Causes of Delay in Construction Projects: A Systematic Review
Zayyanu Mohammed
Business Administration Department Nile University of Nigeria, Abuja, Nigeria
Umar Bello
Business Administration Department Nile University of Nigeria, Abuja, Nigeria
Abstract:- The paper aimed at systematically reviewing extant journal on causes of delay in construction projects and adopted the Systematic Quantitative Assessment Techniques (SQAT) in identifying and examining 51 English peer-reviewed journal articles on causes of delay in construction projects collated from six high quality academic databases: Emerald, Elsevier, Springer, Wiley, Taylor
& Francis and JSTOR. The study revealed that most of the papers focused on factors causing delays in construction projects and project delay analysis. Majority of the articles were studies from Asia and Africa, then Europe, while Australia, North America and South America having one article each.
Keywords: Systematic Review, Causes of delay, Construction Project, Construction Industry
INTRODUCTION
Construction sector is one of the most important industries in every country that can spur economic growth and inspire development in other sectors (Aziz and Abdel-Hakam, 2016). Population growth, increasing urbanization and globalization have made it vital that the infrastructure is developed promptly for sustainable development (Prasad et al. 2019). Construction projects such as roads projects, water supply projects, hospital projects etc. play significant role as they are necessary requirement for employment generation, poverty alleviation and socio-economic development, especially in developing economies (Amoatey and Ankrah, 2017). However, for a project to be successful it has to be completed within the specified budget, cost, time and satisfying the projected standards. Failed projects lead to negative circumstances such as late completion, cost overruns and inferior work (Association of Construction Development, 2014).
Globally, the construction industry encounters delays that pause many projects, in some cases even cause total abandonment, along with it are time and cost overruns, which comes with other consequences such as project failure, reduction of prot margin, and the loss of public confidence, particularly on government funded projects (Doraisamy et al. 2015; Zailani et al. 2016).
Delays are classified into two categories. Excusable and non-excusable delay. Delays that resulted from factors that are beyond the control of the contractor or any other party and were unable to be detected earlier and did not occur due to their fault or negligence is regarded as excusable delay. However, delays that are instigated by the contractor or any other party such as sub- contractor and are within the control of the contractor is referred to non-excusable delays. concurrent delays occur when the contractor and the owner are responsible for the delay (Doraisamy et al. 2015; Anysz and Buczkowski, 2018).
A construction project could experience delay in handing over the site, or when there are unanticipated ground conditions, extra works, variations, suspensions of work, adverse weather conditions etc. Such delays can be recognized and considered based on their causes and effects (Keane and Calettka, 2008). They can also be characterized due to the party that is accountable for them, i.e., Excusable Delays, Non-Excusable Delays and Concurrent Delays (Ekanayeka and Perera, 2016).
Delay in project completion is generally experienced in the construction projects and has always being a problem in the construction industry and is being regularly reported in many countries (Oyegoke and Al Kiyumi, 2017; Budayan et al. 2018) Considering the potential benefit of construction projects to the economic development of any nation and the challenge of projects delay is gradually becoming a global occurrence, it is therefore of great consequence that causes of delay in construction projects be explored in depth, as an in-depth analysis of the concept could be what is needed to mitigate the distress and anxiety to all the parties involved in construction projects and making sure that projects are completed within the specified budgeted time and cost. Also, understanding of the main factors causing the construction projects delays can aid in evaluating the gaps and inadequacies in project implementation and can pave ways of improvement of project performance. As such, this research work conducted a quantitative and systematic analysis of 51 peer-reviewed scholarly articles on causes of delay in construction projects in an attempt to highlight trends and gaps that will serve as points of reference for future research in the area.
The rest of this paper is organized as such: The next section is review of literature, followed by methodology of the study, findings and discussion of the results. Lastly, the conclusion, limitations and recommendation for future research prospects.
Literature Review
Delays in construction projects are acknowledged as one of the most conspicuous challenge facing the industry, Cost and time overruns are common in construction projects and infrastructure development (Mahmidi, 2011; Oyeguke and Kiyumi, 2017; Anysz and Buczkowski, 2018). In the construction industry, delay refers to the time exceeding beyond the specified project completion date or time agreed to complete the projects by both the parties (Yang et al. 2014; Oyegoke and Al Kiyumu, 2017).
History had shown that worldwide the construction industry is full of projects that experienced delays and completed with signicant time and cost overruns (Amehl et al. 2010). Many studies on construction related projects particularly, those in developing countries claim that in most of the cases the cost at the end of the project surpasses the original budgeted cost by almost 30 percent. by the time many projects are completed due to delay in the execution of the projects (Al-Momani, 1996; Mahmidi, 2011).
Shebob et al. (2012) undertook a comparative study of delay factors in Libyan and the UK construction industry. The results indicated the factors that causes delay are different in the two countries and construction projects suffered more delays in Libya than in the UK. Adopting case study approach and looking at the most critical delay factors, found that a building project might be delayed in Libya by 41 to 46 days and 34 to 38 days in the UK.
Amaotey et al. (2015) examined the delay causes and effects in Ghanaian state housing construction projects. the study indicated that the factors that causes delay construction projects were; delay in paying contractors, price fluctuation/inflation, increases of materials prices, insufficient finances from project sponsors, variation orders and absence of good financial or capital market. The major impacts of delays are cost and time overrun, litigation, continuity by client and adjudication.
Khoshgoftar et al. (2010) investigated causes of delays in Iranian construction projects. The findings identified that finance and payments of completed work, inadequate planning, improper site management, improper contract management, and communication gap between the parties involved in the are the main reasons that causes delay in the Iranian construction projects. Several studies related to possible causes of delay in construction projects have been described in the literature. Table 1 displays some of the recent research works and their related references. From Table 1, it can be observed that sources of delay were grouped by researchers under different classes, depending on the reponsible party (such as owners, client, contractor etc.) or the associated theme (such as managerial, technical etc.).
Table 1: List of 10 selected previous studies about causes of delay in construction projects (2010 2019)
References |
Brief description of the study |
Causes of delay |
Kazaz et al. (2012) |
Conducted a survey on 34 factors affecting project duration of 71 construction companies in Turkey |
Outlined the most significant delay factor to include design and materials changes; payments delay; problem of cash flows; poor labor productivity and contractors financial problems. |
Yang et al. (2013) |
Analysis of the contents of legal cases from Supreme Court verdicts in Taiwan on the main causes of schedule delays in construction projects. |
The research work discovered that change orders, changed of scope, weather condition and construction site handover delays as the major reasons for schedule delays in construction related legal cases. |
Akogbe et al. (2013) |
Analysis of delay factors which affect the delay in completion of construction projects in Benin. |
Delays in construction project emanated due to contractors financial capability, owners financial difficulties, poor performance of subcontractors, materials procurement of contractor, inadequate planning and scheduling, sluggish inspection of completed works by the consultants and unavailability of equipment. |
Kim et al. (2016) |
A survey of delay factor analysis for hospital projects in Vietnam. |
The paper indicated that the top five causes of delay in hospital projects were: Owners financial difficulties, change of design, incompetent contractor, inadequate experience of contractor and improper handling of responsibilities by supervisors |
Aditya et al. (2017) |
Review on the causes of delay and difficulties in execution of water supply project in India. |
The causes of delay were due to delays in administration (Land acquisition, planning and coordination), difficulties in execution and non-performance of the contractors. |
Amoatey & Ankrah (2017) |
Conducted a survey of 48 roads projects to examines the causes of delay of roads projects in Ghana. |
The delays were classified as client-related, contractor-related and donor-related. The client-related delays include delay in payment of completed work, changes of scope during the construction and delay to deliver the site to the contractor. The contractor-related delay centered on inadequate experience of contractor, while the donor-related delay was on inflexible funding allocation for project items. |
Agyekum-Mensah & Knight (2017) |
Exploring the practitioners perspective on 32 delay causes in the UK construction industry in the post- recession era. |
Inadequate project planning, poor commercial decisions, design problems, scope creep and unclear project requirements, financial problems, inexperience and incompetence, inappropriate risks transfer and mitigation, poor resource management. |
Zidane and Andersen (2018) |
Analysis of the top 10 universal delay factors in construction projects and review of delay factors in major Norwegian construction projects. |
The Norwegian construction industry experienced delays due to poor planning, scheduling problem, slow decision process, administrative challenges and bureaucratic inadequacies with the project organizations, resources inadequacies, lack of good communication and coordination between parties in the project. The paper highlighted 10 delay factors to comprised changes in design; delay in paying contractors; poor planning and scheduling; bad supervision and site management; inadequate or inappropriate design; contractors inexperience and competence; shortage of finances; sponsor or owners financial difficulties, shortage of resources; poor labor productivity and lack of adequate skills. |
Rezaee et al. (2019) |
Analyzing factors that causes delays in construction projects in Iran and their effect on project performance. |
Incorrect estimation of job, insufficient equipment and correct project completion time, absence of good legal framework relating to job responsibilities and inadequate enforcement of sanctions |
Viles et al. (2019) |
Examined the assessable examination of factors causing delay in construction projects. |
Changes during construction, Poor construction management, Construction errors, Economic/Financial, Conflict/Relationship and Lack of experience. |
METHODOLOGY
This study espouses a systematic quantitative literature review method on Causes of Delay in Construction Projects adopting the Systematic Quantitative Assessment Technique (SQAT) developed by Pickering and Bryne (2014). SQAT is systematic in the way papers are assessed and determine their inclusion or exclusion in the review process, and it allows the researchers, to methodically analyze existing academic literature to produce an organized quantitative summary of the field (Pickering and Bryne 2014). The focus of this studies was on only peer reviewed original English journal publications on causes of delay in construction projects to uphold a high quality of papers. The systematic technique explores the geographical spread of the literature, the research methods adopted, the type of literature and their specific focus (Pickering and Bryne, 2014).
SQAT recommends five important dimensions in undertaking an effective systematic review. Each dimension and how it was implemented in this research work is described within this framework. A total of 51 peer-reviewed English articles on causes of delay in construction projects were compared across the dimensions outlined in Table 1.
Table 1: Description and Application of SQAT
S/No. |
Dimensions |
Application in current study |
1. |
Define topic |
Causes of Delay in Construction Projects (CDCP) |
2. |
Formulate research questions |
Six research questions:
|
3. |
Identify key words |
Causes of Delay and Construction Projects |
4. |
Identify the research databases |
|
5. |
Read and access publication |
|
FINDINGS
Time Distribution of Causes of Delay in Cnstruction projects (CDCP) Articles
This research work reviewed 51 papers which met the selection criteria of within ten (10) years (2010 2019); as ten years is considered enough time to include sufficient data required for the study. These were diagrammatically presented in the bar chart below (Figure i).
12
10 11
Number of Articles
8 9
8
6 7
4
4
2 3 3
2 2 2
0
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Year
Figure 1: Time Distribution of CDCP Articles
Geographical Distribution of Causes of Delay in Construction Projects Articles
The geographical distribution of causes of delay in construction projects papers reviewed was presented in figure 2. Asia had the highest number (30); followed by Africa (10); Europe (8); while Australia, North America and South America had 1 each, respectively. These were presented in figure 2 below.
30
30
Number of Articles
25
20
15 10
10
5
0
8
1 1 1
Africa Asia Australia Europe Norh
America
South America
Research Contients
Figure 2: Geographical Distribution of CDCP Articles
Type of Articles on Causes of Delay in Construction Projects
The 51 articles reviewed were divided into two categories; conceptual and empirical. Conceptual articles here mean papers that focuses on the theory and concept of the causes of delay in construction projects, whilst empirical articles were those which includes both quantitative and qualitative studies where conclusion are drawn from evidence verifiable by observations or experience rather than theory or logic (Difference between Conceptual and Empirical Research, 2019). It can be observed from figure 3 that 82% (42 out of 51) articles reviewed were empirical in nature where researchers presented significant practical conclusions on issues that causes delay in construction projects (Khoshgaftar et al. 2010; Muhammad et al. 2015; Hossain et al. 2019). The remaining 18% were conceptual papers in which authors provides recommendations (Keller et al. 2010; Hamzah et al. 2011; Yang et al. 2014). The pie chart below in figure iii depicted the categorization of type of the articles.
Conceptual 18%
Empirical 82%
Empirical Conceptual
Figure 3: Type of CDCP Articles
Distribution of Top 5 Journal Publishers of CDCP Literatures
The table 3 below, shows the journal publishers with the most articles on causes of delay in construction projects (CDCP).
Table 3: Journal Distribution of CDCP Papers
JOURNAL PUBLISHERS |
NUMBER OF PAPERS |
RANKING |
International Journal of Construction Management (Taylor & Francis) |
6 |
1st |
Procedia Engineering (Elsevier) |
6 |
1st |
KSCE Journal of Civil Engineering (Springer) |
5 |
2nd |
Engineering Construction and Architectural Management (Emerald) |
4 |
3rd |
Alexandria Engineering (Elsevier) |
3 |
4th |
The evidence from table 3 above, shows that International Journal of Construction Management and Procedia Engineering are the most preferred publishers of Causes of Delay in Construction Projects literatures with 6 papers each. Closely followed by KSCE Journal of Civil Engineering with 5 articles, while Engineering Construction & Architectural Management and Alexandria Engineering have 4 and 3 papers, respectively. Other journal site or publishers with publication ranging from one to two were not included in the analysis for ease of interpretations.
Research Method of CDCP Articles
Figure 4 below shows the research method used in each of the 51 CDCP articles reviewed in this research work.
12%
6%
15%
6%
14%
47%
Case study
Survey
Interview
Review
Survey + Case study Survey + interview
Figure 4: Research Methods
Based on the findings in figure 4, the research method mostly adopted in the articles reviewed was survey (47%). This involved the distribution of questionnaires to projects stakeholders (clients, consultants, professionals, owners and users of projects etc.) which would then be collated for analysis and interpretations (Mahmidi, 2011; Marzouk and El-Rasas, 2014; Tahir et al. 2017; Wang and Lin, 2018; Maqsoom et al. 2019). This followed by articles involving case studies (15%) which focuses on organizations or countries issues and impact of causes of delays in construction projects (Yang et al. 2013; Iyer and Kumar, 2016; Koiraila et al. 2017; Guida and Sacco, 2019). The papers that adopted review analysis (14%) which includes theoretical, literature and systematic reviews on delay analysis in construction projects (Yang and Kao, 2012; Doraisamy et al. 2015; Mbala et al. 2018). 12% of the articles adopted combination survey and interviews, which comprised used of both questionnaires and collection of data directly from persons involved in constructions projects (Doloi et al. 2012; Shahsavand and Parchmijalal, 2018; Rachid et al. 2019). Another 6% of the papers reviewed adopted only interviews in collecting data for analysis and interpretation on CDCP (Agyekum-Mensah and Knight, 2017; Durdyev et al. 2017). Lastly, the papers that embraced the methodology of both survey and case studies were 6% (Shebob et al. 2012; Alsuliman, 2019), thus completing the six research methods identified in review of CDCP studies.
CDCP THEMES
It can be observed from figure 5 that the 51articles reviewed on CDCP focuses on 3 themes. Causes of project delay (63%); project delay analysis (23%); and effects of project delay. For the papers with theme on causes of delay, the researchers acknowledged that delays are a common phenomenon in construction projects and its among the challenges must projects faced and investigated the factors that caused cost overrun and scheduled time of projects (Aziz, 2013; Elawi et al. 2016; Al-Hazim et al. 2017; Chen et al. 2019). On the project delay analysis themes, the attention of the researchers was tilted towards method of analyzing causal relationship between delay factors in construction projects (Ekanayeka and Perera, 2016; Chiu and Lai, 2017; Bilgin et al. 2018). While researchers emphasis on the theme on effects of project delay were on analyzing delay factors in construction projects and determining their impacts, mitigations and made recommendations based on the findings of the studies (Senouci and Eldin, 2016; Zailani et al. 2016; Abd El-Karim et al. 2017). Analysis of delay factors, its causes and their impact should be at the forefront of construction project research because of the frequent lengthy delay that occurs which significantly affects most of the projects objective, performance, benefits and costs and in some cases many projects are stalled or abandoned.
Project Delay Analysis 12
Themes
Effects of Project Delay 7
Causes of Project Delay 32
0 5 10 15 20 25 30 35
Number of Articles
Figure 5: CDCP Themes
DISCUSSION OF RESULTS
As seen in figure 1, there is continuous, though uneven growth trend in research observed between 2010 and 2015. However, from 2016 there appeared to be an increase in interest of scholars on the topic, though still fluctuating. Therefore, it is likely that more researchers will take interest in issues of delay in construction projects.
It is observed from figure 2, Asian counties are seen to have dominated the attention of researchers with 30 out 51 reviewed articles, followed by Africa and Europe with 10 and 8 papers, respectively, and 1 each for Australia, North America and South America. This is not surprising, as most of the research papers on this study are from Asian countries of hina, India, Malaysia, Iran and Saudi Arabia which are among fast growing economies where there is remarkable demand for infrastructural developments (Wang and Lin, 2018; Prasad et al. 2019 Rezaee et al. 2019). Meanwhile, in Africa construction industry holds enormous potential in generating employment and stimulating growth, resulting for rapid expansion of infrastructure by government and private sector initiatives that prompted more construction activities (Aziz and Abdel-Hakim, 2016; Amoatey and Ankrah, 2017; Gebrehiweta and Luo, 2017), hence the interest of researchers in delay analysis of construction projects in the continent.
CONCLUSION
This studies considered 51 peerreviewed journal articles on causes of delays in constructions project which were examined based on six key classifications: the time distribution of the articles, where the articles were written, article type, which journal publishers were adopted by the articles research methods employed and the themes explored in the articles. The findings showed that the continent with highest articles on causes of delay in construction projects is Asia. Majority of the articles reviewed were empirical studies and survey method was mostly adopted with less of interview. The findings of the studies were limited by the fact that only peer-reviewed journal articles were included in the research work, book chapters and conference proceedings were excluded. Another limitation is the methodology used of a title search in six databases rather than search using a key word.
However, notwithstanding of these limitations, this study is vital as it identify a clear path on the current situation of issues arising on causes of delay in construction projects and provides clear direction on the areas that future research needs to address in order to mitigate risk associated with delays in construction projects.
Therefore, the following recommendations for future research work on this study were as follows:
Reviewers/Scholars should include, book chapters and conference proceedings in their studies, this is to further improve the understanding of the causes of delay in construction projects.
Future research should also focus on critical analysis and conceptual work and support their research work with considerable theoretical framework method in order to have all round review on causes of delay in construction projects.
Future study emphasis should be tilted towards investigating the impact and risk management strategies of delays in construction projects.
Potential researchers should look at comparative studies between countries on this area as since delays in construction projects has become a global phenomenon, and many projects continue to experience delay despite the adoption of modern project management techniques and application of advanced technology.
REFERENCES
[1] Abd El-Karim, M. S. B. A., Mosa El Nawawy, O. A., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC journal, 13(2), 202-216. [2] Aditya, A. K., Douglass, D. A., & Bhattacharya, M. (2017). Urban infrastructure development works in India: Delay and difficulties in implementation with reference to a water supply project. Journal of The Institution of Engineers (India): Series A, 98(3), 349-354. https://doi/10.1007/s40030-017- 0214-2 [3] Agyekum-Mensah, G., & Knight, A. D. (2017). The professionals perspective on the causes of project delay in the construction industry. Engineering, Construction and Architectural Management. [4] Akogbe, R. K. T., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering, 17(6), 1213-1222. [5] Al-Momani, A. (1996), Construction cost prediction for public school buildings in Jordan, Construction Management and Economics, Vol. 14, pp.311-7.
[6] Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and cost overrun in infrastructure projects in Jordan. Procedia Engineering, 182(2017), 18- 24. [7] Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801-808. [8] Amehl, O., Soyingbe, A. & Odusami, K. (2010), Signicant factors causing cost overruns in telecommunication projects in Nigeria, Journal of Construction in Developing Countries, Vol. 15. [9] Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business. [10] Amoatey, C. T., & Ankrah, A. N. O. (2017). Exploring critical road project delay factors in Ghana. Journal of Facilities Management. [11] Anysz, H., & Buczkowski, B. (2018). The association analysis for risk evaluation of significant delay occurrence in the completion date of construction project. International Journal of Environmental Science and Technology, 1-6. [12] Association of Construction Development (2014), Construction delays, available at: www.associationofconstructiondevelopment.org. [13] Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387-406. [14] Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515-1539. [15] Bilgin, G., Dikmen, I., & Birgonul, M. T. (2018). An ontology-based approach for delay analysis in construction. KSCE Journal of Civil Engineering, 22(2), 384-398. [16] Budayan, C., Dikmen, I., Birgonul, M. T., & Ghaziani, A. (2018). A computerized method for delay risk assessment based on fuzzy set theory using MS project. KSCE Journal of Civil Engineering, 22(8), 2714-2725. [17] Chen, G. X., Shan, M., Chan, A. P., Liu, X., & Zhao, Y. Q. (2019). Investigating the causes of delay in grain bin construction projects: the case of China. International Journal of Construction Management, 19(1), 1-14. [18] Chiu, B. W., & Lai, J. H. (2017). Project delay: key electrical construction factors in Hong Kong. Journal of civil engineering and management, 23(7), 847-857. [19] Difference Between Conceptual and Empirical Research (2019). Retrieved from https://www.pediaa.com/difference-between-conceptual-and- empirical-research/ [20] Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International journal of project management, 30(4), 479-489. [21] Doraisamy, S. V., Akasah, Z. A., & Yunus, R. (2015). An Overview on the Issue of Delay in the Construction Industry. In In CIEC 2014 (pp. 313- 319). Springer, Singapore. [22] Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4(1), 1291117. [23] Ekanayake, E. M. K., & Perera, B. A. K. S. (2016). Appropriate delay analysis techniques to analyse delays in road construction projects in SriLanka. Built Environment Project and Asset Management.
[24] Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners perspective of factors contributing to project delay: case studies of road and bridge projects in Saudi Arabia. Procedia Engineering, 145, 1402-1409. [25] Gebrehiwet, T., & Luo, H. (2017). Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Procedia engineering, 196, 366-374. [26] Guida, P. L., & Sacco, G. (2019). A method for project schedule delay analysis. Computers & Industrial Engineering, 128, 346-357. [27] Hamzah, N., Khoiry, M. A., Arshad, I., Tawil, N. M., & Ani, A. C. (2011). Cause of construction delay-Theoretical framework. Procedia Engineering, 20, 490-495. [28] Hossain, M. A., Raiymbekov, D., Nadeem, A., & Kim J. R. (2019). Delay causes in Kazakhstans construction projects and remedial measures.International Journal of Construction Management, 1-19.
[29] Iyer, K. C., & Kumar, R. (2016). Impact of delay and escalation on cash flow and profitability in a real estate project. Procedia Engineering, 145(7), 388-395. [30] Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes of delays in construction projects in Turkey. Journal of civil Engineering and Management, 18(3), 426-435. [31] Kelleher Jr, T. J., Nelson, E. L., & Miller, G. E. (2010). The resurrection of rice?" The evolution (and de-evolution) of the ability of contractors to recover delay damages on Federal Government Construction Contracts. Public Contract Law Journal, 305-330. [32] Khoshgoftar, M., Bakar, A. H. A., & Osman, O. (2010). Causes of delays in Iranian construction projects. International Journal of Construction Management, 10(2), 53-69. [33] Kim, S. Y., & Tuan, K. N. (2016). Delay factor analysis for hospital projects in Vietnam. KSCE Journal of Civil Engineering, 20(2), 519-529. [34] Koirala, S., Hill, D., & Morgan, R. (2017). Impacts of the delay in construction of a large scale hydropower project on potential displacees. Impact Assessment and Project Appraisal, 35(1), 106-116. [35] Mahamid, I. (2011). Risk matrix for factors affecting time delay in road construction projects: owners' perspective. Engineering, Construction and Architectural Management. [36] Maqsoom, A., Choudhry, R. M., Umer, M., & Mehmood, T. (2019). Influencing factors indicating time delay in construction projects: Impact of firm size and experience. International Journal of Construction Management, 1-12. [37] Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction projects. Journal of advanced research, 5(1), 49-55. [38] Mbala, M., Aigbavboa, C., & Aliu, J. (2018, July). Causes of delay in various construction projects: a literature review. In International Conference on Applied Human Factors and Ergonomics (pp. 489-495). Springer, Cham. [39] Muhamad, N. H., Mohammad, M. F., Ahmad, A. C., & Hussein, E. (2015). Problems Associated with Delay Analysis Methodology in Malaysian Construction Delay Practice. In In CIEC 2014 (pp. 301-311). Springer, Singapore. [40] Oyegoke, A. S., & Al Kiyumi, N. (2017). The causes, impacts and mitigations of delay in megaprojects in the Sultanate of Oman. Journal of Financial Management of Property and Construction. [41] Pickering, C., & Byrne, J. (2014). The benefits of publishing systematic quantitative literature reviews for PhD candidates and other early career researchers. Higher Education Research & Development, 33(3), 534-548 [42] Prasad, K. V., Vasugi, V., Venkatesan, R., & Bhat, N. (2019). Analysis of causes of delay in Indian construction projects and mitigation measures. Journal of Financial Management of Property and Construction. [43] Rachid, Z., Toufik, B., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 19(5), 371-381. [44] Rezaee, M. J., Yousefi, S., & Chakrabortty, R. K. (2019). Analysing causal relationships between delay factors in construction projects. International Journal of Managing Projects in Business. [45] Senouci, A., Ismail, A., & Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia engineering, 164, 368-375. [46] Shahsavand, P., Marefat, A., & Parchamijalal, M. (2018). Causes of delays in construction industry and comparative delay analysis techniques withSCL protocol. Engineering, Construction and Architectural Management.
[47] Shebob, A., Dawood, N., Shah, R. K., & Xu, Q. (2012). Comparative study of delay factors in Libyan and the UK construction industry. Engineering, Construction and Architectural Management. [48] Tahir, M. M., Haron, N. A., Alias, A. H., & Diugwu, I. A. (2017). Causes of Delay and Cost Overrun in Malaysian Construction Industry. In Global Civil Engineering Conference (pp. 47-57). Springer, Singapore. [49] Viles, E., Rudeli, N. C., & Santilli, A. (2019). Causes of delay in construction projects: a quantitative analysis. Engineering, Construction and Architectural Management. [50] Wang, W., & Lin, W. (2018). Study on the influence factors of urban subway project delay in the initial construction stage. Journal of Discrete Mathematical Sciences and Cryptography, 21(6), 1193-1197. [51] Yang, J. B., & Kao, C. K. (2012). Critical path effect based delay analysis method for construction projects. International Journal of Project Management, 30(3), 385-397. [52] Yang, J. B., Chu, M. Y., & Huang, K. M. (2013). An empirical study of schedule delay causes based on Taiwan's litigation cases. Project Management Journal, 44(3), 21-31. [53] Yang, J. B., Huang, K. M., Lee, C. H., & Chiu, C. T. (2014). Incorporating lost productivity calculation into delay analysis for construction projects. KSCE Journal of Civil Engineering, 18(2), 380-388. [54] Zailani, S., Ariffin, H. A. M., Iranmanesh, M., Moeinzadeh, S., & Iranmanesh, M. (2016). The moderating effect of project risk mitigation strategies on the relationship between delay factors and construction project performance. Journal of Science and Technology Policy Management. [55] Zidane, Y. J. T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business.APPENDIX 1
Literature Map of the 51 Articles Reviewed
Reference |
Country |
database |
Journal |
Type of Article |
Method adopted |
Specific theme |
Keller et al. (2010) |
USA |
JSTOR |
Public Contract Law Journal |
Conceptual |
Theoretical review |
Effects of project delay |
Khoshgoftar et al. (2010) |
Iran |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey |
Causes of project delay |
Mahmidi I. (2011) |
Palestine |
Emerald |
Engineering, Construction and Architectural Management |
Empirical |
Survey |
Causes of project delay |
Hamzah et al. (2011) |
Malaysia |
Elsevier |
Procedia Engineering |
Conceptual |
Theoretical review |
Causes of project delay |
Orangi et al. (2011) |
Australia |
Elsevier |
Procedia Engineering |
Empirical |
Interview |
Causes of project delay |
Doloi et al. (2012) |
India |
Elsevier |
International Journal of Project Management |
Empirical |
Survey and Interview |
Causes of project delay |
Kazaz et al. (2012) |
Turkey |
Taylor & Francis |
Journal of Civil Engineering and Management |
Empirical |
Survey |
Causes of project delay |
Shebob et al. (2012) |
UK |
Emerald |
Engineering, Construction and Architectural Management |
Empirical |
Survey and Case study |
Effects of project delay |
Yang & Kao (2012) |
Taiwan |
Elsevier |
International Journal of Project Management |
Conceptual |
Systematic review |
Project delay analysis. |
Akogbe et al. (2013) |
Benin |
Springer |
KSCE Journal of Civil Engineering |
Empirical |
Survey |
Project delay analysis. |
Aziz R.F. (2013) |
Egypt |
Elsevier |
Alexandria Engineering Journal |
Empirical |
Survey |
Causes of project delay |
Yang et al. (2013) |
Taiwan |
Wiley |
Project Management Journal |
Empirical |
Case study |
Causes of project delay |
Marzouk & El-Rasas (2014) |
Egypt |
Elsevier |
Journal of Advanced Research |
Empirical |
Survey |
Causes of project delay |
Yang et al. (2014) |
Taiwan |
Springer |
KSCE Journal of Civil Engineering |
Conceptual |
Case study |
Causes of project delay |
Muhammad et al. (2015) |
Malaysia |
Springer |
CIEC |
Empirical |
Survey |
Project delay analysis |
Doraisamy et al. (2015) |
Malaysia |
Springer |
CIEC |
Conceptual |
Literature review |
Project delay analysis. |
Aziz and Abdel- Hakim (2016) |
Egypt |
Elsevier |
Alexandria Engineering Journal |
Empirical |
Survey and Case study |
Causes of project delay |
Ekanayeka & Perera (2016) |
Sri Lanka |
Emerald |
Built Environment Project and Asset Management |
Empirical |
Survey and Interview |
Project delay analysis |
Elawi et al. (2016) |
Saudi Arabia |
Elsevier |
Procedia Engineering |
Empirical |
Case study |
Causes of project delay |
Kim et al. (2016) |
Vietnam |
Springer |
KSCE Journal of Civil Engineering |
Empirical |
Survey and Interview |
Causes of project delay |
Iyer & Kumar (2016) |
India |
Elsevier |
Procedia Engineering |
Empirical |
Case study |
Project delay analysis |
Senouci & Eldin (2016) |
Qatar |
Elsevier |
Creative Construction Conference |
Empirical |
Survey |
Effects of project delay |
Zailani et al. (2016) |
Malaysia |
Emerald |
Journal of Science and Technology Policy Management |
Empirical |
Survey |
Effects of project delay |
Abd El-Karim et al. (2017) |
Egypt |
Elsevier |
HBRC journal |
Empirical |
Survey |
Effects of project delay |
Aditya et al. (2017) |
India |
Springer |
J. Inst. Eng. India Ser. A |
Conceptual |
Theoretical Review |
Causes of project delay |
Agyekum-Mensah & Knight (2017) |
UK |
Emerald |
Engineering, Construction and Architectural Management |
Empirical |
Interview |
Causes of project delay |
Al-Hazim et al. (2017) |
Jordan |
Elsevier |
Procedia Engineering |
Empirical |
Survey |
Causes of project delay |
Amoatey & Ankrah (2017) |
Ghana |
Emerald |
Journal of Facilities Management |
Empirical |
Survey |
Causes of project delay |
Chiu & Lai (2017) |
Hong Kong |
Taylor & Francis |
Journal of Civil Engineering and Management |
Empirical |
Survey |
Project delay analysis |
Durdyev et al. (2017) |
Cambodia |
Taylor & Francis |
Civil & Environmental Engineering |
Empirical |
Interview |
Causes of project delay |
Gebrehiweta & Luo (2017) |
Ethiopia |
Elsevier |
Procedia Engineering |
Empirical |
Survey |
Impact of project delay |
Koirala et al. (2017) |
Nepal |
Taylor & Francis |
Impact Assessment and Project Appraisal |
Empirical |
Case study |
Impact of project delay |
Oyegoke & Al Kiyumi (2017) |
Oman |
Emerald |
Journal of Financial Management of Property and Construction |
Empirical |
Survey |
Causes of project delay |
Tahir et al. (2017) |
Malaysia |
Springer |
Global Civil Engineering Conference |
Empirical |
Survey |
Causes of project delay |
Anysz & Buczkowski (2018) |
Poland |
Springer |
International Journal of Environmental |
Empirical |
Survey |
Project delay analysis |
Science and Technology |
||||||
Bajjou & Chafi (2018) |
Morocco |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey |
Causes of project delay |
Bilgin et al. (2018) |
Turkey |
Springer |
KSCE Journal of Civil Engineering |
Literature review |
Case study |
Project delay analysis |
Budayan et al. (2018) |
Turkey |
Springer |
KSCE Journal of Civil Engineering |
Empirical |
Survey |
Project delay analysis |
Mbala et al. (2018) |
South Africa |
Springer |
International Conference on Applied Human Factors and Ergonomics |
Conceptual |
Literature review |
Causes of project delay |
Shahsavand & Parchamijalal (2018) |
Iran |
Emerald |
Engineering, Construction and Architectural Management |
Empirical |
Survey and Interview |
Causes of project delay |
Wang & Lin (2018) |
China |
Taylor & Francis |
Journal of Discrete Mathematical Sciences and Cryptography |
Empirical |
Survey |
Causes of project delay |
Zidane and Andersen (2018) |
Norway |
Emerald |
International Journal of Managing Projects in Business |
Empirical |
Survey |
Causes of project delay |
Alsuliman J.A. (2019) |
Saudi Arabia |
Elsevier |
Alexandria Engineering Journal |
Empirical |
Survey and Case study |
Causes of project delay |
Chen et al. (2019) |
China |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey |
Causes of project delay |
Guida & Sacco (2019) |
Italy |
Elsevier |
Computers & Industrial Engineering |
Empirical |
Case study |
Project delay analysis |
Hossain et al. (2019) |
Kazakhstan |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey and Interview |
Causes of project delay |
Maqsoom et al. (2019) |
Pakistan |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey |
Causes of project delay |
Prasad et al. (2019) |
India |
Emerald |
Journal of Financial Management of Property and Construction |
Empirical |
Survey |
Causes of project delay |
Rachid et al. (2019) |
Algeria |
Taylor & Francis |
International Journal of Construction Management |
Empirical |
Survey and Interview |
Causes of project delay |
Rezaee et al. (2019) |
Iran |
Emerald |
International Journal of Managing Projects in Business |
Empirical |
Case study |
Project delay analysis |
Viles et al. (2019) |
Uruguay |
Emerald |
Engineering, Construction and Architectural Management |
Conceptual |
Literature review |
Causes of project delay |