machine

    2. Slat Conveyor

    3. Painting

  2. Sub Assembly Line

    1. Hub Drum Line

    2. Differential Line Hub Drum line may be sub divided in two ways

  1. Hub-Drum Washing Machine

  2. Hub-Drum Assembly

Differential Line may be sub divided in two ways

  1. Differential Washing Machine

  2. Differential Assembly

    Similarly, the assembly of MCV Line can be sub divided. Process layout chart are prepared. The components for assembly on slat conveyor are washed on the main Washing Machine and one operator is involved for the loading the component and other for unloading the component. At the Slat conveyor Knuckle Assembly, Brake Assembly, Torquing, Dust cover fitment, Tie rod fitment, Differential fitment, Shaft Fitment, Hub Drum Fitment etc. are done. The operators are involved for assembly. Workers are doing the assembly at both side of the conveyor and are denoted as Left Hand Side Worker (LH) and the Right hand side worker (RH). The Final assembly will go for painting. Here two workers are allocated to do the job. At Hub Drum line, the Bearing race fitment, Bearing Fitment, Oil Seal Presing, Bolt Pressing Shim Selection and Greasing application were done. At Differential Line, the differential Case Assembly, Retainer Assembly, Carrier Retainer assembly and Final differential assembly were done. There were two equipments, which are common to HCV and LCV Line. These are

    1. Hub Drum Washing Machine

    2. Differential Washing Machine

At Hub Drum Washing Machine, the Hub and Drum are washed and supplied to the different line. At Differential Washing Machine, the different components used for Differential Assembly are washed and are supplied to the Differential Line. The summary sheet of the process chart for HCV 40/shift and LCV/MCV 60/shift are shown in Table 7 & Table 8 respectively. From these summary Tables one may be able to know how the work is done and how much work will be done at a particular station.

CONCLUSIONS

The capacity up gradation is the basic need of all automobile manufacturing and assembly units of automobile components. The axle is the most important part of the vehicle. To increase the capacity of axle assembly from existing 60/shift to 100/shift of an assembly unit, the equipments either added in the existing assembly line (extension line) or may be put parallel to the existing line (parallel line) and also the capacities of the individual equipments are calculated and from that additional required quantity of equipments are proposed.

REFERENCES:

  1. John P. Tanner & Associates, Manufacturing engineering, an introduction to the basic function, Orlan, Florida, 1991.

  2. www.atlantic.cc.wm/timesheet-benefits.htm/

  3. K.R.Phaneesh, Production and Operation Management, Sudha Publications, 2002.

  4. Edward J. Phillips, Manufacturing Plant Layout, Fundamentals and fine points of Optimum facility design, P.E. Society of Manufacturing Engineers One SME Drive Michigan,1997.

  5. Richard Muther, Practical plant layout, McGraw-Hill Book Company, 1955.

[6]. Joseph Harrington, Understanding the manufacturing process, Marcel Dekker, Inc., New York,

  1. Arthur C. Ansley, Manufacturing Methods and Processes, Chilton Book Company,

  2. Maynard, H.B., Stegemerten G.J. & Schwab, Methods-time Measurement New York: McGraw-Hill, 1948.

  3. Bryan B. Christopher son, www.managers.net.com.

  4. Dirk J Rauglas, www.propalanner.net.

  5. Tanner, T.P., Planning To Minimize Manufacturing Corpn. Production Engineering, June 1986.

  6. Ravi Shanker, Industrial Engineering and Management, Golgotha Publication Pvt. Ltd, New Delhi 1971

  7. Harold T. Amrine, John A. Ritchey, Oliver S, Hulley, Manufacturing Organization and Management Second Edition, Prentice Hall of India Private Limited, New Delhi, 1971.

  8. Vijay S, Seth, Facilities Planning and Material Handling, Methods and Requirements, Marcel Dekker Inc., New York, 1995.

  9. Kirpal Singh, Automobile Engineering, Vol-1, Standard Publishers Distributers, 2001.

  10. Jay Kopycinsk, www.minitruckinweb.wm, A Premedia Publication.

  11. Sadhu Singh, Machine Design Khanna Publishers, Third Edition, Delhi, 1999.

  12. Hicks, Philip E, Introduction to Industrial Engineering and Management Science, Mc Graw Hill, NewYork, 1977.

  13. Ed. T.J.Bently, The Management Service Handbook, Institute of management Services.

  14. Dennis A Whitmore, Work Measurement, Institute of Management Services

  15. Krick, E.V., Methods Engineering Design and Measurement of Work Methods, Wiley, New York, 1962.

  16. Maynard, H.B. Industrial Engineering Handbook, Third Edition, Mc Graw Hill, New York, 1971.

  17. Herbert Meyr, Supply chain planning in the German automotive industry, Institute of Transport Economics and Logistics, 2004.

  18. A. Gürhan Kök Fuqua, School of Business Duke University, Marshall

    L. Fisher, The Wharton School University of Pennsylvania, Ramnath Vaidyanathan, The Wharton School, Assortment Planning:

    Review of Literature and Industry Practice, 2006.

  19. Patrick J. Montana and Bruce H. Charnov, Barron's Management book fourth edition

  20. M. Lorenzen, "Strategic Pla nning for Academic Library Instructional Programming." In: Illinois Libraries 86, Page no. 2, 200.6

Leave a Reply