Causes of Delay in Construction Projects: A Systematic Review

DOI : 10.17577/IJERTV11IS030016

Download Full-Text PDF Cite this Publication

Text Only Version

Causes of Delay in Construction Projects: A Systematic Review

Zayyanu Mohammed

Business Administration Department Nile University of Nigeria, Abuja, Nigeria

Umar Bello

Business Administration Department Nile University of Nigeria, Abuja, Nigeria

Abstract:- The paper aimed at systematically reviewing extant journal on causes of delay in construction projects and adopted the Systematic Quantitative Assessment Techniques (SQAT) in identifying and examining 51 English peer-reviewed journal articles on causes of delay in construction projects collated from six high quality academic databases: Emerald, Elsevier, Springer, Wiley, Taylor

& Francis and JSTOR. The study revealed that most of the papers focused on factors causing delays in construction projects and project delay analysis. Majority of the articles were studies from Asia and Africa, then Europe, while Australia, North America and South America having one article each.

Keywords: Systematic Review, Causes of delay, Construction Project, Construction Industry

INTRODUCTION

Construction sector is one of the most important industries in every country that can spur economic growth and inspire development in other sectors (Aziz and Abdel-Hakam, 2016). Population growth, increasing urbanization and globalization have made it vital that the infrastructure is developed promptly for sustainable development (Prasad et al. 2019). Construction projects such as roads projects, water supply projects, hospital projects etc. play significant role as they are necessary requirement for employment generation, poverty alleviation and socio-economic development, especially in developing economies (Amoatey and Ankrah, 2017). However, for a project to be successful it has to be completed within the specified budget, cost, time and satisfying the projected standards. Failed projects lead to negative circumstances such as late completion, cost overruns and inferior work (Association of Construction Development, 2014).

Globally, the construction industry encounters delays that pause many projects, in some cases even cause total abandonment, along with it are time and cost overruns, which comes with other consequences such as project failure, reduction of prot margin, and the loss of public confidence, particularly on government funded projects (Doraisamy et al. 2015; Zailani et al. 2016).

Delays are classified into two categories. Excusable and non-excusable delay. Delays that resulted from factors that are beyond the control of the contractor or any other party and were unable to be detected earlier and did not occur due to their fault or negligence is regarded as excusable delay. However, delays that are instigated by the contractor or any other party such as sub- contractor and are within the control of the contractor is referred to non-excusable delays. concurrent delays occur when the contractor and the owner are responsible for the delay (Doraisamy et al. 2015; Anysz and Buczkowski, 2018).

A construction project could experience delay in handing over the site, or when there are unanticipated ground conditions, extra works, variations, suspensions of work, adverse weather conditions etc. Such delays can be recognized and considered based on their causes and effects (Keane and Calettka, 2008). They can also be characterized due to the party that is accountable for them, i.e., Excusable Delays, Non-Excusable Delays and Concurrent Delays (Ekanayeka and Perera, 2016).

Delay in project completion is generally experienced in the construction projects and has always being a problem in the construction industry and is being regularly reported in many countries (Oyegoke and Al Kiyumi, 2017; Budayan et al. 2018) Considering the potential benefit of construction projects to the economic development of any nation and the challenge of projects delay is gradually becoming a global occurrence, it is therefore of great consequence that causes of delay in construction projects be explored in depth, as an in-depth analysis of the concept could be what is needed to mitigate the distress and anxiety to all the parties involved in construction projects and making sure that projects are completed within the specified budgeted time and cost. Also, understanding of the main factors causing the construction projects delays can aid in evaluating the gaps and inadequacies in project implementation and can pave ways of improvement of project performance. As such, this research work conducted a quantitative and systematic analysis of 51 peer-reviewed scholarly articles on causes of delay in construction projects in an attempt to highlight trends and gaps that will serve as points of reference for future research in the area.

The rest of this paper is organized as such: The next section is review of literature, followed by methodology of the study, findings and discussion of the results. Lastly, the conclusion, limitations and recommendation for future research prospects.

Literature Review

Delays in construction projects are acknowledged as one of the most conspicuous challenge facing the industry, Cost and time overruns are common in construction projects and infrastructure development (Mahmidi, 2011; Oyeguke and Kiyumi, 2017; Anysz and Buczkowski, 2018). In the construction industry, delay refers to the time exceeding beyond the specified project completion date or time agreed to complete the projects by both the parties (Yang et al. 2014; Oyegoke and Al Kiyumu, 2017).

History had shown that worldwide the construction industry is full of projects that experienced delays and completed with signicant time and cost overruns (Amehl et al. 2010). Many studies on construction related projects particularly, those in developing countries claim that in most of the cases the cost at the end of the project surpasses the original budgeted cost by almost 30 percent. by the time many projects are completed due to delay in the execution of the projects (Al-Momani, 1996; Mahmidi, 2011).

Shebob et al. (2012) undertook a comparative study of delay factors in Libyan and the UK construction industry. The results indicated the factors that causes delay are different in the two countries and construction projects suffered more delays in Libya than in the UK. Adopting case study approach and looking at the most critical delay factors, found that a building project might be delayed in Libya by 41 to 46 days and 34 to 38 days in the UK.

Amaotey et al. (2015) examined the delay causes and effects in Ghanaian state housing construction projects. the study indicated that the factors that causes delay construction projects were; delay in paying contractors, price fluctuation/inflation, increases of materials prices, insufficient finances from project sponsors, variation orders and absence of good financial or capital market. The major impacts of delays are cost and time overrun, litigation, continuity by client and adjudication.

Khoshgoftar et al. (2010) investigated causes of delays in Iranian construction projects. The findings identified that finance and payments of completed work, inadequate planning, improper site management, improper contract management, and communication gap between the parties involved in the are the main reasons that causes delay in the Iranian construction projects. Several studies related to possible causes of delay in construction projects have been described in the literature. Table 1 displays some of the recent research works and their related references. From Table 1, it can be observed that sources of delay were grouped by researchers under different classes, depending on the reponsible party (such as owners, client, contractor etc.) or the associated theme (such as managerial, technical etc.).

Table 1: List of 10 selected previous studies about causes of delay in construction projects (2010 2019)

References

Brief description of the study

Causes of delay

Kazaz et al. (2012)

Conducted a survey on 34 factors affecting project duration of 71 construction companies in Turkey

Outlined the most significant delay factor to include design and materials changes; payments delay; problem of cash flows; poor labor productivity and contractors financial problems.

Yang et al. (2013)

Analysis of the contents of legal cases from Supreme Court verdicts in Taiwan on the main causes of schedule delays in construction projects.

The research work discovered that change orders, changed of scope, weather condition and construction site handover delays as the major reasons for schedule delays in construction related legal cases.

Akogbe et al. (2013)

Analysis of delay factors which affect the delay in completion of construction projects in Benin.

Delays in construction project emanated due to contractors financial capability, owners financial difficulties, poor performance of subcontractors, materials procurement of contractor, inadequate planning and scheduling, sluggish inspection of completed works by the consultants and unavailability of equipment.

Kim et al. (2016)

A survey of delay factor analysis for hospital projects in Vietnam.

The paper indicated that the top five causes of delay in hospital projects were: Owners financial difficulties, change of design, incompetent contractor, inadequate experience of contractor and improper handling of responsibilities by supervisors

Aditya et al. (2017)

Review on the causes of delay and difficulties in execution of water supply project in India.

The causes of delay were due to delays in administration (Land acquisition, planning and coordination), difficulties in execution and non-performance of the contractors.

Amoatey & Ankrah (2017)

Conducted a survey of 48 roads projects to examines the causes of delay of roads projects in Ghana.

The delays were classified as client-related, contractor-related and donor-related. The client-related delays include delay in payment of completed work, changes of scope during the construction and delay to deliver the site to the contractor. The contractor-related delay centered on inadequate experience of contractor, while the donor-related delay was on inflexible funding allocation for project items.

Agyekum-Mensah & Knight (2017)

Exploring the practitioners perspective on 32 delay causes in the UK construction industry in the post- recession era.

Inadequate project planning, poor commercial decisions, design problems, scope creep and unclear project requirements, financial problems, inexperience and incompetence, inappropriate risks transfer and mitigation, poor resource management.

Zidane and Andersen (2018)

Analysis of the top 10 universal delay factors in construction projects and review of delay factors in major Norwegian construction projects.

The Norwegian construction industry experienced delays due to poor planning, scheduling problem, slow decision process, administrative challenges and bureaucratic inadequacies with the project organizations, resources inadequacies, lack of good communication and coordination between parties in the project. The paper highlighted

10 delay factors to comprised changes in design; delay in paying contractors; poor planning and scheduling; bad supervision and site management; inadequate or inappropriate design; contractors inexperience and competence; shortage of finances; sponsor or owners financial difficulties, shortage of resources; poor labor productivity and lack of adequate skills.

Rezaee et al. (2019)

Analyzing factors that causes delays in construction projects in Iran and their effect on project performance.

Incorrect estimation of job, insufficient equipment and correct project completion time, absence of good legal framework relating to job responsibilities and inadequate enforcement of sanctions

Viles et al. (2019)

Examined the assessable examination of factors causing delay in construction projects.

Changes during construction, Poor construction management, Construction errors, Economic/Financial, Conflict/Relationship and Lack of experience.

METHODOLOGY

This study espouses a systematic quantitative literature review method on Causes of Delay in Construction Projects adopting the Systematic Quantitative Assessment Technique (SQAT) developed by Pickering and Bryne (2014). SQAT is systematic in the way papers are assessed and determine their inclusion or exclusion in the review process, and it allows the researchers, to methodically analyze existing academic literature to produce an organized quantitative summary of the field (Pickering and Bryne 2014). The focus of this studies was on only peer reviewed original English journal publications on causes of delay in construction projects to uphold a high quality of papers. The systematic technique explores the geographical spread of the literature, the research methods adopted, the type of literature and their specific focus (Pickering and Bryne, 2014).

SQAT recommends five important dimensions in undertaking an effective systematic review. Each dimension and how it was implemented in this research work is described within this framework. A total of 51 peer-reviewed English articles on causes of delay in construction projects were compared across the dimensions outlined in Table 1.

Table 1: Description and Application of SQAT

S/No.

Dimensions

Application in current study

1.

Define topic

Causes of Delay in Construction Projects (CDCP)

2.

Formulate research questions

Six research questions:

  1. What is the time distribution of CDCP research articles?

  2. Where were these articles written?

  3. What kind of CDCP articles were published? (Conceptual vs. Empirical)

  4. Which journal publishers were adopted by the articles?

  5. What research methods were employed in the research?

  6. What were the specific themes explored in the articles?

3.

Identify key words

Causes of Delay and Construction Projects

4.

Identify the research databases

  1. 6 databases utilized: Emerald; Elsevier; Springer; Wiley; Taylor and Francis; JSTOR.

  2. All in title search using three search combinations:

    1. delay + construction project

    2. delay + project

    3. delay + construction

5.

Read and access publication

  1. Abstracts of articles found were read and where necessary, the entire research works were read to ensure that they were dealing with Causes of Delay in Construction Projects and ensure that the research questions were answered.

  2. Book chapters and conference proceedings were not included; only peer-reviewed conceptual and empirical papers were assessed.

FINDINGS

Time Distribution of Causes of Delay in Cnstruction projects (CDCP) Articles

This research work reviewed 51 papers which met the selection criteria of within ten (10) years (2010 2019); as ten years is considered enough time to include sufficient data required for the study. These were diagrammatically presented in the bar chart below (Figure i).

12

10 11

Number of Articles

8 9

8

6 7

4

4

2 3 3

2 2 2

0

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Year

Figure 1: Time Distribution of CDCP Articles

Geographical Distribution of Causes of Delay in Construction Projects Articles

The geographical distribution of causes of delay in construction projects papers reviewed was presented in figure 2. Asia had the highest number (30); followed by Africa (10); Europe (8); while Australia, North America and South America had 1 each, respectively. These were presented in figure 2 below.

30

30

Number of Articles

25

20

15 10

10

5

0

8

1 1 1

Africa Asia Australia Europe Norh

America

South America

Research Contients

Figure 2: Geographical Distribution of CDCP Articles

Type of Articles on Causes of Delay in Construction Projects

The 51 articles reviewed were divided into two categories; conceptual and empirical. Conceptual articles here mean papers that focuses on the theory and concept of the causes of delay in construction projects, whilst empirical articles were those which includes both quantitative and qualitative studies where conclusion are drawn from evidence verifiable by observations or experience rather than theory or logic (Difference between Conceptual and Empirical Research, 2019). It can be observed from figure 3 that 82% (42 out of 51) articles reviewed were empirical in nature where researchers presented significant practical conclusions on issues that causes delay in construction projects (Khoshgaftar et al. 2010; Muhammad et al. 2015; Hossain et al. 2019). The remaining 18% were conceptual papers in which authors provides recommendations (Keller et al. 2010; Hamzah et al. 2011; Yang et al. 2014). The pie chart below in figure iii depicted the categorization of type of the articles.

Conceptual 18%

Empirical 82%

Empirical Conceptual

Figure 3: Type of CDCP Articles

Distribution of Top 5 Journal Publishers of CDCP Literatures

The table 3 below, shows the journal publishers with the most articles on causes of delay in construction projects (CDCP).

Table 3: Journal Distribution of CDCP Papers

JOURNAL PUBLISHERS

NUMBER OF PAPERS

RANKING

International Journal of Construction Management (Taylor & Francis)

6

1st

Procedia Engineering (Elsevier)

6

1st

KSCE Journal of Civil Engineering (Springer)

5

2nd

Engineering Construction and Architectural Management (Emerald)

4

3rd

Alexandria Engineering (Elsevier)

3

4th

The evidence from table 3 above, shows that International Journal of Construction Management and Procedia Engineering are the most preferred publishers of Causes of Delay in Construction Projects literatures with 6 papers each. Closely followed by KSCE Journal of Civil Engineering with 5 articles, while Engineering Construction & Architectural Management and Alexandria Engineering have 4 and 3 papers, respectively. Other journal site or publishers with publication ranging from one to two were not included in the analysis for ease of interpretations.

Research Method of CDCP Articles

Figure 4 below shows the research method used in each of the 51 CDCP articles reviewed in this research work.

12%

6%

15%

6%

14%

47%

Case study

Survey

Interview

Review

Survey + Case study Survey + interview

Figure 4: Research Methods

Based on the findings in figure 4, the research method mostly adopted in the articles reviewed was survey (47%). This involved the distribution of questionnaires to projects stakeholders (clients, consultants, professionals, owners and users of projects etc.) which would then be collated for analysis and interpretations (Mahmidi, 2011; Marzouk and El-Rasas, 2014; Tahir et al. 2017; Wang and Lin, 2018; Maqsoom et al. 2019). This followed by articles involving case studies (15%) which focuses on organizations or countries issues and impact of causes of delays in construction projects (Yang et al. 2013; Iyer and Kumar, 2016; Koiraila et al. 2017; Guida and Sacco, 2019). The papers that adopted review analysis (14%) which includes theoretical, literature and systematic reviews on delay analysis in construction projects (Yang and Kao, 2012; Doraisamy et al. 2015; Mbala et al. 2018). 12% of the articles adopted combination survey and interviews, which comprised used of both questionnaires and collection of data directly from persons involved in constructions projects (Doloi et al. 2012; Shahsavand and Parchmijalal, 2018; Rachid et al. 2019). Another 6% of the papers reviewed adopted only interviews in collecting data for analysis and interpretation on CDCP (Agyekum-Mensah and Knight, 2017; Durdyev et al. 2017). Lastly, the papers that embraced the methodology of both survey and case studies were 6% (Shebob et al. 2012; Alsuliman, 2019), thus completing the six research methods identified in review of CDCP studies.

CDCP THEMES

It can be observed from figure 5 that the 51articles reviewed on CDCP focuses on 3 themes. Causes of project delay (63%); project delay analysis (23%); and effects of project delay. For the papers with theme on causes of delay, the researchers acknowledged that delays are a common phenomenon in construction projects and its among the challenges must projects faced and investigated the factors that caused cost overrun and scheduled time of projects (Aziz, 2013; Elawi et al. 2016; Al-Hazim et al. 2017; Chen et al. 2019). On the project delay analysis themes, the attention of the researchers was tilted towards method of analyzing causal relationship between delay factors in construction projects (Ekanayeka and Perera, 2016; Chiu and Lai, 2017; Bilgin et al. 2018). While researchers emphasis on the theme on effects of project delay were on analyzing delay factors in construction projects and determining their impacts, mitigations and made recommendations based on the findings of the studies (Senouci and Eldin, 2016; Zailani et al. 2016; Abd El-Karim et al. 2017). Analysis of delay factors, its causes and their impact should be at the forefront of construction project research because of the frequent lengthy delay that occurs which significantly affects most of the projects objective, performance, benefits and costs and in some cases many projects are stalled or abandoned.

Project Delay Analysis 12

Themes

Effects of Project Delay 7

Causes of Project Delay 32

0 5 10 15 20 25 30 35

Number of Articles

Figure 5: CDCP Themes

DISCUSSION OF RESULTS

As seen in figure 1, there is continuous, though uneven growth trend in research observed between 2010 and 2015. However, from 2016 there appeared to be an increase in interest of scholars on the topic, though still fluctuating. Therefore, it is likely that more researchers will take interest in issues of delay in construction projects.

It is observed from figure 2, Asian counties are seen to have dominated the attention of researchers with 30 out 51 reviewed articles, followed by Africa and Europe with 10 and 8 papers, respectively, and 1 each for Australia, North America and South America. This is not surprising, as most of the research papers on this study are from Asian countries of hina, India, Malaysia, Iran and Saudi Arabia which are among fast growing economies where there is remarkable demand for infrastructural developments (Wang and Lin, 2018; Prasad et al. 2019 Rezaee et al. 2019). Meanwhile, in Africa construction industry holds enormous potential in generating employment and stimulating growth, resulting for rapid expansion of infrastructure by government and private sector initiatives that prompted more construction activities (Aziz and Abdel-Hakim, 2016; Amoatey and Ankrah, 2017; Gebrehiweta and Luo, 2017), hence the interest of researchers in delay analysis of construction projects in the continent.

CONCLUSION

This studies considered 51 peerreviewed journal articles on causes of delays in constructions project which were examined based on six key classifications: the time distribution of the articles, where the articles were written, article type, which journal publishers were adopted by the articles research methods employed and the themes explored in the articles. The findings showed that the continent with highest articles on causes of delay in construction projects is Asia. Majority of the articles reviewed were empirical studies and survey method was mostly adopted with less of interview. The findings of the studies were limited by the fact that only peer-reviewed journal articles were included in the research work, book chapters and conference proceedings were excluded. Another limitation is the methodology used of a title search in six databases rather than search using a key word.

However, notwithstanding of these limitations, this study is vital as it identify a clear path on the current situation of issues arising on causes of delay in construction projects and provides clear direction on the areas that future research needs to address in order to mitigate risk associated with delays in construction projects.

Therefore, the following recommendations for future research work on this study were as follows:

Reviewers/Scholars should include, book chapters and conference proceedings in their studies, this is to further improve the understanding of the causes of delay in construction projects.

Future research should also focus on critical analysis and conceptual work and support their research work with considerable theoretical framework method in order to have all round review on causes of delay in construction projects.

Future study emphasis should be tilted towards investigating the impact and risk management strategies of delays in construction projects.

Potential researchers should look at comparative studies between countries on this area as since delays in construction projects has become a global phenomenon, and many projects continue to experience delay despite the adoption of modern project management techniques and application of advanced technology.

REFERENCES

[1] Abd El-Karim, M. S. B. A., Mosa El Nawawy, O. A., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC journal, 13(2), 202-216.

[2] Aditya, A. K., Douglass, D. A., & Bhattacharya, M. (2017). Urban infrastructure development works in India: Delay and difficulties in implementation with reference to a water supply project. Journal of The Institution of Engineers (India): Series A, 98(3), 349-354. https://doi/10.1007/s40030-017- 0214-2

[3] Agyekum-Mensah, G., & Knight, A. D. (2017). The professionals perspective on the causes of project delay in the construction industry. Engineering, Construction and Architectural Management.

[4] Akogbe, R. K. T., Feng, X., & Zhou, J. (2013). Importance and ranking evaluation of delay factors for development construction projects in Benin. KSCE Journal of Civil Engineering, 17(6), 1213-1222.

[5] Al-Momani, A. (1996), Construction cost prediction for public school buildings in Jordan, Construction Management and Economics, Vol. 14, pp.

311-7.

[6] Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and cost overrun in infrastructure projects in Jordan. Procedia Engineering, 182(2017), 18- 24.

[7] Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801-808.

[8] Amehl, O., Soyingbe, A. & Odusami, K. (2010), Signicant factors causing cost overruns in telecommunication projects in Nigeria, Journal of Construction in Developing Countries, Vol. 15.

[9] Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business.

[10] Amoatey, C. T., & Ankrah, A. N. O. (2017). Exploring critical road project delay factors in Ghana. Journal of Facilities Management.

[11] Anysz, H., & Buczkowski, B. (2018). The association analysis for risk evaluation of significant delay occurrence in the completion date of construction project. International Journal of Environmental Science and Technology, 1-6.

[12] Association of Construction Development (2014), Construction delays, available at: www.associationofconstructiondevelopment.org.

[13] Aziz, R. F. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3), 387-406.

[14] Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515-1539.

[15] Bilgin, G., Dikmen, I., & Birgonul, M. T. (2018). An ontology-based approach for delay analysis in construction. KSCE Journal of Civil Engineering, 22(2), 384-398.

[16] Budayan, C., Dikmen, I., Birgonul, M. T., & Ghaziani, A. (2018). A computerized method for delay risk assessment based on fuzzy set theory using MS project. KSCE Journal of Civil Engineering, 22(8), 2714-2725.

[17] Chen, G. X., Shan, M., Chan, A. P., Liu, X., & Zhao, Y. Q. (2019). Investigating the causes of delay in grain bin construction projects: the case of China. International Journal of Construction Management, 19(1), 1-14.

[18] Chiu, B. W., & Lai, J. H. (2017). Project delay: key electrical construction factors in Hong Kong. Journal of civil engineering and management, 23(7), 847-857.

[19] Difference Between Conceptual and Empirical Research (2019). Retrieved from https://www.pediaa.com/difference-between-conceptual-and- empirical-research/

[20] Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International journal of project management, 30(4), 479-489.

[21] Doraisamy, S. V., Akasah, Z. A., & Yunus, R. (2015). An Overview on the Issue of Delay in the Construction Industry. In In CIEC 2014 (pp. 313- 319). Springer, Singapore.

[22] Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4(1), 1291117. [23] Ekanayake, E. M. K., & Perera, B. A. K. S. (2016). Appropriate delay analysis techniques to analyse delays in road construction projects in Sri

Lanka. Built Environment Project and Asset Management.

[24] Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners perspective of factors contributing to project delay: case studies of road and bridge projects in Saudi Arabia. Procedia Engineering, 145, 1402-1409.

[25] Gebrehiwet, T., & Luo, H. (2017). Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Procedia engineering, 196, 366-374.

[26] Guida, P. L., & Sacco, G. (2019). A method for project schedule delay analysis. Computers & Industrial Engineering, 128, 346-357.

[27] Hamzah, N., Khoiry, M. A., Arshad, I., Tawil, N. M., & Ani, A. C. (2011). Cause of construction delay-Theoretical framework. Procedia Engineering, 20, 490-495.

[28] Hossain, M. A., Raiymbekov, D., Nadeem, A., & Kim J. R. (2019). Delay causes in Kazakhstans construction projects and remedial measures.

International Journal of Construction Management, 1-19.

[29] Iyer, K. C., & Kumar, R. (2016). Impact of delay and escalation on cash flow and profitability in a real estate project. Procedia Engineering, 145(7), 388-395.

[30] Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes of delays in construction projects in Turkey. Journal of civil Engineering and Management, 18(3), 426-435.

[31] Kelleher Jr, T. J., Nelson, E. L., & Miller, G. E. (2010). The resurrection of rice?" The evolution (and de-evolution) of the ability of contractors to recover delay damages on Federal Government Construction Contracts. Public Contract Law Journal, 305-330.

[32] Khoshgoftar, M., Bakar, A. H. A., & Osman, O. (2010). Causes of delays in Iranian construction projects. International Journal of Construction Management, 10(2), 53-69.

[33] Kim, S. Y., & Tuan, K. N. (2016). Delay factor analysis for hospital projects in Vietnam. KSCE Journal of Civil Engineering, 20(2), 519-529.

[34] Koirala, S., Hill, D., & Morgan, R. (2017). Impacts of the delay in construction of a large scale hydropower project on potential displacees. Impact Assessment and Project Appraisal, 35(1), 106-116.

[35] Mahamid, I. (2011). Risk matrix for factors affecting time delay in road construction projects: owners' perspective. Engineering, Construction and Architectural Management.

[36] Maqsoom, A., Choudhry, R. M., Umer, M., & Mehmood, T. (2019). Influencing factors indicating time delay in construction projects: Impact of firm size and experience. International Journal of Construction Management, 1-12.

[37] Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction projects. Journal of advanced research, 5(1), 49-55.

[38] Mbala, M., Aigbavboa, C., & Aliu, J. (2018, July). Causes of delay in various construction projects: a literature review. In International Conference on Applied Human Factors and Ergonomics (pp. 489-495). Springer, Cham.

[39] Muhamad, N. H., Mohammad, M. F., Ahmad, A. C., & Hussein, E. (2015). Problems Associated with Delay Analysis Methodology in Malaysian Construction Delay Practice. In In CIEC 2014 (pp. 301-311). Springer, Singapore.

[40] Oyegoke, A. S., & Al Kiyumi, N. (2017). The causes, impacts and mitigations of delay in megaprojects in the Sultanate of Oman. Journal of Financial Management of Property and Construction.

[41] Pickering, C., & Byrne, J. (2014). The benefits of publishing systematic quantitative literature reviews for PhD candidates and other early career researchers. Higher Education Research & Development, 33(3), 534-548

[42] Prasad, K. V., Vasugi, V., Venkatesan, R., & Bhat, N. (2019). Analysis of causes of delay in Indian construction projects and mitigation measures. Journal of Financial Management of Property and Construction.

[43] Rachid, Z., Toufik, B., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 19(5), 371-381.

[44] Rezaee, M. J., Yousefi, S., & Chakrabortty, R. K. (2019). Analysing causal relationships between delay factors in construction projects. International Journal of Managing Projects in Business.

[45] Senouci, A., Ismail, A., & Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia engineering, 164, 368-375. [46] Shahsavand, P., Marefat, A., & Parchamijalal, M. (2018). Causes of delays in construction industry and comparative delay analysis techniques with

SCL protocol. Engineering, Construction and Architectural Management.

[47] Shebob, A., Dawood, N., Shah, R. K., & Xu, Q. (2012). Comparative study of delay factors in Libyan and the UK construction industry. Engineering, Construction and Architectural Management.

[48] Tahir, M. M., Haron, N. A., Alias, A. H., & Diugwu, I. A. (2017). Causes of Delay and Cost Overrun in Malaysian Construction Industry. In Global Civil Engineering Conference (pp. 47-57). Springer, Singapore.

[49] Viles, E., Rudeli, N. C., & Santilli, A. (2019). Causes of delay in construction projects: a quantitative analysis. Engineering, Construction and Architectural Management.

[50] Wang, W., & Lin, W. (2018). Study on the influence factors of urban subway project delay in the initial construction stage. Journal of Discrete Mathematical Sciences and Cryptography, 21(6), 1193-1197.

[51] Yang, J. B., & Kao, C. K. (2012). Critical path effect based delay analysis method for construction projects. International Journal of Project Management, 30(3), 385-397.

[52] Yang, J. B., Chu, M. Y., & Huang, K. M. (2013). An empirical study of schedule delay causes based on Taiwan's litigation cases. Project Management Journal, 44(3), 21-31.

[53] Yang, J. B., Huang, K. M., Lee, C. H., & Chiu, C. T. (2014). Incorporating lost productivity calculation into delay analysis for construction projects. KSCE Journal of Civil Engineering, 18(2), 380-388.

[54] Zailani, S., Ariffin, H. A. M., Iranmanesh, M., Moeinzadeh, S., & Iranmanesh, M. (2016). The moderating effect of project risk mitigation strategies on the relationship between delay factors and construction project performance. Journal of Science and Technology Policy Management.

[55] Zidane, Y. J. T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business.

APPENDIX 1

Literature Map of the 51 Articles Reviewed

Reference

Country

database

Journal

Type of Article

Method adopted

Specific theme

Keller et al. (2010)

USA

JSTOR

Public Contract Law Journal

Conceptual

Theoretical review

Effects of project delay

Khoshgoftar et al. (2010)

Iran

Taylor & Francis

International Journal of Construction Management

Empirical

Survey

Causes of project delay

Mahmidi I. (2011)

Palestine

Emerald

Engineering, Construction and Architectural Management

Empirical

Survey

Causes of project delay

Hamzah et al. (2011)

Malaysia

Elsevier

Procedia Engineering

Conceptual

Theoretical review

Causes of project delay

Orangi et al. (2011)

Australia

Elsevier

Procedia Engineering

Empirical

Interview

Causes of project delay

Doloi et al. (2012)

India

Elsevier

International Journal of Project Management

Empirical

Survey and Interview

Causes of project delay

Kazaz et al. (2012)

Turkey

Taylor & Francis

Journal of Civil Engineering and Management

Empirical

Survey

Causes of project delay

Shebob et al. (2012)

UK

Emerald

Engineering, Construction and Architectural Management

Empirical

Survey and Case study

Effects of project delay

Yang & Kao (2012)

Taiwan

Elsevier

International Journal of Project Management

Conceptual

Systematic review

Project delay analysis.

Akogbe et al. (2013)

Benin

Springer

KSCE Journal of Civil Engineering

Empirical

Survey

Project delay analysis.

Aziz R.F. (2013)

Egypt

Elsevier

Alexandria Engineering Journal

Empirical

Survey

Causes of project delay

Yang et al. (2013)

Taiwan

Wiley

Project Management Journal

Empirical

Case study

Causes of project delay

Marzouk & El-Rasas (2014)

Egypt

Elsevier

Journal of Advanced Research

Empirical

Survey

Causes of project delay

Yang et al. (2014)

Taiwan

Springer

KSCE Journal of Civil Engineering

Conceptual

Case study

Causes of project delay

Muhammad et al. (2015)

Malaysia

Springer

CIEC

Empirical

Survey

Project delay analysis

Doraisamy et al. (2015)

Malaysia

Springer

CIEC

Conceptual

Literature review

Project delay analysis.

Aziz and Abdel- Hakim (2016)

Egypt

Elsevier

Alexandria Engineering Journal

Empirical

Survey and Case study

Causes of project delay

Ekanayeka & Perera (2016)

Sri Lanka

Emerald

Built Environment Project and Asset Management

Empirical

Survey and Interview

Project delay analysis

Elawi et al. (2016)

Saudi Arabia

Elsevier

Procedia Engineering

Empirical

Case study

Causes of project delay

Kim et al. (2016)

Vietnam

Springer

KSCE Journal of Civil Engineering

Empirical

Survey and Interview

Causes of project delay

Iyer & Kumar (2016)

India

Elsevier

Procedia Engineering

Empirical

Case study

Project delay analysis

Senouci & Eldin (2016)

Qatar

Elsevier

Creative Construction Conference

Empirical

Survey

Effects of project delay

Zailani et al. (2016)

Malaysia

Emerald

Journal of Science and Technology Policy Management

Empirical

Survey

Effects of project delay

Abd El-Karim et al. (2017)

Egypt

Elsevier

HBRC journal

Empirical

Survey

Effects of project delay

Aditya et al. (2017)

India

Springer

J. Inst. Eng. India Ser. A

Conceptual

Theoretical Review

Causes of project delay

Agyekum-Mensah & Knight (2017)

UK

Emerald

Engineering, Construction and Architectural Management

Empirical

Interview

Causes of project delay

Al-Hazim et al. (2017)

Jordan

Elsevier

Procedia Engineering

Empirical

Survey

Causes of project delay

Amoatey & Ankrah (2017)

Ghana

Emerald

Journal of Facilities Management

Empirical

Survey

Causes of project delay

Chiu & Lai (2017)

Hong Kong

Taylor & Francis

Journal of Civil Engineering and Management

Empirical

Survey

Project delay analysis

Durdyev et al. (2017)

Cambodia

Taylor & Francis

Civil & Environmental Engineering

Empirical

Interview

Causes of project delay

Gebrehiweta & Luo (2017)

Ethiopia

Elsevier

Procedia Engineering

Empirical

Survey

Impact of project delay

Koirala et al. (2017)

Nepal

Taylor & Francis

Impact Assessment and Project Appraisal

Empirical

Case study

Impact of project delay

Oyegoke & Al Kiyumi (2017)

Oman

Emerald

Journal of Financial Management of Property and Construction

Empirical

Survey

Causes of project delay

Tahir et al. (2017)

Malaysia

Springer

Global Civil Engineering Conference

Empirical

Survey

Causes of project delay

Anysz & Buczkowski (2018)

Poland

Springer

International Journal of Environmental

Empirical

Survey

Project delay analysis

Science and Technology

Bajjou & Chafi (2018)

Morocco

Taylor & Francis

International Journal of Construction Management

Empirical

Survey

Causes of project delay

Bilgin et al. (2018)

Turkey

Springer

KSCE Journal of Civil Engineering

Literature review

Case study

Project delay analysis

Budayan et al. (2018)

Turkey

Springer

KSCE Journal of Civil Engineering

Empirical

Survey

Project delay analysis

Mbala et al. (2018)

South Africa

Springer

International Conference on Applied Human Factors and Ergonomics

Conceptual

Literature review

Causes of project delay

Shahsavand & Parchamijalal (2018)

Iran

Emerald

Engineering, Construction and Architectural Management

Empirical

Survey and Interview

Causes of project delay

Wang & Lin (2018)

China

Taylor & Francis

Journal of Discrete Mathematical Sciences and Cryptography

Empirical

Survey

Causes of project delay

Zidane and Andersen (2018)

Norway

Emerald

International Journal of Managing Projects in Business

Empirical

Survey

Causes of project delay

Alsuliman J.A. (2019)

Saudi Arabia

Elsevier

Alexandria Engineering Journal

Empirical

Survey and Case study

Causes of project delay

Chen et al. (2019)

China

Taylor & Francis

International Journal of Construction Management

Empirical

Survey

Causes of project delay

Guida & Sacco (2019)

Italy

Elsevier

Computers & Industrial Engineering

Empirical

Case study

Project delay analysis

Hossain et al. (2019)

Kazakhstan

Taylor & Francis

International Journal of Construction Management

Empirical

Survey and Interview

Causes of project delay

Maqsoom et al. (2019)

Pakistan

Taylor & Francis

International Journal of Construction Management

Empirical

Survey

Causes of project delay

Prasad et al. (2019)

India

Emerald

Journal of Financial Management of Property and Construction

Empirical

Survey

Causes of project delay

Rachid et al. (2019)

Algeria

Taylor & Francis

International Journal of Construction Management

Empirical

Survey and Interview

Causes of project delay

Rezaee et al. (2019)

Iran

Emerald

International Journal of Managing Projects in Business

Empirical

Case study

Project delay analysis

Viles et al. (2019)

Uruguay

Emerald

Engineering, Construction and Architectural Management

Conceptual

Literature review

Causes of project delay