ABSTRACT

Scheduling refers to the process of allocating resources to tasks or assigning tasks to resources. This is done by generating a table with explicit start times for each task such that only one task at a time requests the resource. This is called static scheduling. Another solution for scheduling is to assign priorities to tasks and choose this task for execution with highest priority. Scheduling decision arises whenever the number of tasks to be executed is more than the available resources. Under fluid traffic flow Pro- active scheduling needs a re look with respect to traffic pattern analysis and scheduling accordingly[1]. Here we enumerate the whys and hows of disruptions in scheduling. Despite the plethora of studies and commercial solutions proposed, scheduling is still considered as one of the scientific areas where substantial improvements can be gained by the development and application of new research approaches[2]. Transferring this knowledge in to practice is really difficult because poor evaluation of benefits that can be got by adopting the methods in real time processes and understanding which solution can give better results according to a pre defined set of tasks.

Key words: VLSI, Traffic, Multiprocessor, Robustness.

  1. Introduction

    In the emerging VLSI Technology paradigm the consumer plays an important role. The tasks initiated by the consumer drive the systems traffic. In the historical evolution of scheduling technique first approach is based on a determinate view with implicit assumption that the proposed schedule will be carried as predicted before hand. In reality changeability and exceptions have demanded the stochastic based scheduling approach. The ever growing external and internal changing conditions which heavily affect the quality of of schedule are still under investigation in the research community. A scheduling scheme for tasks which guarantees the quality of services for video and audio is arrived at by means of dynamic priority scheduling .Feasibility of offline schedulers are affected by a large variety of dynamic events.

  2. RELATED WORKS

    It has been shown that the Liu and Layland results break down on multiprocessor systems [3]. Dhall and Liu [4] gave examples of task sets for which global RM scheduling can fail at very low processor utilizations, essentially leaving all but one processor idle nearly all of the time. Reasoning from such examples it may be perhaps easy to conjecture that Rate Monotonic is not a good or efficient scheduling policy for multiprocessor systems. However, at the moment these conclusions have not yet been formerly justified [5].

    The partitioning scheme has received greater attention than the global scheme because the scheduling problem can be reduced to the scheduling on a single processor, where at the moment a great variety of scheduling algorithms exist. It has been proved by Leung and Whitehead [6] that the partitioned and global approaches to static-priority scheduling on identical multiprocessors are incomparable in the sense that

    1. There are task sets that are feasible on m identical processors under the partitioned approach but for which no priority assignment exists which would call all jobs of all tasks to meet their deadlines under

      2,., n }

      be a set of tasks with Tl T2 Tn and let

      global scheduling in the same m processors, and

      n -1

      u Ci

      / Ti

      n -1

      21 / n 1 -1

    2. There are task sets that are feasible on m identical i 1

    processors under the global approach, which cannot be partitioned into m distinct subsets such that each

    (3.1)

    individual partition is feasible on a single static- priority uni processor.

    If the following condition is met,

    – n -1

    In this work, therefore only the partitioning scheme has been dealt with and not the global scheme.

    Cn / Tn 2 1

    u 1

    n -1

    (3.2)

  3. MODEL DESCRIPTION AND PROBLEM FORMULATION

    We consider a queuing architecture of a homogeneous system in which n processors are connected to m classes of tasks through a Scheduler. m and n are integers greater than or equal to 1.All processors functions in same speed and are identical. The system architectural model consists of a task scheduler queue, a scheduling strategy for multiple classes of tasks and n local task queues. The aim of the scheduler is to make good task allocation decision for each class of tasks and maintain an ideal performance in response time. A schedule queue stores incoming tasks and maintain an ideal performance in response time. The scheduler processes the tasks in FCFS manner and are dispatched to one of the designated processors. The processor maintains a local queue. We formulate the scheduling problem as a problem between number of incoming tasks and the number of processors required to execute this task when the scheduling policy is RMFF and RMBF.

    then the set of tasks will have a feasible schedule under the RM algorithm. When n , the minimum utilization of task Tn approaches to (2e-u 1).

  4. RATE MONOTONIC SCHEDULING ON MULTIPROCESSOR SYSTEMS

When can a set of tasks be scheduled on a multiprocessor system? The result has to be found for the minimal number of processors that is needed to find a feasible assignment of a task set to a multiprocessor system. Obviously, in the worst case, only one task can be assigned to each processor. Therefore, the following question should be taken into concern: When can a set of tasks be scheduled on less than one processor for each task? The answer to this question is given in Theorem 2. Roughly, Theorem 2 says, that if K processors are needed to schedule a set of K tasks, then the load on each processor cannot be much less than 1/2.

Theorem 2: If the total load of a set of K real-time tasks satisfies

A. SCHEDULABILITY CONDITION IP (INCREASING PERIOD):

U K

21/K 1

(4.1)

In condition IP [7], it is required that the periods of the tasks are ordered increasingly, thus the timing constraints of the task set must be known a priori. Condition IP, introduced by Dhall and Liu [7] is used in the implementation of the multiprocessor algorithms Rate Monotonic Next Fit and Rate Monotonic First Fit.

Theorem 1: (Condition IP) [6]: Let = { 1,

then the task set can be scheduled with the RM algorithm on less than K processors. The condition is tight.

RATE MONOTONIC ALGORITHMS UNDER PARTITIONING SCHEME

In the following sections, the heuristic static scheduling algorithms executed under RM on multiple processors are described. It is assumed that in the notation used the allocation of task Ti to processor Pj consists on increasing the utilization of the processor by, Uj = Uj +ui, where Uj denotes the utilization of processor Pj and ui denotes the utilization of task Ti.

A.RATE MONOTONIC FIRST FIT (RMFF):

In the allocation process, some algorithms verifies the current processor to see if a feasible schedule can be found for a new task (along with the previously allocated tasks). If there is no feasible schedule in that processor, it allocates the task on an idle processor, even though the task could be feasibly scheduled in another non-idle processor previously used. To overcome this waste of processor utlization, RMFF always checks the schedulability of the new task from the first processor to the current one on which the task can be scheduled.

The Rate Monotonic First Fit (RMFF) algorithm [7], illustrated in Figure 4.1, orders tasks increasingly according to their periods, before the allocation process. To allocate task Ti, it is required to select the processor with smallest index, such that task Ti along with previously allocated tasks, finds a feasible schedule using the schedulability condition IP.

In the algorithm, if task Ti satisfies condition IP (step 4 from the algorithm) then it is schedulable, so the task is allocated to processor Pm (step 7). km denotes

Output: j; number of processors required.

  1. Sort the tasks by increasing periods

  2. i:= 1; j:= 1; / * i = ith task, j = jth processor * /

  3. while (i n) do

4. q : = 1; ,

q

q

  1. while (ui > 2(1 + Uq/kq)-k – 1) do

  2. q : = q + 1; / * q denotes the processor index * /

  3. Uq : = Uq + ui ; kq := kq + 1

  4. if (q > j) then

9. j: = q;

10. i : = i + l;

  1. return (j);

  2. end

Fig. 4.1.Rate Monotonic First Fit (RMFF) Algorithm

B.RATE MONOTONIC BEST FIT (RMBF):

Algorithm RMBF[7], illustrated in Figure 4.2, allocates the task to the processor with smallest available utilization, on which it can be feasibly scheduled.RMBF orders tasks increasingly according to their periods, before the allocation process. In this algorithm, the allocation of task Ti to processor Pj (step 5 from the algorithm) requires finding the smallest j such that task Ti together with all the task previously allocated to processor Pj, can be feasibly scheduled according to the schedulability condition IP, and that the value of 2(1 + Uj / kj) -kj – 1 be as small as possible (step 4).

the number of tasks allocated to processor Pm, and Um

denotes the total utilization of the km tasks. If (i > n), its means that all tasks have already been allocated (step 3), then the algorithm finishes, otherwise, the index is increased (step 10), and the algorithm continues with steps 4 to 10. When the algorithms finishes, the total number of processors required for the feasible scheduling of the task set is given by variable j.

The performance of the RMFF algorithm is 2

RMFF (4 x 21/3) / (1 + 21/3 2.23 [6] and its computational complexity is O(n log n).

Input: Task set T ={Tl,T2,…,Tn}

and a set of processors {P1,…, Pm}.

Input: Task set = { l, 2,…, n} and a set of processors {P1,…,Pm}.

Output: j; number of processors required.

  1. Order tasks increasingly by their periods

  2. i:= 1; j:= 1; / * i = ith task, j = jth processor * /

  3. while (i n) do

  4. if (ui Condition IP) and

    j

    j

    (2(1 + Uj / kj )-k – 1) is the smallest possible

  5. Uj := Uj + ui ;

  6. else

  7. task i is allocated to an idle processor

19

8. i := i + 1; 17

Numbers of Processors

Numbers of Processors

15

15

13

13

9. return (j);

11

11

10.end

9

7

5

5

Fig. 4.2 Rate Monotonic Best Fit (RMBF) Algorithm

The processor with the smallest available utilization, on which the new task can be feasibly scheduled, will

3

1

5 10

Number of Tasks

15 20

be the one where the task will be allocated.

The performance of RMBF is RM BF 2 + (3 – 23/2) / a 2.33, where a = 2 (21-3 – 1) [7], and its computational complexity is O( n log n).

  1. EXPERIMENTAL RESULTS AND PERFORMANCE EVALUATION

    To obtain the average case performance of the algorithms one can analyze the scheme with probabilistic assumptions, or conduct simulation experiments to empirically study the average performance. Since a probabilistic analysis of our algorithms is beyond the scope of this study simulation is used to gain insight in to the average case behavior.

    The simulation experiments are presented with task sets ranging from 5 K 20 In each experiment the value of is varied = Max i=1,.k V; the maximal load factor of any task in the set. The task periods are assumed to be uniformly distributed with values 5 Ti 100. The execution times of the tasks are also taken from a uniform distribution with range 1 Ci

    Fig. 5.1 Performance of RMBF

    19

    17

    Number of Processors

    Number of Processors

    15

    13

    11

    9

    7

    5

    3

    1

    5 10 15 20

    Number of Taks

    Fig. 5.2 Performance of RMFF

    For = 0.5

    19

    17

    Number of Processors

    Number of Processors

    15

    13

    11

    9

    7

    5

    3

    1

    Ti The performance metric in all experiments is the number of processors required to assign a given task set. All the assignment schemes are executed on identical task sets.

    The outcome of the simulation experiments is shown for = 0.2 , 0.5 and 0.8. The graphs show that in all schemes the number of processors required for the respective schemes increases proportionally to the total load.

    For = 0.2

    5 10 15 20

    Number of Tasks

    Fig. 5.3 Performance of RMBF

    19

    17

    Number of Processors

    Number of Processors

    15

    13

    11

    9

    7

    5

    3

    1

    5 10 15 20

    Number of Tasks

    Fig. 5.4 Performance of RMFF

    For = 0.8

    19

    17

    Number of Processors

    Number of Processors

    15

    13

    11

    9

    7

    5

    3

    1

    5 10 15 20

    Number of Tasks

    Fig. 5.5 Performance of RMBF

    19

    17

    Number of Processors

    Number of Processors

    15

    13

    11

    9

    7

    5

    3

    1

    5 10 15 20

    Number of Tasks

    Fig. 5.6 Performance of RMFF

    1. J. W. S. Liu, Real-Time Systems, Prentice-Hall, 2000.

    2. C. L. Liu and W. Layland, Scheduling Algorithms for Multiprogramming in a Hard Real-Time Environment, Journal of ACM, vol. 20, number 1, pp.46- 61, January 1973.

    3. T. P. Baker, Multiprocessor EDF and Deadline Monotonic Schedulability Analysis, IEEE Real-Time Systems Symposium, Dec. 2003.

    4. J. Y. T. Leung and J. Whitehead. On the Complexity of Fixed-Priority Sceduling of Periodic, Real-Time tasks. Performance Evaluation, 2:237-250,1982.

    5. S. K. Dhall and C. L. Liu. On a real-time scheduling problem. Operations Research, 26(1):127-140, January/February 1978.

  2. SUMMARY AND FUTURE WORK

An increasing number of applications with traffic constraints are running on homogeneous processors. In both scheduling schemes, it is shown that for particular number of tasks, if the suggested number of processors are not available ,scheduling fails. The traffic/task pattern which causes this is called disruptive traffic. Present schedulers focus on bin- packing algorithms and not capable of handling disruptive traffic. Schedulers to work with disruptive conditions are to be formulated. Also scheduling algorithms must look into handling different types of traffic cases from Poisson to general arrivals.

References:

  1. Kai Nagel, Traffic Networks ETH Zurich,CH-8092 Zurich ,Switzerland 2002

  2. Sergio Cavalientand Sergio Terzi, Proposal of a performance Measurement system for the evaluation of scheduling solutions Int.J. Manufacturing Technology and Management, Vol 8,Nos1/2/3,2006,Department of Industrial Engineering,University of Bergmo,Dalmine,BG,Italy.

Leave a Reply