Developing a Module Helping to Optimize the Cost of Construction of Residential Buildings using the Concept of Value Engineering
Thamarai Selvan. P
-
ech – Construction Engineering and Management
SRM University Kanchipuram, India
Jagannathan. P. M.Tech (Ph.D) Educational consultant SRM University Kanchipuram, India
Abstract – Keeping the costs low with traditional cost management has been a commonly applied measure to improve competitiveness. However, keeping cost down alone is not enough, there is an increasing need for improve in schedule as well as efficiency and effectiveness. Value engineering is thus arguably of greater importance than cost management efforts. Value engineering is used to analyze the function of the materials and methods and to obtain its required functions at the lowest total cost without reducing the necessary quality of performance. This method saves money and ensures that projects are cost-effective, time-effective and or improves the quality of the project. The methodology consists of three stages. The first is pre workshop in which the value engineering team is formed and the collection of data from an organization is done. The second and core stage is workshop stage with five phases which are information, functional, creative, evaluation and presentation where best alternative recommendations are made. The last is post workshop stage where the recommendations from second stage will be implemented. The main aim of this thesis is to develop a Value Engineering methodology that leads to reduce cost and improve schedule of residential building projects for people in an applicable way that local professionals can understand and apply. An existing project data was collected for case study and it was studied and the methodology was applied for improvement of the project by saving the cost and improving schedule. The developed methodology forms the first step towards applying Value Engineering in local projects and it can easily be adapted to serve other sectors like infrastructure.
-
INTRODUCTION
Keeping costs low with traditional methods has been a common practice to improve competitiveness. Saving money and also providing better value for the money is a concept that everyone emphasizes. Value Engineering is a practice whose goal is, always, to achieve value for money. A systematic and organized approach to provide the necessary functions in a project at the lowest cost. Value engineering recommends the replacement of materials, methods or techniques with less expensive alternatives, without lowering its functional standards. It is focused mainly on the functions of various techniques and materials, rather than their physical characteristics. Also aims to deliver measurable value improvements through cost reduction and or improve quality and also by improving the schedule of the project for the customer. These features cannot be avoided if a company is to continue meeting the rising expectations of its customer, who
will always take their business to where they can get the highest quality at the lowest possible price.
A. Scope
The scope of this study is to analyze the concepts of value engineering over an existing residential building projects and obtaining the best alternatives by reducing the cost and also improving the schedule of the project to develop and prioritize value engineering concepts over the future projects. Value engineering techniques can be applied in logistics, material procurement, and design of services, construction methodology, and quality and inventory management. Thus, it is observed that the scope for application is present almost in every aspect of any industry.
-
METHODOLOGY
The methodology explains the procedure and sequence of steps that are framed to follow in the project. The methodology is divided into different steps, accordingly the project procedure is divided. The methodology is depicted in a flow chart format for easy understanding.
-
Literature collection and study
Various books papers and relevant literature regarding value engineering and value management in construction were collected and the concept was studied in depth. Seminars relating to value engineering were studied for thorough understanding of subject.
-
Selection of case study
With due permission of client a residential building project was selected for case study as this provides scope for value analysis and at the same time value engineering for the next repetitive project.
-
Data collection
All necessary and possible information regarding the project were collected by visiting the site office and company directly. The information includes financial and technical aspects of the projects. The data were collected though meetings, interviews and questionnaire with owner, consultant, contractor, architect and uses. Other information regarding alternative materials was collected from manufacturers and dealers.
-
Interpretation of data
From the chunk of the data available, useful data related to scope of the case were interpreted.
-
Identification of feasible alternatives
The areas where value engineering could be applied were identified for improving value. The other alternatives performing the same function at a lower cost and better attributes were recognized
-
Recommendations / conclusion
The scope and application of value engineering in a project was successfully implemented, which yielded improvement in the value of the under study.
-
-
QUESTIONNAIRE ANALYSIS
Questionnaire survey is conducted in order to find the knowledge about value engineering and implementation of value engineering by the local companies in the construction practice. From 20 members the results were collected which includes contractors, professionals, consultants and owners. In the analysis of questionnaire, it is found that almost every company is unaware of value engineering. They are very keen to increase revenue by incorporating cost management by substituted material without even considering the improvement in the quality. They are substituting material in place of other material which may be costlier than the substituting material. The companies are not aware of the aftermath of the usage of low cost material. The owners point is they do not want to try anything new without knowing the result of the alternatives for sure. .
-
CASE STUDY
For the purpose of this study, data of the existing residential building project were collected. As per the scope of the research, the VE concept should be applied during the initial phases of the project in order to gain more benefit.
-
The project name is Nana Nani apartments Block F which is located in Coimbatore. This project is constructing by the company Sivasakthi builders.
-
The project will be built on an overall area of 14195 square feet and the built-up area of 8760. The estimated cost of the project is 6 crores 60 lakhs.
-
This block consists of five floor and terrace floor where the stilt floor is allocated for parking space and the other four for houses.
-
Each floor consists of 8 houses of 2bhk with staircases on both sides and a lift in the middle. Open to sky spaces are also provided in every floors.
-
Quality model
Quality model is described as a quantitative description of the owner requirements. This model is done to know if the owners requirement will be fulfilled as expected by analyzing the project data. This inludes ranking of elements operational effectiveness, architectural performance, capital cost effectiveness, schedule, maintenance, user comfort and
expandability from 2 to 10 as in 2 for very poor and 10 for very good.
Fig. 1. Quality model
The Figure 1 shows the graphical representation of quality model in which the solid blue line represents the owners expectation and the dotted red line shows the design parameters.
-
Uniformat presentation
Uniformat presentation of bill of quantities is done to find out the cost for separate works in the project. For buildings, the most common work breakdown structure for a construction cost model is based on the Uniformat system.
Fig. 2. Uniformat model
Figure.2 shows the uniformat bill of quantities in which the cost for each individual items in every work is mentioned in terms of lakhs.
-
-
IDENTIFICATION OF ALTERNATIVES
The main objective in this stage is to be creative and brainstorm alternate proposals and solutions. Many techniques are available to stimulate creative thinking that may be applied during this stage. In this study brainstorming technique is used. The items under consideration are external walls, partition walls, water tanks, windows, sunshades, parking floor, Terrace ceramic floor, plastering, putty and painting works.
A. Technique used
To find out the best alternative from many, evaluation will be done for each and every alternatives. This evaluation of alternatives is done by using the Decision Matrix Analysis technique. Decision Matrix Analysis is a useful technique to use for making a decision in which ranking of alternatives is done. It's particularly powerful where you have a number of good alternatives to choose from, and many different factors to take into account. This makes it a great technique to use in almost any important decision where there isn't a clear and obvious preferred option. To do the ranking of all the alternatives and find the best of them a simple methodology is carried out and the technique has its essence in the mutual comparison where each is compared with all others and points are given based on their differences from 1 to 3 where 1 is no difference and 3 is major difference. When the function A is evaluated with B, then A is evaluated with next function C and this is continued till all the functions are compared with all other functions and rated.
-
EVALUATION OF ALTERNATIVES
For evaluation ranking is done to each and every alternative items based on seven different functions which are cost, schedule, aesthetics, maintenance, durability, availability and efficiency.
TABLE I. FUNCTION CODES
Code
Item
A
Initial cost
B
Schedule
C
Aesthetics
D
Maintenance
E
Durability
F
Availability
G
Efficiency
-
External walls
The external walls are done with fly ash bricks of 9" thickness. The alternatives considered are AAC blocks, hollow concrete blocks, solid concrete blocks and burnt bricks.
TABLE II. EVALUATION OF ALTERNATIVES FOR EXTERNALL WALLS
Criteria
A
B
C
D
E
F
G
Weighted
Score
12
11
6
2
2
1
3
Alternatives
Total Score
Solid concrete block
4
4
4
3
4
4
3
143
48
44
24
6
8
4
9
Hollow concrete block
5
4
4
3
3
5
2
151
60
44
24
6
6
5
6
AAC blocks
4
5
4
4
5
4
5
154
48
55
24
8
10
4
15
Burnt Brick
4
3
4
3
5
5
3
135
48
33
24
6
10
5
9
After analyzing the alternatives of AAC blocks are considered for development. It is considered as it performs all the functions required with high thermal efficiency and high pace of construction. It gains a total score of 154.
-
Partition walls
The partition walls are done with fly ash bricks of 4.5" thickness. The alternatives considered for this are Burnt brick wall, ferrocement wall, plywood and hollow concrete block.
Criteria
A
B
C
D
E
F
G
Weighted Score
12
11
6
2
2
1
3
Alternatives
Total Score
Plywood
3
5
4
3
2
5
3
139
36
55
24
6
4
5
9
Hollow concrete block
5
4
4
3
3
5
2
161
60
44
24
6
6
5
6
Ferrocement
5
4
4
4
5
5
4
162
60
44
24
8
10
4
12
Burnt Brick
3
3
4
3
5
5
3
123
36
33
24
6
10
5
9
TABLE III. EVALUATION OF ALTERNATIVES FOR PARTITION WALLS
After analyzing the alternatives of ferrocement walls are considered for development. It is considered as it performs all the functions required high pace of construction. It gains a total score of 162.
-
Windows
The windows are done by using Sal wood. The alternatives considered are Aluminium windows, upvc windows, neem wood windows.
TABLE IV. EVALUATION OF ALTERNATIVES FOR WINDOWS
Criteria
A
B
C
D
E
F
G
Weighted Score
12
11
6
2
2
1
3
Alternatives
Total Score
Aluminum
5
5
3
2
3
5
2
154
60
55
18
4
6
5
6
UPVC
4
5
4
4
4
5
5
163
48
55
24
8
8
5
15
Neem wood windows
4
3
5
4
5
4
4
145
48
33
30
8
10
4
12
After analyzing the alternatives of UPVC are considered for development. It is considered as it performs all the functions required with high pace of construction. It gains a total score of 163.
-
Water tanks and sunshades
From The water tanks and sunshades are built by using M20 grade concrete. the alternatives are M15 concrete and ferrocement concrete.
Criteria
A
B
C
D
E
F
G
Weighted
Score
12
11
6
2
2
1
3
Alternatives
Total Score
M15 concrete
4
3
4
4
4
5
4
138
48
33
24
8
8
5
12
Ferrocement
5
5
4
3
3
5
4
168
60
55
24
6
6
5
12
TABLE V. EVALUATION OF ALTERNATIVES FOR WATERTANKS AND SUNSHADES
After analyzing the alternatives of ferrocement concrete are considered for development. It is considered as it performs all the functions required high pace of construction. It gains a total score of 168.
-
Parking floor
The parking floor is finished with parking paver tiles. the alternatives for this are IPS floor, interlocking blocks, shahabad tiles, PCC floor.
TABLE VI. EVALUATION OF ALTERNATIVES FOR PARKING FLOOR
Criteria
A
B
C
D
E
F
G
Weighted Score
12
11
6
2
2
1
3
Alternatives
Total Score
IPS floor
4
4
3
3
4
4
3
139
48
44
18
8
8
4
9
PCC floor
3
3
3
5
5
5
4
124
36
33
18
10
10
5
12
Shahabad tiles
5
4
3
4
4
3
5
156
60
44
18
8
8
3
15
Interlock blocks
4
5
4
3
4
3
3
153
48
55
24
6
8
3
9
After analyzing the alternatives of Shahabad tiles floor walls are considered for development. It is considered as it performs all the functions required high pace of construction. It gains a total score of 156.
-
Ceramic floor in terrace
In terrace ceramic floor is used for the flooring. the alternatives for that are cement floor, red oxide floor, terracotta floor and mosaic floor.
TABLE VII. EVALUATION OF ALTERNATIVES FOR TERRACE FLOOR
Criteria
A
B
C
D
E
F
G
Weighted Score
12
11
6
2
2
1
3
Alternatives
Total Score
Cement floor
3
3
3
4
4
5
4
120
36
33
18
8
8
5
12
Terracotta floor
5
4
3
4
4
3
3
150
60
44
18
8
8
3
9
Red oxide floor
4
4
3
3
4
3
3
136
48
44
18
6
8
3
9
Mosaic floor
4
4
4
3
4
4
3
143
48
44
24
6
8
4
9
After analyzing the alternatives of Terracotta floor are considered for development. It is considered as it performs all the functions required high pace of construction. It gains a total score of 150.
-
Plastering
For plastering use of plaster pump is recommended which gives good result by reducing the labour cost and also the time required to complete the work. This method includes investment for plaster pump, so break even analysis have been calculated to find out whether the investment is profit or loss. The results showed that how much area should the machine has to cover per year in order to avoid the loss which can be easily covered by small companies. As per the result this method is considered as the profit.
-
Putty and Painting works
For putty and painting works spraying method is recommended in order to reduce the labour cost and time required. For this spraying machine is used which have the benefit of using it for both putty works and painting works. For this also break even analysis is calculated to find out whether the investment is profit or loss. according to break even analysis this method the investment is a good choice for this techniques. Nowadays labours costs are increasing regularly, so implement of this method benefits more than cost and time.
-
-
RECOMMENDATIONS
The alternatives evaluated are applies on the project and savings and schedule improvement were done.
Sl.No
Proposed idea
(-)Reduction
/(+) Increase in cost (Rs)
%
improvement in schedule in specific work
Remarks
1
AAC blocks masonry for all external walls
+1,24,106
35
3 times lesser in weight, uniform dimension, thermal resistant, eco friendly
2
Ferrocement walls for partitions walls
– 1,13,796
30
Cost effective, speedy process
3
UPVC
windows
– 1,01,280
18
Facilitate better use, increased life and
reduce air conditionin g cost
4
Ferrocement concrete for
water tanks and sunshades
-59,355
50
Cost effective, speedy process, low materials used
5
Use of
Shahbad tiles in parking and drive way area
-76,122
No change
Cost effective and same aesthetics can be
achieved by good architectura l design
6
Terracotta tiles in terrace area
-83,286
No change
Cost effective, breaks monotony, Aestheticall y pleasing
7
Plastering pump for Plastering
– 5,61,347
40
Cost effective, saves labour problems
8
Spraying method for putty and paint works
– 3,22,783
30
Cost effective, saves labour problems
Total savings of the project
11,93,863
26
TABLE VIII. COST SAVINGS, SCHEDULE IMPROVEMENT AND REMARKS OF RECOMMENDED ALTERNATIVES
Table VIII shows the savings and improvement of schedule after the application of recommended alternatives in the collected projects and last column shows the advantages of using the recommended alternatives.
-
CONCLUSION
-
Value Engineering aims to deliver measurable value improvements through cost reduction and improve quality and enhance design features for the customer. This has been systematically applied in the architectural, structural and material components of the building. In this study alternatives used result not only in cost reduction but also improves schedule as well as the quality.
This proves the scope and application of Value Engineering in building construction is tremendous, from both the developers and buyers point of view. Until recent times, VE was applied only in large turnkey projects like waste water treatment plants. It is sincerely hoped that this study opens new
dimensions in the construction industry for the purpose of providing the best facility ultimately to the end user.
REFERENCES
-
Fallon., and Carlos, Value Analysis to Increase Productivity, John Wiley & Sons Inc, New York, 1991
-
E.Heller, Value management and cost reduction, Addition willey publishing company, Philippines, 1971,
-
Gokhram,P.R, Value Engineering, National Productivity Council, New Delhi, 1998.
-
Kelly,J and Male.S, Value Management in Design and Construction,
E&F.N.Spon, London, 1993.
-
Krishnan.P. and Saxena.KR, Value Engineering in Project Management, Oxford IBH Publications, Oxford, 1994.
-
Greve, Jhon,W, Frank W Wilson, Value Engineering in Manufacturing,
Prentice Hall Inc, New Jersey. 1987.
-
Norton R Brain, William,C, Mc Elligot, Value Management Construction, McMillan Press Ltd, London, 1995.
-
Ahuja., Hira, N., and Michael A Walsh, Successful Methods in Cost Engineering, A Wiley Interscience Publication, New York, 2000