Enhancing the Performance Utilization of Locos and Minimizing the Demurrage of Rakes in A Steel Plant

DOI : 10.17577/IJERTV3IS061367

Download Full-Text PDF Cite this Publication

Text Only Version

Enhancing the Performance Utilization of Locos and Minimizing the Demurrage of Rakes in A Steel Plant

Mr. Shridhar. B. Sutar

Graduate Student (M .Tech in Industrial Engineering) Dept. of Industrial Engineering and Management

M.S. Ramaiah Institute of Technology Bangalore, India.

Dr. Chethan Kumar. C. S

Associate Professor, Dept. of Industrial Engineering and Management

M.S. Ramaiah Institute of Technology Bangalore, India.

Abstract – This paper deals with enhancing the performance utilization of locos (Railway Engines) by uncovering the non- value adding activities in raw material unloading yard (RMUY) of an integrated steel plant. The capacity expansion of steel industry involves expansion of the production capacity at different stages of steel making like Raw material handling system, Treatment plants, Iron making, Steel making, Casting, & Rolling mills. At present Cold Rolling Mill-2 and Steel Making Shop-3 are going to be commissioned shortly. Hence with the expansion of the steel plant, the demand for raw materials will increase which will increase the number of inbound rakes arriving at RMUY. The increase in number of rakes arriving at RMUY causes congestion at the tracks causing bottlenecks for the unloading facilities and limits the rake movements within RMUY. The external railway agency providing the rail service, charges for demurrage (delay in return of rakes beyond 8hr of free unloading time). Thus such bottlenecks not only adversely affect the unloading capabilities of the yard, but also increase the demurrage costs.

Using Work Measurement Technique, 24hr Time study has been conducted in raw material unloading yard to estimate the existing utilization of nine locos simultaneously three shifts per day. Process chart is drawn to identify the separate steps or events that occur during a series of actions carried out by loco in RMUY and activity chart is drawn to identify operation time, travel time & idle time of locos in continuous three shifts. Daily Loco requirement plan is developed for different production levels and rake arrival plan to enhance the performance utilization of Locos.By using Value Stream Mapping Technique the non-value adding activities in RMUY are reduced which will reduce the lead time of unloading the rake and delay in return of rakes, hence demurrage cost is minimized. Based on utilization and various scenarios of different production levels, it is found out that the existing number of locos can handle the increased arrival of raw materials due to plant expansion.

By reducing the lead time of rake unloading process, congestion in tracks is reduced & by modifying the unloading facilities, the operational costs in the form of demurrage charges will be saved, which will lead to a savings of Rs 100 million over

a period of 14 months. The proposed system is currently under implementation by steel plant.

Key Words: RMUY, Locos, Work Measurement Technique, Time study, Process chart, Activity chart, Utilization, Bottleneck, Optimization, Value Stream Mapping, Lead Time, Demurrage cost.

  1. INTRODUCTION

    A major Indian steel manufacturer is planning for plant capacity expansion. The capacity expansion involves expansion of the production capacity at different stages of steel making which is shown in Figure 1[1].

    Figure 1: The typical steel making process of a Steel Plant

    At the RMUY, major raw materials such as iron ore, Non Coking coal, Coking coal, coke, Limestone, Dolomite, Quartzite and Manganese Ore are received from various sources through goods trains called rakes, provided by an external railway agency. The rakes are sent to mechanized unloading stations (wagon tipplers & track hoppers), where material is unloaded. In this plant, the in-plant movement of

    rakes is through captive locomotives that run on diesel. The external railway locomotives, deliver the rakes to the yard and leave. Some rakes are divided into smaller wagon sets before being sent to unloading stations. After unloading, the wagon sets are joined together. This process of splitting and joining of rakes is called rake handling. All the rakes after unloading and handling, if needed, are then handed over back to the railway agency. The external railway agency providing the rail service, charges for demurrage (delays in return of rakes beyond a certain time limit). Hence delay in return of rakes must be avoided to reduce the demurrage cost.

    Logistics is the management of the flow of resources between the point of origin and the point of destination in order to meet some requirements of customers or corporations.

    Operating responsibility of Logistics is repositioning of raw materials, work in process & finished goods where required at lowest cost possible & quality service. It is difficult to accomplish any Receipt/Dispatch processes, repositioning of products & manufacturing without a Professional Logistics Support.

    This plant is producing 10 Million Tonne of Steel per annum, aiming to achieve 16 MTPA in the coming years. To cater the raw material requirement and also to dispatch the finished products, it is having rail infrastructure at plant premises. To produce this capacity of steel, it has to bring in nearly 40 MTPA of various types of raw materials and also move nearly 10 MTPA of finished products. Both inbound and outbound traffic is handled by having own Locomotives and Railway Yards. Logistic department internally has an infrastructure of 40 Locomotives, 160 km of Track

    The steel plant owned Locomotives are used for internal shunting operation at plant premises. Raw materials booked from various ports / sidings are received in railway wagons and are handed over to thesteel plant.

    South Yard being the main receipt yard with 26 lines handles the rakes offered. The logistics section at south yard instructs the shunting operation of rakes to offer for unloading at Wagon Tipplers, Track Hopper or Manual unloading. The feeding lines to tipplers are limited, the rakes parked at different lines are to be shunted and placed in the minimum possible time.

    At present 40 Locos are existing in the plant for various requirements like

    1. Input Raw material handling at South Yard, (9+1=10)

    2. Hot metal handling at 4MT and 7,10MT Iron making to SMS-1&2, (19+1=20)

    3. Finished goods handling at North Yard and HSM-1, HSM-2, BRM and WRM. (9+1=10)

    A process flow diagram for the raw material unloading process is provided in Figure 2.

    Figure 2: Raw Material Unloading Process

    The adequacy of the current facilities for handling the increased arrival of raw materials needed to be investigated and in case of inadequacy, appropriate changes needed to be proposed, so that the system is capable of unloading the annual requirement of raw materials with minimum network congestion.

  2. OBJECTIVES

    • To investigate the adequacy of the current facilities for handling the increased arrival of raw materials.

    • To estimate the existing utilization of nine locos deployed for raw material handling at south yard.

    • To enhance the utilization of locos, which lead to optimization of required number of locos.

    • To develop loco requirement plan.

    • To reduce the lead time of rake unloading process which in turn reduce the delay in return of rakes to minimize the demurrage cost.

  3. TOOLS AND TECHNIQUES USED

    • Work Measurement.

      o Time and motion study.

    • Process Chart.

    • Activity Chart.

    • Value Stream Mapping (VSM).

  4. LITERATURE REVIEW

    A case study research was conducted by N. Yusoff at a local car seat polyurethane (p/u) injection manufacturing company by extensively exploiting the work study methods and techniques during the on-site studies. Two fundamental approaches in work study namely method study and work measurement offer a systematic and organized steps in the research studies. The work measurement has been widely used as a method for measuring actual working time via its several techniques i.e time study. This paper discusses on the application of the work measurement technique in

    establishing a benchmark time for producing the car seat p/u injection line of the case study subject[2].

    A research was carried out by K. Al-Saleh at the Motor Vehicle Periodic Inspection (MVPI) station to improve and enhance the bottleneck inspection point by using different applications to reduce the inspection time. The main problem of this research was an inspection point (No. 1) which consumed more time in comparison with the other inspection points. Accordingly, this inspection point increases the flow time in the inspection lanes. This research investigated and searched for possible solutions and alternatives aimed at achieving the objective using some tools from motion and time study and ARENA software to simulate and predict the changes expected to occur in the inspection lanes[3].

    Lean approach has been applied more than frequent in many manufacturing management floors over these few decades. Started in the automotive industry, sequential improvement initiatives were implemented to enhance the manufacturing practice changes. The team described a case where Lean Production (LP) principles were adapted for the process sector of an automotive part manufacturing plant. Value Stream Mapping (VSM) is one of the key lean tools used to identify the opportunities for various lean techniques. The contrast of the before and after the LP initiatives in determine managers potential benefits such as reduced production lead-time and lower work-in-process inventory. As VSM involves in all of the process steps, both value added and non-value added, are analysed and using VSM as a visual tool to help see the hidden waste and sources of waste. A Current State Map is drawn to document how things actually operated on the production floor. Then, a Future State Map is developed to design a lean process flow through the elimination of the root causes of waste and through process improvements.

    The use of the VSM improved the approach in LP initiatives as it reveals obvious and hidden waste that affected the productivity of D45T production. There is a significant amount of the time products spent on the production system usually was waiting and non-value added. Quantitative evidence showed that many of the Lean tools have an expected impact related to the reduction of this waiting time [4].

    scenarios of different production levels like present day average, medium, and maximum capacity material receipt are considered to maximize the utilization of existing locos and unloading equipments, resulting in optimization of required number of locos. Daily Loco requirement plan is developed for different production levels and rake arrival plan to enhance the performance utilization of Locos.

    1. By using Value Stream Mapping Technique the non- value adding activities in RMUY are reduced which will reduce the lead time of unloading the rake and delay in return of rakes, hence demurrage cost is minimized.

      1. DATA COLLECTION

        Process flow of steel plant

        Figure 3: Process flow of steel plant

        V. METHODOLOGY

        To meet the main aim and the specific objectives of the study a quantitative research methodology study along with a comprehensive literature review were employed.

        1. Using Work Measurement Technique, 24hr Time study has been conducted in raw material unloading yard to estimate the existing utilization of nine locos simultaneously three shifts per day.

        2. Process chart is drawn to identify the separate steps or events that occur during a series of actions carried out by loco in RMUY and activity chart is drawn to identify operation time, travel time & idle time of locos in continuous three shifts. In addition to the calculation of exiting utilization of locos, various

        South yard loco time and motion study Data

        Table 1: Time study data of loco 4 . Table 2:Time study data of loco 17 .

        South Yard Loco Time Study

        Date: 15 & 16-2-2014 Loco No: 4 Shift: C,A,B

        Activity

        Loco Movements

        Time in min

        From

        To

        Elapsed

        Shift relieving

        Shift relieving

        22:00

        22:40

        00:40

        5 rear , 9 rear Empty rake formation

        LL from R8 to 5 rear

        22:40

        22:50

        00:10

        Placing 5 rear empty for cleaning

        22:50

        23:40

        00:50

        5 rear , 9 rear empty rake shunting

        & backing to R19

        23:40

        00:00

        00:20

        LL from R19 to R14

        00:00

        00:10

        00:10

        Idle

        WFT in R14

        00:10

        02:45

        02:35

        Placement of load to T1

        LL from R14 to R7

        02:45

        03:00

        00:15

        Attached to load rake WF brake release

        03:00

        03:30

        00:30

        Placing load rake to T1

        03:30

        03:40

        00:10

        Placement of load to CY

        LL from R7 to R8

        03:40

        03:45

        00:05

        Banker attachment to CY load

        03:45

        03:50

        00:05

        Weighment of CY load

        03:50

        04:05

        00:15

        Pushing load rake from R8 to CY

        04:05

        05:45

        01:40

        Reached SY 4rear LL from 4rear to R1

        05:45

        06:00

        00:15

        Shift relieving

        Shift relieving

        06:00

        06:35

        00:35

        Idle

        WFT in R1

        06:35

        06:52

        00:17

        Bulge wagon removing

        LL from R1 to 10 rear

        06:52

        07:00

        00:08

        Attached to 2 bulge wagons and

        pulling towards DL

        07:00

        07:10

        00:10

        Shunting bulge wagons to empty rake

        in R20

        07:10

        07:25

        00:15

        LL from R20 to R14

        07:25

        07:35

        00:10

        Idle

        WFT in R14

        07:35

        08:35

        01:00

        10 rear & 13 rear Empty rake formation

        LL from R14 to 10 rear

        08:35

        08:45

        00:10

        Shunting 10 rear & 13 rear empty rake

        & pulling to DL

        08:45

        09:10

        00:25

        LL from DL to 11 rear

        09:10

        09:15

        00:05/p>

        Idle

        WFT in 11 rear

        09:15

        09:30

        00:15

        5 rear Empty rake formation

        Pulling 5 rear empty from DL to R19

        09:30

        09:50

        00:20

        LL from R19 to R2

        09:50

        09:55

        00:05

        WF signal at top pt

        09:55

        10:15

        00:20

        LL from top pt to R2

        10:15

        10:25

        00:10

        Idle

        WFT in R2

        10:25

        11:10

        00:45

        Miscellaneous

        LL from R2 to top pt & again to R2

        11:10

        11:20

        00:10

        Idle

        WFT in R2

        11:20

        14:00

        02:40

        Shift relieving

        Shift relieving

        14:00

        14:30

        00:30

        Miscellaneous

        LL from R1 to DL

        14:30

        14:40

        00:10

        LL from DL to R2

        14:40

        14:50

        00:10

        Shifting brake wagon from R2 to R3

        14:50

        15:10

        00:20

        Idle

        WFT in R3

        15:10

        17:30

        02:20

        10 rear Empty rake formation

        LL from R3 to 10 rear

        17:30

        17:40

        00:10

        Placing 10 rear empty rake for cleaning

        17:40

        18:30

        00:50

        Pulling 10 rear empty to DL

        18:30

        18:40

        00:10

        12 rear Empty rake formation

        LL from DL to 12 rear

        18:40

        18:50

        00:10

        LL from 12 rear to DL

        18:50

        19:00

        00:10

        Pulling 12 rear empty rake from DL to R18

        19:00

        19:20

        00:20

        4 rear Empty rake formation

        LL from R18 to DL via R20

        19:20

        19:50

        00:30

        Pulling 4 rear empty from DL to R20

        19:50

        20:10

        00:20

        LL from R20 to R13

        20:10

        20:20

        00:10

        Idle

        WFT in R13

        20:20

        20:30

        00:10

        Bulge wagon removing

        Shifting 17 bulge wagons from DL to R7

        20:30

        21:00

        00:30

        Placing bulge wagons to T1

        21:00

        21:10

        00:10

        5 rear Empty rake formation

        LL from R7 to R9

        21:10

        21:20

        00:10

        LL from R9 to DL

        21:20

        21:25

        00:05

        Pulling 5 rear empty from DL to R9

        21:25

        21:40

        00:15

        LL from R9 to R8

        21:40

        21:45

        00:05

        Idle

        WFT in R8

        21:45

        22:00

        00:15

        South Yard Loco Time Study

        Date: 15 & 16-2-2014 Loco No: 17 Shift: C,A,B

        Activity

        Loco Movements

        Time in min

        From

        To

        Elapsed

        Shift relieving

        Shift relieving

        22:00

        22:40

        00:40

        13 rear Empty rake

        formation

        LL from R14 to 13 rear

        22:40

        22:50

        00:10

        Pulling 13 rear empty to DL

        22:50

        23:05

        00:15

        12 rear Empty rake formation

        LL from DL to 12 rear

        23:05

        23:10

        00:05

        WFLC in 12 rear

        23:10

        23:15

        00:05

        Pulling 12 rear empty to DL

        23:15

        23:30

        00:15

        5 rear , 9 rear Empty rake formation

        LL from DL to 9 rear

        23:30

        23:40

        00:10

        5 rear ,9 rear empty rake shunting

        & backing to R19

        23:40

        00:00

        00:20

        LL from R19 to R14

        00:00

        00:10

        00:10

        Idle

        WFT in R14

        00:10

        03:40

        03:30

        Miscellaneous

        LL from R14 to R23

        03:40

        03:50

        00:10

        Pulling 29 load wagons from R23 to DL

        03:50

        04:20

        00:30

        9 rear Empty rake formation

        LL from DL to 9 rear

        04:20

        04:30

        00:10

        Attached to 9 rear empty WFLC

        04:30

        05:10

        00:40

        Pulling 9 rear empty to DL

        05:10

        05:15

        00:05

        12 rear Empty rake formation

        LL from DL to 12 rear

        05:15

        05:25

        00:10

        Pulling 12 rear empty to DL

        05:25

        05:40

        00:15

        Pushing 12 rear empty from DL to R26

        05:40

        06:00

        00:20

        Shift relieving

        Shift relieving

        06:00

        06:35

        00:35

        Idle

        WFT in R26

        06:35

        07:15

        00:40

        Bulge wagon

        removing

        LL from R26 to R23

        07:15

        07:25

        00:10

        T5 bulge wagon shunting

        07:25

        07:35

        00:10

        13 rear Empty rake formation

        LL from R23 to 13 rear

        07:35

        07:45

        00:10

        Pulling 13 rear empty rake up to poling

        07:45

        08:00

        00:15

        LL from 13 rear to R1

        08:00

        08:10

        00:10

        Idle

        WFT in R1

        08:10

        09:20

        01:10

        Maintenance

        LL from SY to NY for Diesel

        09:20

        12:15

        02:55

        Idle

        LL reached SY, WFT in R1

        12:15

        13:40

        01:25

        Placement of load to T2

        LL from R1 to R4

        13:40

        13:45

        00:05

        Placing load rake to T2

        13:45

        13:50

        00:05

        LL from R4 to R1

        13:50

        14:00

        00:10

        Shift relieving

        Shift relieving

        14:00

        14:30

        00:30

        Placement of load to

        T5

        LL from R1 to R24

        14:30

        14:45

        00:15

        Placing load rake to T5

        14:45

        14:55

        00:10

        Placement of load to

        T4

        LL from R24 to R12

        14:55

        15:15

        00:20

        Placing load rake to T4

        15:15

        15:30

        00:15

        Placement of load to T1

        LL from R12 to R7

        15:30

        15:45

        00:15

        Placing load rake to T1

        15:45

        15:55

        00:10

        LL from R7 to R8

        15:55

        16:05

        00:10

        Idle

        WFT in R8

        16:05

        16:30

        00:25

        EY Empty rake formation

        LL from R8 to R10

        16:30

        16:40

        00:10

        Removing 2 empty box from R10 rake

        16:40

        16:50

        00:10

        Shifting 2 empty box from R10 to R8

        16:50

        17:15

        00:25

        WF another 2 box attachment

        17:15

        17:30

        00:15

        Pulling 4 empty box to DL

        17:30

        17:45

        00:15

        Another one box attachment in DL

        17:45

        18:00

        00:15

        Pulling 5 empty wagons from DL to EY

        18:00

        21:20

        03:20

        Idle

        Reached SY, WFT in 11 rear

        21:20

        21:30

        00:10

        9 rear Empty rake formation

        Pulling 9 rear empty from DL to R14

        21:30

        21:50

        00:20

        LL from R14 to R3

        21:50

        22:00

        00:10

      2. FINDINGS AND DISCUSSION

        Process Chart

        The process chart is a device for recording a process in a compact manner, as a means of understanding it better and improving it. The chart represents graphically the separate steps or events that occur during a series of actions [5]. Process chart is drawn to identify the separate steps or events that occur during a series of actions carried out by loco in the raw material unloading yard. Process chart is drawn to the data collected through time and motion study.

        Activity Chart

        Although the process chart give the picture of the different steps in the process, it is often desirable to have a breakdown of the process or of a series of operations plotted against a time scale. Such a picture is called an activity chart [3]. Activity chart is drawn to identify operation time, travel time & idle time of locos in continuous three shifts.

        Table 3: 1st Day Analysis.

        Sumof Elapsed Time

        Loco Numbers

        Description

        4

        17

        18

        22

        24

        26

        30

        38

        41

        Grand Total

        Planned shift relieving

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        0:45:00

        6:45:00

        Shift relieving loss =SR- PSR

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        1:00:00

        9:00:00

        Idle Time =Idle +Shift relieving loss +Loco Shutdown

        11:17:00

        8:20:00

        10:47:00

        5:30:00

        10:55:00

        10:17:00

        12:55:00

        3:28:00

        11:17:00

        84:46:00

        Working Time =AT- IT

        12:43:00

        15:40:00

        13:13:00

        18:30:00

        13:05:00

        13:43:00

        11:05:00

        20:32:00

        12:43:00

        131:14:00

        Available Time

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        24:00:00

        216:00:00

        Utilization =WT/AT

        53%

        65%

        55%

        77%

        55%

        57%

        46%

        86%

        53%

        61%

        • In south yard of this steel plant, 9 Locos are deployed for raw material handling.

        • 216 Loco hours has been considered for study.

        • Utilization of 9 Locos is 61%. Out of 39% loss time, 89% is due to idle (waiting for task) & remaining 11% is due to shift relieving loss.

          Table 4: 2nd Day Analysis.

          Sumof Elapsed Time

          Loco Numbers

          Description

          4

          17

          18

          22

          24

          26

          30

          38

          41

          Grand Total

          Planned shift relieving

          00:45

          00:45

          00:45

          00:45

          00:45

          00:45

          00:45

          00:45

          00:45

          06:45

          Shift relievingloss =SR- PSR

          00:25

          00:25

          00:25

          00:25

          00:25

          00:25

          00:25

          00:25

          00:25

          03:45

          Idle Time =Idle +Shift relievingloss +Loco Shutdown

          9:40:00

          5:40:00

          8:40:00

          10:20:00

          8:00:00

          6:40:00

          4:15:00

          5:20:00

          4:53:00

          56:23:00

          Working Time =AT- IT

          14:20:00

          18:20:00

          15:20:00

          13:40:00

          16:00:00

          17:20:00

          19:45:00

          18:40:00

          19:07:00

          159:37:00

          Available Time

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          216:00:00

          Utilization =WT/AT

          60%

          76%

          64%

          57%

          67%

          72%

          82%

          78%

          80%

          74%

        • Utilization of 9 Locos is 74%. Out of 26% loss time, 80% is due to idle (waiting for task), 13% is due to loco shutdown & remaining 7% is due to shift relieving loss.

          Table 5: 3rd Day Analysis.

          SumofElapsedTime

          LocoNumbers

          Description

          4

          17

          18

          22

          24

          26

          30

          38

          41

          GrandTotal

          Plannedshiftrelieving

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          00:45:00

          6:45:00

          Shiftrelievingloss=SR-PSR

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          00:25:00

          3:45:00

          Idle Time=Idle+Shiftrelievingloss+LocoShutdown

          9:30:00

          10:20:00

          9:30:00

          10:10:00

          7:25:00

          11:15:00

          8:15:00

          7:30:00

          5:15:00

          79:10:00

          WorkingTime=AT-IT

          14:30:00

          13:40:00

          14:30:00

          13:50:00

          16:35:00

          12:45:00

          15:45:00

          16:30:00

          18:45:00

          136:50:00

          Available Time

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          24:00:00

          216:00:00

          Utilization=WT/AT

          60%

          57%

          60%

          58%

          69%

          53%

          66%

          69%

          78%

          63%

        • Utilization of 9 Locos is 63%. Out of 37% loss time, 95% is due to idle (waiting for task), & remaining 5% is due to shift relieving loss.

          After estimating the existing utilization of nine locos it is found that the utilization of locos is low. Hence to enhance the utilization and optimize the required number of locos different hot metal production levels in terms of tons per day (TPD), tons per annum (TPA), and metric tons per annum (MTPA) are considered. For hot metal production calculation norms for one ton of hot metal is considered. Optimum number of locos required for different production levels and rake arrivals is proposed. Table 6 shows the proposed system for handling increased arrival of raw material.

          Table 6: Proposed system for various production levels.

          Present System

          Proposed System

          1st day

          2nd day

          3rd day

          Average

          Available No. of Locos

          9

          9

          9

          9

          9

          9

          9

          9

          9

          9

          Loco Utilization

          61%

          74%

          63%

          66%

          71.98%

          75.41%

          78.83%

          82.26%

          85.69%

          88.27%

          Numberof rakes

          handled

          19

          24

          22

          22

          24

          25

          26

          27

          28

          29

          Norms for one tonne

          of Hot Metal

          Materials

          Quantity

          Coal

          34463.66

          21955.56

          33014.13

          29811.12

          29250.59

          30643.48

          32036.36

          33429.25

          34822.14

          35870.98

          1.39289

          IOF

          15066.00

          11174.49

          21950.55

          16063.68

          29723.89

          31139.31

          32554.73

          33970.15

          35385.58

          36451.39

          1.41542

          C-ore

          0.00

          15514.69

          7751.50

          7755.40

          7204.77

          7547.86

          7890.94

          8234.03

          8577.11

          8835.46

          0.34308

          ROM

          7469.95

          15664.43

          7885.21

          10339.86

          6299.99

          6599.99

          6899.99

          7199.99

          7499.99

          7725.89

          0.30000

          L/S

          2750.58

          10101.87

          10903.58

          7918.68

          9089.83

          9522.68

          9955.53

          10388.38

          10821.23

          11147.16

          0.43285

          Dolomite

          3663.10

          7296.99

          0.00

          3653.36

          4256.85

          4459.55

          4662.26

          4864.97

          5067.67

          5220.31

          0.20271

          Quartz

          4052.25

          7817.10

          0.00

          3956.45

          875.04

          916.71

          958.37

          1000.04

          1041.71

          1073.09

          0.04167

          Total

          67465.54

          89525.13

          81504.97

          79498.55

          86700.96

          90829.58

          94958.19

          99086.81

          103215.43

          106324.28

          Iron Material

          22535.95

          42353.61

          37587.26

          34158.94

          43228.65

          45287.16

          47345.66

          49404.17

          51462.68

          53012.73

          Hot metal/TPD

          10945.09

          20569.99

          18255.10

          16590.06

          21000.00

          22000.00

          23000.00

          24000.00

          25000.00

          25753.00

          Hot metal/TPA

          3994959.57

          7508046.45

          6663113.11

          6055373.05

          7665000.00

          8030000.00

          8395000.00

          8760000.00

          9125000.00

          9399845.00

          Hot metal/MTPA

          3.99

          7.51

          6.66

          6.06

          7.67

          8.03

          8.40

          8.76

          9.13

          9.40

          Required No. of Locos

          @existing locos utilization

          5

          7

          6

          6

          6

          7

          7

          7

          8

          8

          Table 7: Loco requirement plan

          Loco Requirement Plan

          Daily production plan in terms of hot metal tons per day

          Range of rakes per day

          Number of Locos required

          10945.09

          15 to 18

          5

          21000

          19 to 22

          6

          23000

          23 to 27

          7

          25753

          28 to 31

          8

          >25753

          31 to 34

          9

        • Daily Loco requirement plan is developed for different production levels and rake arrival plan to enhance the performance utilization of Locos.

        • Based on number of rakes arrival plan on particular day, number of Locos deployment can be planned.

        • Remaining Locos can be sent to other yard or these locos can be shut down so that unnecessary diesel consumption will be saved.

          Value stream mapping

          Current state value stream map

          From the available data current state value stream map is drawn using Microsoft Visio software to find out lead time of rake unloading process. Figure 4 shows the current state value stream map.

          CURRENT STATE VALUE STREAM MAP

          SAP

        • Average utilization of 9 Locos 1st day, 2nd day, and 3rd day of study is 61%, 74%, 63% respectively.

        • Average existing utilization of 9 Locos at south yard is 66%.

        • Average number of rakes handled per day is 22 & average quantity of raw material received per day is 79498.55 tons.

        • For various production levels, utilization of Locos is estimated.

        • To achieve the target of 9.4 MTPA, 29 rakes has to be received per day.

    30 min

    Loco

    Two persons has to be allotted for brake release

    Arival of loaded rake

    60 min

    30 min

    Double Wagon Tippler

    has to be installed

    Prozess

    Tippler Unloading process

    300 min

    Dust absorber has to be installed

    Prozess

    Cleaning

    90 min

    Prozess

    Empty Rake Formation

    105 min

    • At maximum production level the utilization of Locos is 88.27%.

      Traveling Brake Release

      Placement Time

      D = 100mt

      Unloading Time Cleaning Time

      Lead Time = 615 min

      Figure 4: Current state value stream map.

    • Inferences

    • From figure 4: Current state value stream map.

      • The total lead time for unloading one rake is 615 min.

      • 615 min includes, traveling time of 30min, brake release time 60min, placement time 30min, unloading time 300min, cleaning 90min, and empty rake formation time of 105min.

      • From current state value stream map three improvement activities are identified.

    Future state value stream map

    After study and analysis of current state value stream map future state valuestream map is designed. Figure 5 shows future state value stream map.

    FUTURE STATE VALUE STREAM MAP

    SAP

    Loco

    Table 8: Rake wise DC analysis

    Lead Time = 320 min

    20 min

    Arival of loaded rake

    30 min

    30 min

    Prozess

    Double Wagon Tippler Unloading process

    150 min

    Prozess

    Cleaning

    30 min

    Prozess

    Obse rvatio n Day

    Total Rakes Studi ed

    Name of the Unloading Facility

    DC

    Rak e

    DC

    Hrs

    Amoun t in Rs

    No.of Wago n/ Rake

    1st Day

    19

    C/Y

    1

    3

    26100

    58

    TH 01

    1

    1

    7800

    52

    T3&T1&T

    6

    1

    4

    35400

    59

    Total

    3

    8

    69300

    2nd Day

    24

    T5

    1

    3

    26550

    59

    T4

    1

    3

    26550

    59

    T5

    1

    5

    44250

    59

    T3&T6

    1

    2

    17100

    57

    T4

    1

    1

    8850

    59

    T3

    1

    3

    26550

    59

    T6

    1

    1

    8850

    59

    T2

    1

    4

    35400

    59

    T1&T4

    1

    1

    8850

    59

    T2

    1

    2

    17700

    59

    T1&T4

    1

    2

    17700

    59

    C/Y

    1

    3

    26550

    59

    C/Y

    1

    9

    79650

    59

    T2

    1

    1

    8850

    59

    T5

    1

    1

    8850

    59

    T2

    1

    2

    17700

    59

    Total

    16

    43

    379950

    3rd Day

    22

    T5

    1

    1

    8700

    58

    TH-01

    1

    1

    7800

    52

    T5&T3

    1

    3

    26550

    59

    T5

    1

    1

    8850

    59

    C/Y

    1

    1

    8850

    59

    TH-01

    1

    2

    17700

    59

    T6

    1

    5

    44250

    59

    T3

    1

    2

    17100

    57

    Total

    8

    16

    139800

    Total

    65

    27

    67

    589050

    Empty Rake Formation

    60 min

    Traveling Brake Release

    Placement Time

    D = 100mt

    Unloading Time Cleaning Time

    Figure 5: Future state value stream map.

    • Inferences

    • From figure 5: Future state value stream map.

      • The total lead time for unloading one rake can be reduced from 615min to 320 min.

      • 320 min includes, traveling time of 20min, brake release time 30min, placement time 30min, unloading time 150min, cleaning 30min, and empty rake formation time of 60min.

    Cost Benefit Analysis

    For demurrage cost (DC) analysis total number of rakes handled during study period, Unloading facility, demurrage charged rakes, demurrage hours, number of wagons per rake, demurrage amount in rupee are considered. Table 8 gives Rake wise DC analysis.

    • Demurrage cost charged by Indian Railway is Rs 150/wagon/Hr.

    • Total number of rakes handled during 3day study is

      65. Out of which for 27 rakes demurrage cost is incurred.

    • Total demurrage cost incurred during study period is Rs 5,89,050/-

    • Average demurrage cost incurred per rake is Rs 26,030.35/-

      • Average demurrage hours per rake is 2.96hr.That means 2.96hr extra time is taking for unloading, than the scheduled free unloading time of 8hr.

        Track Hopper

        Table 9: Track hopper DC hours analysis

        Type of

        Unloading Facility

        Name of the Unloading Facility

        DC Hrs

        TH

        TH-01

        2

        TH

        TH 01

        1

        TH

        TH-01

        1

        Average DC Hrs

        1.33

      • Demurrage cost incurred per rake due to 1:20 DC hr is Rs 11800/-

      • In case of 1rake per day cost of 3 man power for one shift is Rs 1200/-

      • We can save Rs 10600/- per day. Rs 38.69 lakhs per annum.

      • If we increase the number of BOBSN rakes received per day from 1 to 6

      • We can save Rs 8200/- per day & Rs 179.58 lakhs per annum.

        Single Wagon Tipplers

        In south yard out of 6 WT 1,2,3&4 are single wagon tipplers, 5 & 6 are double wagon tipplers.

        Table 10: Wagon tippler DC hours analysis

        Type of Unloading

        Facility

        Unloading Facility

        No

        DC Hrs

        SWT

        T3

        2

        SWT

        T2

        2

        SWT

        T2

        1

        SWT

        T2

        2

        SWT

        T4

        3

        SWT

        T2

        4

        SWT

        T3

        3

        SWT

        T4

        1

        Average DC Hrs

        2.25

      • Demurrage cost incurred per rake due to 2:15 DC hr is Rs 19,912.5/-

      • Tippler modifying cost from SWT to DWT is considered as 200 lakhs per tippler. For 4 tipplers total of 800 lakhs has to be invested.

      • By modifying the system we can unload the rake within the free unloading time & we can save

        Rs 19,912.5/-per rake.

      • Considering average of 10 rakes per day we can save Rs 1,99,125/-, for a month Rs 59,73,750/- , Rs

        7,16,85,000/- per annum and for 14 months 836 lakhs.

    • Hence back payment of invested amount can be achieved within 14 months at the rate of

      Rs 59,73,750/- per month.

      1. RECOMMENDATIONS

    • Daily Loco requirement plan is developed for different production levels and rake arrival plan to enhance the performance utilization of Locos.

    • Based on number of rakes arrival plan on particular day, number of Locos deployment can be planned.

    • Remaining Locos can be sent to other yard or these locos can be shut down so that unnecessary diesel consumption will be saved.

    • Based on utilization and various scenarios of different production levels it is found out that the existing number of locos can handle the increased arrival of raw materials due to plant expansion.

    • Shift relieving losses must be minimized by providing scheduled transportation facility for loco drivers and points men.

    • Track hopper

      • Loco attachment time can be avoided by using Indian Railway Engine only for placement of rake and return.

      • Unloading time can be reduced by deploying additional 4 man power.

      • Material receiving through BOBSN rake must be increased from 1 to 6 rakes per day.

    • Single wagon tippler

    • From figure 5: Future state value stream map.

      • The total lead time for unloading one rake can be reduced from 615min to 320 min.

      • 320 min includes, traveling time of 20min, brake release time 30min, placement time 30min, unloading time 150min, cleaning 30min, and empty rake formation time of 60min.

      • Traveling time of loco can be reduced from 30min to 20 min by keeping it near top point.

      • Brake release time can be reduced from 60min to 30min by deploying two persons.

      • Unloading time can be reduced from 300min to 150min by installing double wagon tippler.

      • Cleaning time can be reduced from 90min to 30min by installing dust absorber at wagon tipplers.

      • Empty rake formation time can be reduced from 105min to 60min by keeping the loco rear side of the tippler.

      Instead of procuring new Loco, we have to go for expansion of unloading facility i.e. from single wagon tippler to double wagon tippler at wagon tippler 1,2,3,4, which reduces unloading time, which in turn reduces delay in return of rakes, hence we can save demurrage cost.

      1. CONCLUSIONS

        Abbreviations

        Loco Railway Engine SY South Yard

        NY North Yard CY Cement Yard

        Y Yard

        ANNEXURE

        This paper deals with enhancing the performance utilization of locos by uncovering the non-value adding activities in raw material unloading yard (RMUY) of an integrated steel plant. The capacity expansion of steel industry involves expansion of the production capacity at different stages of steel making like Raw material handling system, Treatment plants, Iron making, Steel making, Casting, & Rolling mills.

        Using Work Measurement Technique, 24hr Time study has been conducted in raw material unloading yard to estimate the existing utilization of nine locos simultaneously three shifts per day. Process chart is drawn to identify the separate steps or events that occur during a series of actions carried out by loco in RMUY and activity chart is drawn to identify operation time, travel time & idle time of locos in continuous three shifts. In addition to the calculation of exiting utilization of locos, various scenarios of different production levels like present day average, medium, and maximum capacity material receipt are considered to maximize the utilization of existing locos and unloading equipments, resulting in optimization of required number of locos. Daily Loco requirement plan is developed for different production levels and rake arrival plan to enhance the performance utilization of Locos. And is successfully implemented in south yard of steel plant.

        By using Value Stream Mapping Technique the non-value adding activities in RMUY are reduced which will reduce the lead time of unloading the rake and delay in return of rakes, hence demurrage cost is minimized. Based on utilization and various scenarios of different production levels, it is found out that the existing number of locos can handle the increased arrival of raw materials due to plant expansion.

        By reducing the lead time of rake unloading process, congestion in tracks is reduced & by modifying the unloading facilities, the operational costs in the form of demurrage charges will be saved, which will leads to a savings of Rs 100 million over a period of 14 months. The proposed system of modifying the unloading facility is currently under implementation by steel plant.

      2. SCOPE FOR FURTHER STUDY

    • Proper scheduling of incoming rakes.

    • Pre scheduling and assignment of locos to particular activities based on rake arrival schedule.

    • Study and implementation of signaling and transport system at rear side of the tipplers in raw material unloading yard.

SMS Steel Making Shop HSM Hot Strip Mill BRM Bar Rod Mill

R1toR26 Railway tracks WFT Waiting For Task

WFLC Waiting For Line Clearance LL Light Loco

TH Track Hopper WT Wagon Tippler

SWT Single Wagon Tippler DWT Double Wagon Tippler

T Tippler

MTPA Metric Tons Per Annum IOF Iron Ore Fines

ROM Raw Ore Magnetite

DRI Directly Reduced Iron ore L/S Lime Stone

RMMD Raw Material Managing Dept. RMHS Raw Material Handling System RMUY Raw Material Unloading Yard

VSM Value Stream Mapping DC Demurrage Cost

BOBSN Bogie hopper wagon side discharge

BOBRN Bogie open rapid discharge hopper wagon

(It is a type of wagon in which material is unloaded with the help of gravity.)

REFERENCES

  1. A. Mukherjee, A. Som, A. Adak, P. Raj and S. Kirtania, 'Augmenting an inbound raw material handling system of a steel plant by uncovering hidden logistics capacity', p. 116, 2012.

  2. N. Yusoff, A. Jaffar, N. Abbas and N. Saad, 'Work Measurement for Process Improvement in the Car Seat Polyurethane Injection Manufacturing Line', Procedia Engineering, vol 41, pp. 1800–1805, 2012.

  3. K. Al-Saleh, 'Productivity improvement of a motor vehicle inspection station using motion and time study techniques', Journal of King Saud University-Engineering Sciences, vol 23, iss 1, pp. 33–41, 2011.

  4. A. Rahani and M. al-Ashraf, 'Production flow analysis through Value Stream Mapping: A Lean manufacturing process case study', Procedia Engineering, vol 41, pp. 1727–1734, 2012.

  5. Barnes, R.M., 1980. Motion and Time Study; Design and Measurement of Work, seventh ed. John Wiley, New York, USA.

Leave a Reply