Comparative Analysis of Tunnel Formwork System and Aluminum Formwork System for High Rise Buildings

DOI : 10.17577/IJERTV6IS050520

Download Full-Text PDF Cite this Publication

Text Only Version

Comparative Analysis of Tunnel Formwork System and Aluminum Formwork System for High Rise Buildings

Kalbhor Shailesh S

PG Student Civil – Construction management Rajarambapu Institute of Technology, Rajaramnagar,Sangali

Abstract The high rise building construction consist of number of repetitive activities and also have same identical floors. The increase in duration of construction greatly affects the construction cost. Selection of best formwork system gives best result in cost saving. Formwork consist of 20-25% of total cost of project[2]. So that used advanced formwork system helps in cost saving as reduction slab cycle time. This study is done for comparative analysis of tunnel formwork system and aluminum formwork used for high rise building construction.

Keywords Formwork, High Rise Building, Tunnel Formwork , Cost

  1. INTRODUCTION

    The high rise building involves high cost investment which is increased day by day as delay in execution is occurred formwork systems are key factors in determining the success of a building construction project in terms of cost, speed, quality and safety of work. Selecting poor quality of formwork systems in aiming to minimize the cost of project will directly affect the speed and quality of construction. According to the National building code of India, a tall building is one with four floors or more or a high-rise building is one 15 meters or more in height. . The formwork used in construction project contain 20-25% cost of project[2], so that selection of best suitable formwork for high rise building will result in successful completion of project.

    The formwork can be defined as the temporary structure which is used to support the fresh concrete until it gain its own strength. The Formwork selection for high rise building is depend upon the cost , time and finishing quality. High rise building construction consist of many type of repetitive activity. For repetitive work and high rise building construction Tunnel formwork system and aluminum formwork system is developed.

  2. TUNNEL FORMWORK SYSTEM

    The tunnel formwork is room formwork in which RCC slab and walls are casted in continuous pour. Then By Using hot air blows thermal curing is used for accelerate the concrete. The cycle Time for tunnel formwork system is 1-3days only, The tunnel formwork system is very useful for repetitive room design.

    Operational cycle

    The 24 Hour cycle defines the works to be done each day. To establish this cycle, the overall structure is divided into a number of more or less similar construction phases,

    Dr. A. C. Attar

    Professor Department of Civil Engineering

    Rajarambapu Institute of Technology,

    Rajaramnagar,Sangali

    corresponding to a days work. The necessary manpower and equipment are then determined according to the size of these phases. To reach maximum efficiency, the phases done every day are similar.

    The cycle is divided into the following activities:

    1. Initial striking operations

    2. Movement of forms

    3. Final preparation

    4. Pouring

  3. ALUMINIUM FORMWORK SYSTEM Aluminium formwork also known as MIVAN technology..

    MIVAN system is formwork construction, cast in situ concrete wall and floor slabs cast monolithic provides the structural system in one continuous pour. Large room sized forms for walls and floors slabs are erected at site. These forms are made strong and sturdy, fabricated with accuracy and easy to handle. They afford large number of repetitions (around 250).

    Operational cycle time

    Sr.no

    Activity

    1

    Wall Shuttering

    2

    Slab Shuttering

    3

    Prob Install

    4

    Slab level

    5

    Leveling

    6

    Line and plumb

    7

    Wall reinforcement

    8

    Slab Reinforcement

    9

    Electrical fitting

    10

    Casting of slab

    11

    De shuttering wall

    12

    De shuttering slab

  4. OBJECTIVES

    1] Collection of primary and secondary data

    2] Comparison of Tunnel formwork system and aluminum formwork system used for high rise building construction on time cost quality and its characteristics parameters.

    3] Techno-Economical analysis of both formwork system

  5. METHODOLOGY

    For data collection questionnaires was prepared on the basis of objectives of the project. Then for questionary survey and data collection two different sites were studied, Rohan Builders India Pvt Ltd. is using Tunnel Formwork System and Tricon Infra Buildtech Pvt Ltd using aluminiumsystem.

    Case Study 1

    Case study2

    RohanAbhilasha,wagholi

    PanchshilHighrise,Wagholi

    Residential

    Residential

    Tunnel Formwork System

    Aluminium Formwork System

    MESA Imalat Hi TekInsat

    Tricon Infra Buildtechpvt .Ltd.

    Case study Details

  6. DATA COLLECTION A] Data Collected from Interview

    Sr.No

    Parameters

    1

    Cost

    Initial Invesment

    High

    Avg cost/m2

    25000/m2

    Labour Cost/m2

    200/m2

    2

    Numbers of repetations

    500

    3

    Cycle time

    3days

    4

    Deshuttering time

    10hrs

    5

    Manpower requirments

    55-60Nos/slab area

    6

    Accuracy

    +- 3mm

    7

    Durability

    High

    8

    Wastage of material

    0%

    9

    Additional Equipment Requirements

    Tower crane, Concrete Spreader

    10

    Curing method

    Thermal curing

    11

    Finishing

    Paint Finish

    From Case study 1 Rohan Builders:

    From Case Study 2 Tricon Infra Buildtech

    Sr.No

    Description

    1

    Initial Investment(for Project)

    High

    2

    Average cost/sq.m

    8500

    3

    Labour cost / sq.m

    165

    4

    Maintenance cost

    10

    5

    Storage cost

    02

    6

    Cycle time

    12days

    7

    Size of panel

    600*2050

    8

    Weight of panel

    8.50kg/sq.m

    9

    Salvage value

    50% of cost

    10

    Number of repetitins

    110Nos

    11

    De-shuttering time

    24hrs

    12

    Additional Equipment requirement

    Staff and material

    13

    Manpower requirement

    3labour/day/sq.m

    15

    Durability

    High

    16

    Finishing

    Fine

    17

    Percentage of wastage

    0%

    18

    Accuracy

    +-5mm

    19

    Curing method

    Curing compound

  7. DATA ANALYSIS General Comparative statement

    Sr.No

    Description

    Tunnel

    formwork

    Aluminium

    Formwork

    1

    Initial Investment(for Project)

    High

    High

    2

    Average cost/sq.m

    25000rs

    8500rs

    3

    Labour cost / sq.m

    175-200/slab

    area

    165

    4

    Maintenance cost

    10

    5

    Storage cost

    02

    6

    Cycle time

    24hours

    12days

    7

    Size of panel

    1 to 4 m

    600*2050

    8

    Weight of panel

    2-4 tonne

    8.50kg/sq.m

    9

    Salvage value

    50% of cost

    10

    Number of repetitions

    500nos

    110Nos

    11

    De-shuttering time

    10hrs

    24hrs

    12

    Additional Equipment

    requirement

    Tower crane &

    boom placer

    Staff and material

    13

    Manpower

    requirement

    55-60nos /slab

    3labour/day/sq.m

    14

    Permissible fresh

    concrete pressure

    NA

    NA

    15

    Durability

    High

    High

    16

    Finishing

    Paint finish

    Fine

    17

    Percentage of

    wastage

    0

    0%

    18

    Accuracy

    +-3mm

    +-5mm

    19

    Curing method

    Thermal curing

    Curing compound

    20

    Casting System

    RCC

    monolithic

    RccFramed

    Initial Cost/m2

    Type

    Unit

    Rate

    Tunnel Formwork

    Sq. mt

    25000 Rs

    Aluminium Formwork

    Sq. mt

    8500 Rs

    Cycle Time (days)

    Type

    Days

    Tunnel Formwork

    3 days

    Aluminium Formwork

    14 days

    Numbers of repetitions

    Type

    Nos.

    Tunnel Formwork

    500

    Aluminium Formwork

    200

    Cost Analysis for Numbers of repetitions

  8. CONCLUSION

    From Data analysis and study of both formwork system it is concluded that initial cost/sq.m for tunnel formwork is high But as the numbers of repetations increases tunnel formwork system is best suitable after 500 nos repetations. So that Aluminium formwork can be used for 200 repetations.

  9. REFERENCES

  1. Sandip P. Pawar and P.M.Atterde (June 2014) Comparative analysis of formwork in multistory building. IJRET,Volume;03 Special issue;09

    June 2014

  2. ArbazKazi and FauwazParkar (Dec 2015) Comparative study and decision making for formwork technique to be adopted on construction site in Mumbai IJRET Volume; 04 Issue; 12 Dec 2015

  3. Hisham A. Abou Ibrahim and Farook R. Hamzeh (April 2016) Role of Formwork system in High Rise building construction

    The masterbuilder april 2016

  4. K.Loganathan and K.E.Viswanathan ( April 2016) A study on Cost, Duration and Quality analysis of different formworks in high rise building IJSER Volume 7; Issue 4 April 2016

  5. Tejas D. Aradhye and Emeritus M.R.Apte ( May 2016 )

    Study of Advanced tunnel formwork system in high rise building

    IJRET Volume; 05 Issue; 05 May 2016

  6. National Building code of india 2005

Leave a Reply