Economic Feasibility and Efficient Project Scheduling of Fly-Over in Visakhapatnam (India)

DOI : 10.17577/IJERTV2IS3050

Download Full-Text PDF Cite this Publication

Text Only Version

Economic Feasibility and Efficient Project Scheduling of Fly-Over in Visakhapatnam (India)

Economic Feasibility and Efficient Project Scheduling of Fly-Over in Visakhapatnam (India)

A. V. Arjun1, Dr. L. Venkat2 and V. M. Naidu3

1M.Tech Scholar, 2Associate Professor and 3Assistant Professor Department of Civil Engineering, GVP College of Engineering (A) Visakhapatnam-530 041. India

Abstract

Construction of flyover in major cities due to heavy traffic is very essential in the present day scenario in order to reduce fuel consumption, accidents and travel time. It is also important to schedule the construction duration efficiently. In the present paper an economic feasibility of a flyover in Visakhapatnam (India) between Maddilapalem and Satyam junction is carried out. Based upon the benefits acquired and construction cost of the flyover, feasibility study has been done. Then, the flyover construction scheduling is carried out through different stages of construction. The construction period and cost of construction is worked out for two different stages of construction. A database prepared for construction manager to decide between economy and duration of the project.

Key words: Flyover construction scheduling; Economic feasibility; cost-benefit analysis Corresponding mail id: venkata.arjun@gmail.com

INTRODUCTION

In the present day, the transportation system is an important component of the infrastructure, which is essential in the development of any country. Construction management is a highly specialized task to achieve project with a minimum of elapsed time, capital investment without delay.

This involves three phases: Project planning, Project scheduling and Project controlling. The first two phases are accomplished before the actual project starts. This third phase is operative during the execution of the project. The aim is to recognize the difficulties during execution and to apply the measures to deal with those difficulties.

Project planning is the most important phase of construction management, which involves tasks, must be performed in the estimations of costs, durations for various jobs, direction and uniformity of the work. Project scheduling depends upon available resources and man power, and equipments. Project controlling is organizing, decision making and the skill to solve problems occurred during construction time. This is the normal or casual mechanism to determine deviations in planning.

ESTABLISHING THE STUDY METHODOLOGY

The realization of highway projects involves large capital. The features being permanent need a thorough analysis for technical and economical feasibility. Scarcity of resources and computing demands from various sectors are dominating features for an economy like India. In order to allocate the available resources in the most beneficial manner, a systematic economic analysis is outmost importance. Over the years, a scientific methodology has been evolved to evaluate highway projects, keeping in view the changing economic parameters. The methodology is explained in the Fig1.

Fig1: flow chart for economic evaluation of the project.

DATA COLLECTION AND ANALYSIS

The traffic data is essential to know the magnitude of travelers who are going to use the fly-over once it is constructed [1]. The traffic data is also essential to determine both the technical and economic feasibility of the flyover. Maddilapallem junction and satyam junction, both are four road junctions where the proposed flyover will take off from NH-5 from satyam junction to maddilapalem junction by covering both the junctions (Fig 2). The details of the traffic data collection and preliminary analysis are presented in the subsequent articles. The flow of the traffic between these junctions is shown in the Fig 2 by passenger car units (PCU) per day.

Fig2: Traffic flow at Maddilapallem Junction and Satyam junction.

Traffic volume count surveys

The traffic volume count surveys at 15-minutes intervals were conducted to estimate the traffic patterns at both the junctions. Traffic volume survey at MADDILAPALLEM JUNCTION towards NAD was conducted on 21st Dec 2012 from morning 8.00 Hrs to 11.00 Hrs and at evening 17.00 Hrs to 21.00 Hrs and the survey was conducted at SATHYAM JUNCTION towards PM Pallem on 24th Dec 2012 from morning 8.00 Hrs to 11.00 Hrs and at evening

    1. Hrs to 21.00 Hrs.

      Speed and Delay Survey

      A survey is conducted by travelling between these two junctions by different modes of transport. The travel time and delays in travel time are shown in the table 1

      Table.1 travelling time results between junctions

      Junction

      Time

      Duration

      Trucks

      Car

      Bike

      Morning Period

      Maddilapallem Junction – Satyam Junction

      Journey Time

      00:05:42

      00:05:32

      00:04:18

      Stopped delay

      00:03:50

      00:03:34

      00:03:08

      Running Time

      00:01:52

      00:01:58

      00:01:10

      Satyam Junction – Maddilapallem Junction

      Journey Time

      00:05:54

      00:05:26

      00:05:47

      Stopped delay

      00:03:58

      00:03:42

      00:02:52

      Running Time

      00:01:56

      00:01:44

      00:02:55

      Evening Period

      Maddilapallem Junction – Satyam Junction

      Journey Time

      00:05:19

      00:05:18

      00:03:50

      Stopped delay

      00:03:27

      00:03:53

      00:02:48

      Running Time

      00:01:52

      00:01:25

      00:01:02

      Satyam Junction – Maddilapallem Junction

      Journey Time

      00:05:41

      00:04:41

      00:05:22

      Stopped delay

      00:03:46

      00:03:19

      00:03:39

      Running Time

      00:01:55

      00:01:22

      00:01:43

      ANALYSIS OF TRAFFIC DATA

      The time to time variation of the traffic at both the maddilapalem junction and at satyam junctions are represented in Fig3 and 4 represents the traffic flow at Maddilapallem junction morning and evening periods respectively and Fig 5 and 6 represents the traffic flow at Satyam junction morning and evening periods respectively.

      1800

      1600

      1400

      1200

      1000

      800

      600

      400

      200

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      1800

      1600

      1400

      1200

      1000

      800

      600

      400

      200

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      Time (Hrs)

      Time (Hrs)

      Traffic Count

      Traffic Count

      Traffic Count

      Traffic Count

      Fig 3: Morning Period Traffic at Maddilapallem junction towards NAD

      600

      500

      400

      300

      200

      100

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      600

      500

      400

      300

      200

      100

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      Time (Hrs)

      Time (Hrs)

      Fig 4: Evening period Traffic at Maddilapallem junction towards NAD

      1800

      1600

      1400

      1200

      1000

      800

      600

      400

      200

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      1800

      1600

      1400

      1200

      1000

      800

      600

      400

      200

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      Time (Hrs)

      Time (Hrs)

      Traffic Count

      Traffic Count

      Traffic Count

      Traffic Count

      Fig 5: Morning period Traffic at Satyam junction towards PM Pallem

      900

      800

      700

      600

      500

      400

      300

      200

      100

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      900

      800

      700

      600

      500

      400

      300

      200

      100

      0

      Total Traffic (In Veh)

      NMT

      three axle trucks two axle trucks three wheelers LCV's

      two wheelers mini buses buses

      car

      Time (Hrs)

      Time (Hrs)

      Fig 6: Evening period Traffic at Satyam junction towards PM Pallem

      Traffic composition

      The traffic composition at Maddilapalem junction in the morning and evening times are shown in Fig 7 and Fig 8.

      Three axle trucks

      NMT

      Three axle trucks

      NMT

      1%

      Two axle trucks 2%

      Three wheelers 31%

      car 21%

      2%

      buses 3%

      mini buses 1%

      Two

      1%

      Two axle trucks 6%

      Three wheelers 26%

      2% car

      20%

      buses 8%

      mini buses 2%

      LCV's 1%

      wheelers 39%

      LCV's 2%

      Two

      wheelers 33%

      Fig 7: Morning Period Traffic Fig 8: Evening period traffic composition at compositions at Maddilapallem junction maddilapalem junction

      three

      axle trucks 1.87%

      three

      axle trucks 1.87%

      NMT

      2.18%

      NMT

      2.18%

      two axle

      trucks 2.21%

      three wheelers 27.75%

      two axle

      trucks 2.21%

      three wheelers 27.75%

      car

      15.33%

      buses

      3.68%

      mini buses 2.37%

      car

      15.33%

      buses

      3.68%

      mini buses 2.37%

      three axle

      three axle

      two axle trucks 1.72%

      two axle trucks 1.72%

      trucks

      0.60%

      trucks

      0.60%

      NMT 0.53%

      NMT 0.53%

      car

      car

      16.39%

      16.39%

      three wheelers 26.62%

      three wheelers 26.62%

      buses 2.30%

      buses 2.30%

      The traffic composition at Satyam junction in the morning and evening times are shown in the Fig 9 and Fig 10

      LCV's

      2.50%

      LCV's

      2.50%

      two

      wheelers 42.11%

      two

      wheelers 42.11%

      LCV's 1.40%

      LCV's 1.40%

      mini buses 0.53%

      mini buses 0.53%

      two wheelers 49.92%

      two wheelers 49.92%

      Fig 9: Morning Period Traffic Fig 10: Evening period traffic composition at compositions at Satyam junction Satyam junction

      Peak hour traffic

      The peak hour traffic is calculated at both junctions in morning and evening periods and tabulated in table 2.

      Table 2 Peak Traffic Volume

      Junction Name

      Direction

      Peak Hour

      Peak Traffic (PCU)

      Morning Period

      Maddilapallem Junction

      Towards NAD

      10.00 11.00

      2443

      Satyam Junction

      Towards PM Pallem

      10.00 11.00

      2366

      Evening Period

      Maddilapallem Junction

      Towards NAD

      17.15 18.15

      1078

      Satyam Junction

      Towards PM Pallem

      17.45 18.45

      1092

      Projected Traffic on flyover

      The traffic which is going to travel between these two junctions may not use the proposed flyover. So, the traffic which is using the flyover can be calculated from the origin and destination survey [1]. The Fig 11 shows the total projected traffic on the flyover is 15058 PCU per day at Maddilapallem junction and 11475 PCU per day at Satyam junction.

      Fig11: Projected Traffic on flyover per day.

      PROPOSED ALIGNMENT

      The alignment details are essential in the geometric design of the flyover taking into consideration the design speeds and maximum horizontal curvature allowed to provide proper sight distance [5].

      Alignment Details: The alignment details for the proposed flyover were assumed and the design aspect of the flyover is

      • The design speed is 100Kmph.

      • Gradient maintained 1:20 to 1:25

      • Length of Bridge portion = 720 m

      • Total length of flyover = 1250m

      • Carriage way width of flyover = 4 lanes (2*7.5m)

      • Length of Retaining wall approach towards NAD = 250m

      • Length of Retaining wall approach towards PM Pallem = 250m

      • Total Number of piers = 23_(P1,P2,Pn)

      • Total Number of spans= 24 spans

      • Span length = 30m

        ECONOMIC ANALYSIS

        The feasibility study of the fly-over must be done taking into consideration the various alternatives proposed [2]. The cost of construction is taken as per the present industry standards. The details of accident costs, travel time savings, vehicle idling costs and vehicle operating cost are estimated and tabulated in table 3.

        Table 3: Total Annual Benefits (Costs in Rs. lakhs)

        Year

        Accident costs

        Travel Time Savings

        Vehicle Idling Cost

        Vehicle Operating Cost

        TOTAL BENEFITS

        2012

        15.19

        1001.82

        119.32

        308.15

        1444.46

        2017

        48.14

        1457.13

        174.39

        562.59

        2242.24

        2022

        152.64

        2133.3

        256.58

        801.75

        3344.25

        2027

        484

        3136.27

        379.62

        1150.87

        5150.74

        2032

        1534.68

        4627.77

        564.42

        1662.68

        8389.53

        2037

        4866.26

        6852.98

        842.65

        2415.64

        14977.51

        Accident costs: The past accident data is collected and by using IRC SP-30 [4], the cost of accidents are calculated. The forecasting of the accidents are calculated according to the past 2years growth rate of accidents.

        The annual costs of travel time Savings, vehicle idling costs and vehicle operating costs are calculated from the delay studies of table1 [4]. Based upon the growth rate of traffic [3], the individual costs are calculated forecasting up to 2037.

        ECONOMIC ANALYSIS OF THE FLYOVER

        For the purpose of economic analysis, the discount rate whic are adopted for the present feasibility study are 8%, 9%, 10%, 11% and 12%.

        Generally the economic life of highway projects is expected to be 20-30 years. In this particular case, the design life is taken as 25years.

        Routine Cost: The routine maintenance cost is taken equal to 1% of construction cost.

        Periodic Cost: The periodic maintenance cost is taken equal to 5% of the construction cost and it is considered for every five years.

        Economic analysis of the flyover is done by the following

        • The first column indicates the different years within the design life of the fly-over.

        • The second column gives the construction cost of the flyover for a length of 1.25km in the year 2012 is 5142Lakhs (approx).

        • The third column gives the routine maintenance costs with respect to each year considering the wholesale price index.

        • The fourth column indicates the periodic maintenance cost once in 5 years taking into considering the wholesale price index.

        • The fifth column gives the construction cost computed with respect to each year taking into consideration the discount rate.

        • The sixth column gives the total cost including the maintenance costs with respect to each year.

        • The seventh column indicates the benefits obtained from table 3.

        • The eighth column gives the benefits accrued with respect to each year.

        • The ninth column gives the difference between columns eight and six that provides the benefits and costs for up to that year.

        • The tenth column gives the difference of benefits and costs for each year. This is used to find the Internal Rate of Return IRR

        • The eleventh column gives the break-even year

          International Journal of Engineering Research & Technology (IJERT)

          Vol. 2 Issue 3IS, SMNa:rc2p7-82-0011381

          Table 4 Economic Analysis of the Flyover Discount rate 10% (Cost in Rs.lakhs)

          Year (1)

          Construc tion cost (2)

          Maintenance Cost

          const amount (5)

          Total Cost up to that year

          (6)

          Total benefits (7)

          benefits up to that year (8)

          benefits – cost(1) (9)

          benefits – cost(2) (10)

          benefits/ cost Ratio (11)

          Routine (3)

          Periodic (4)

          2012

          5142

          5142

          5142

          1444.46

          1444.46

          3697.54

          3697.54

          0.28

          2013

          54.15

          5656.2

          5710.36

          1652.85

          3097.31

          2613.05

          1598.69

          0.54

          2014

          57.036

          6221.82

          6278.86

          1782.57

          4879.88

          1398.98

          1725.53

          0.77

          2015

          60.070

          6844.01

          6904.09

          1922.72

          6802.6

          -101.49

          1862.64

          0.98

          2016

          63.266

          7528.42

          7591.69

          2076.28

          8878.88

          1287.19

          2013.01

          1.16

          2017

          333.16

          8281.27

          8614.44

          2242.24

          11121.12

          2506.68

          2242.24

          1.29

          2018

          70.177

          9109.4

          9179.58

          2424.21

          13545.33

          4365.75

          2354.03

          1.47

          2019

          73.910

          10020.3

          10094.26

          2623.88

          16169.21

          6074.95

          2549.99

          1.60

          2020

          77.842

          11022.3

          11100.23

          2841.48

          19010.69

          7910.46

          2763.63

          1.71

          2021

          81.984

          12124.6

          12206.61

          3080.37

          22091.06

          9884.45

          2998.38

          1.80

          2022

          431.72

          13337.0

          13768.82

          3344.25

          25435.31

          11666.4

          3344.25

          1.84

          2023

          90.939

          14670.8

          14761.74

          3633.92

          29069.23

          14307.4

          3542.98

          1.96

          2024

          95.777

          16137.8

          16233.66

          3954.72

          33023.95

          16790.2

          3858.94

          2.03

          2025

          100.87

          17751.6

          17852.55

          4310.65

          37334.6

          19482.0

          4209.77

          2.09

          2026

          106.23

          19526.8

          19633.08

          4707.57

          42042.17

          22409.0

          4601.33

          2.14

          2027

          559.45

          21479.5

          22038.99

          5150.74

          47192.91

          25153.9

          4591.28

          2.14

          2028

          117.84

          23627.4

          23745.34

          5647.43

          52840.34

          29095

          5529.52

          2.22

          2029

          124.11

          25990.2

          26114.36

          6207.21

          59047.55

          32933.1

          6083.09

          2.26

          2030

          130.71

          28589.2

          28719.99

          6841.51

          65889.06

          37169.0

          6710.79

          2.29

          2031

          137.66

          31448.2

          31585.87

          7564.09

          73453.15

          41867.2

          7426.42

          2.30

          2032

          724.96

          34593.0

          35317.99

          8389.53

          81842.68

          46524.6

          7664.56

          2.31

          2033

          152.70

          38052.3

          38205.04

          9339.7

          91182.38

          52977.3

          9186.99

          2.38

          2034

          160.83

          41857.5

          42018.41

          10439.6

          101622.0

          59603.6

          10278.8

          2.41

          2035

          169.38

          46043.3

          46212.72

          11717.9

          113339.9

          67127.2

          11548.5

          2.45

          2036

          178.39

          50647.7

          50826.07

          13216.4

          126556.4

          75730.3

          13038.0

          2.48

          2037

          939.44

          55712.4

          56651.89

          14977.5

          141533.9

          84882.0

          14038.0

          2.49

          www.ijert.org 9

          SENSITIVITY ANALYSIS

          Future values are difficult to predict and there is some uncertainty about the project results. Hence it is necessary to assess the possible changes on the different project variables that are quantified. In the present study, sensitivity analysis has been carried out taking into consideration the following possibilities:

          • When the costs increased by 15%.

          • When the benefits decreased by 15%.

          • When both the above cases occur simultaneously.

          The sensitivity analysis is carried for the three cases and the Internal Rate of Return (IRR) is carried out and the results are shown in table 5

          Table 5 Sensitivity Analysis

          8%

          9%

          10%

          11%

          12%

          IRR (%)

          Actual cost and benefits

          benefit/cost

          3.91

          3.12

          2.49

          1.99

          1.60

          14.805%

          break-even year

          2015

          2015

          2016

          2016

          2016

          Increase in cost by 15%

          benefit/cost

          3.40

          2.71

          2.17

          1.73

          1.39

          13.955%

          break-even year

          2016

          2016

          2016

          2017

          2017

          Decrease in benefits by 15%

          benefit/cost

          3.32

          2.65

          2.12

          1.69

          1.36

          13.832%

          break-even year

          2016

          2016

          2017

          2017

          2017

          Both Increase in cost and Decrease in Benefits by 15%

          benefit/cost

          2.89

          2.31

          1.84

          1.47

          0.82

          12.955%

          break-even year

          2017

          2018

          2018

          2018

          —–

          CONSTRUCTION SCHEDULING

          Planning, scheduling and cost estimation are important activities in the project delivery process, linking the design of a facility to its construction. It takes many years to become an experienced scheduler and estimator and even experienced professionals. It is often challenge to develop realistic and cost estimates a challenge. Among other things, a realistic construction schedule must be in equilibrium with the estimate [7]. The estimate must reflect the cost of the resources required carrying out the proposed schedule, and it must be developed at the level of detail appropriate for its purpose [6].

          Hence the flyover is feasible at this zone. The flyover having a length of 1.25km has been planned with 23piers and 24 spans with span length of 30m each and each span is having 12 spine segments and 24 cantilever segments, two approaches of each length 250m on either side [8].

          So by using the MS Projects software [9] the secluding of the project is carried out. The major activities of the flyover are

        • Preliminaries

        • Mobilization

        • Design and drawings

        • Foundations & sub-structure

        • Yard development & precasting

        • Erection of segments – preliminary works

        • Segment erection

        • Miscellaneous works

        • Handing over of viaduct

          Considering, the critical path of the project depends upon the number of beds available for casting of spine segments and cantilever segments and the crash barriers. In this paper work there are two alternatives of construction has been planned i.e., single stage of construction and the second one is two stage construction. In single stage of construction all the pilling, pile caps, piers, and erection of segments is done one after the other from abutments A to another abutment B. Therefore the total project duration for single stage construction is 576 days and by two stage constructions the project duration is 557days, where the flyover is divided in to two parts of construction activities are carried in parallel.

          The study has been conducted to vary the number of spine segment beds and cantilever segment beds in the precasting yard. The effect of variation of these beds on the duration of the project is carried out and listed in the following table 6

          Table 6 Effect of casting beds on project duration

          Type of construction

          No. of Spine segments beds

          No. of Cantilever segment beds

          Duration (days)

          Single Stage

          4

          4

          576

          4

          3

          576

          3

          3

          617

          3

          4

          617

          Two Stage

          4

          4

          536

          4

          3

          557

          3

          3

          640

          3

          4

          640

          SUMMARY AND CONCLUSION

          In the present paper, economic feasibility of a flyover between Maddilapalem and Satyam junction is carried out. Then the construction scheduling is done for the proposed flyover using MSP. The duration verses economy for the construction is worked. The conclusions from the present study are as follows:

        • From traffic survey study it is concluded that the peak hour traffic at Maddilapallem junction towards NAD at 10.00 Hrs 11.00 Hrs is 2443 PCU per day and at 17.15 Hrs 18.15 Hrs is 1078 PCU per day and the peak hour traffic at Satyam junction towards PM Pallem at 10.00 Hrs 11.00 Hrs is 2366 PCU per day and at 17.15 Hrs 18.15 Hrs is 1092 PCU per day.

        • From the benefit cost study it is concluded that the construction of a 4-lane fly-over is thoroughly feasible between Maddilapalem and Satyam junction.

        • Based on sensitivity analysis, considering 25 years of life span of the flyover, the construction of a 4-lane is feasible only if the discount rate is equal to or less than 11%.

        • From the sensitivity analysis, the IRR for the actual benefits and cost is 14.8%. When the cost is increased by 15% then the IRR is 13.9%. When the benefits are decreased by 15% then the IRR is 13.8%. When the cost is increased and benefits are decreased simultaneously then the IRR is 12.9%.

        • The duration of single stage of construction of a flyover is 576 days where as two stage construction the project duration is 557 days keeping duration of each activity is same both types of construction. Hence single stage of construction is preferred.

        • By decrease or increase in number of casting beds for spine and cantilever segments, the duration of the construction is varied. So, the optimum number of casting beds for spine segments are four and for cantilever segments are three, then the duration for that construction is 576 days i.e., 82Weeks.

REFERENCES:

  1. Kadiyali. L.R. Traffic Engineering and Transportation Planning, Khanna Publishers, Delhi-1983.

  2. Winfary, Economic Analysis for Highways International Textbook Company, 1969.

  3. Whole Sale Price Index, Office of Economic Advisor, Ministry of Finance-India, from internet www.eaindustry.com.

  4. IRC SP-30, Manual on Economic Evaluation of Highway Projects in India, Indian Road Congress, 1993.

  5. IRC64-1990, Guidelines for Capacity of Urban Roads in Plain Areas.

  6. Seetharaman.S, Construction Engineering & Management, Nai Sarak, New Delhi, 2006.

  7. Project management for engineering and construction : Garold D.Oberlender 1993

  8. Sengupta.B, and Guha.H, Construction Management and Planning, Tata Mc.Graw Hill publishing company Ltd., New Delhi, 2004.

  9. Microsoft Office Enterprise Project Management (EPM) Solution 2007.

Leave a Reply