Hot Topic and Evolution Trend of Chinese International Contracting Project Risk Research Knowledge Graph Analysis Based on Citespace

DOI : 10.17577/IJERTV12IS020142

Download Full-Text PDF Cite this Publication

Text Only Version

Hot Topic and Evolution Trend of Chinese International Contracting Project Risk Research Knowledge Graph Analysis Based on Citespace

Xiaofei Pu

.Xi 'an University of Architecture and Technology Xian.shaaxi. China

Yuan He Xijing University Xian.shaaxi. China

Abstract: With the high-quality development of the "One Belt and One Road" initiative, Chinese enterprises actively "go out", the international contracting project business is growing steadily, and its risk research results are constantly emerging. In order to summarize the research achievements of this field in nearly 20 years, this paper uses CiteSpace software to organize and analyze 2009 documents in this field in the period from 2000 to 2021 in China Knowledge Network (CNKI) journal database, and clearly shows the development course, hot themes and evolution trend of the field. First, this field will become the focus of scholars' attention with the growth of turnover; second, the core scholar group has been formed, but the cooperation between universities, enterprises and scholars is not close enough; third, the three hot topics are risk involved object, risk theory research and risk practice application; and fourth, the development process and evolution trend are divided into three stages: starting period, rising period and breakthrough period.

Keywords: Belt and Road , international contracting project, risk researches

  1. INTRODUCTION

    In 2021, the total number of 11,932 newly signed contracts for international contracting project business in China is 11,932, the amount of newly signed contracts is 260.25 billion US dollars, the completed turnover is 172.9 billion US dollars, the total turnover has been 2.00 trillion US dollars, and the amount of newly signed contracts is 3.01 trillion US dollars. To drive China's products, technologies and services to "go global", promote the transformation and upgrading of the domestic economy, and achieve win-win cooperation and development with relevant countries (regions), international contracting projects have become the main way for Chinese enterprises to jointly build "Belt and Road" and promote the construction of international infrastructure connectivity and production capacity cooperation. However, international contracting projects are more complex than domestic projects, and in addition to traditional risks, the political, legal, fiscal, exchange rate and other risks of the host country. In 1996, Lei Shengqiang published International Engineering Risk Management and Insurance, which marked the beginning of

    Chinese scholars in this field has become more and more mature and meticulous.

  2. 1. DATA SOURCE AND RESEARCH METHOD

    1. Data source

      Using the China National Knowledge Network (CNKI) database as the retrieval platform, the retrieval method is set as: "theme =" ('+' overseas project '+' international project '+' overseas contracting project ') risk, retrieval condition = "accurate", literature category = "academic journal". The time range is set from 2000-2021, and the retrieval time is November 27,2022. A total of 2041 documents are obtained. Non-research documents such as "news report" and "meeting notice" were artificially removed during the data cleaning process, and 2,009 documents were finally obtained as data sources for bibliometric statistics and visual analysis of the literature.1

    2. Study Methods

    CiteSpace is a visual analysis software focusing on the analysis of the potential knowledge contained in scientific literature2 . In this paper, on the basis of documentation, through CiteSpace software generated keywords clustering knowledge map, keywords time line clustering analysis map, keywords emergent analysis map, and the author post analysis map, in 2000-2021 China international contracting engineering literature hot topics and evolution trend of statistical analysis and visual presentation, to show the knowledge of domestic and international contracted engineering risk research panorama.

  3. OVERVIEW OF INTERNATIONAL CONTRACTING PROJECT RISK RESEARCH

    1. Annual publication volume trend

      The publication time and the annual publication volume distribution of the literature can directly reflect the research heat and development speed in the research field (see Table 1). Table 1 shows the published scale of the completed turnover and international engineering contracting risk research literature of Chinese enterprises from 2001 to 2021. As can be seen from Figure 1, from 2000 to 2021, the number of

      the systematic research of international contracting project

      risk in China. After decades of development, the research of

      published articles on international project contracting risk research has been increasing year by year, especially after 2006. This shows that the risk research of international contracting projects has attracted more and more attention from more and more scholars, and the research heat is increasing. According to the annual post volume trend chart, The risk study of international contracting projects can be roughly divided into three stages: the first stage is 2000-2006, At this stage, the number of articles is small and the growth is slow, The average annual number of publications is 25, Among them, 22 articles were published in 2001; The second phase was from 2006- -2016, In this stage, the growth rate of

      documents was significantly accelerated compared with the previous stage, The average annual number of articles was 115.8, In 2016, There were 162 articles posted, It is nearly 5 times of the average annual amount of documents issued in the previous stage; The third phase is for 2017-2021, At this stage, the number of articles appeared in twists and turns, The average post volume was 143.8, 109 articles in 2019, 162 articles in 2020. In particular, in the third phase of 2019, the global COVID-19 epidemic affected the development of international contracting project business, and the number of documents plummeted.

      Table 1 The Volume of Chinese Enterprises and the published literature from 2001 to 2021

      year

      Turnover (US

      $100 million) A

      post volume (article) B

      year

      Turnover (US

      $100 million) A

      post volume (article) B

      2001

      89

      22

      2012

      1166

      112

      2002

      112

      15

      2013

      1371

      130

      2003

      138

      31

      2014

      1424

      147

      2004

      175

      20

      2015

      1541

      136

      2005

      218

      42

      2016

      1594

      162

      2006

      300

      37

      2017

      1686

      152

      2007

      406

      45

      2018

      1690

      151

      2008

      566

      68

      2019

      1729

      109

      2009

      777

      85

      2020

      1559

      162

      2010

      92

      85

      2021

      1549

      127

      2011

      1034

      115

      At the same time, the study found that the period associated with Chinese enterprise international contracting project turnover, using SPASS software in table 1 A (turnover) and B (post) for variable correlation analysis, calculate the

      correlation coefficient of 0.991 (table 2), shows that the strong correlation, namely the more the turnover, the more the number of post.

      Table 2 Analysis results of the correlation between publication volume and turnover

      turnover

      Number of posts

      turnover

      1(0.000***)

      0.991(0.000***)

      Number of posts

      0.991(0.000***)

      1(0.000***)

      Note: * * *, * * and * represent the significance levels of 1%, 5% and 10%, respectively

    2. Study power distribution

      1. Document quantity and partnership analysis

        The core author is a mainstay of research in various

        professional fields, and research in leading fields. According to the lower limit of the core authors of Price (Price) theory3 the minimum number of core authors in this field is 3. Statistics show that 45 authors published 3 or more papers during this period and published a total of 205 papers, accounting for 10.2% of the total number of papers. This indicates that the core authors in this research field has been formed, but the overall number of core authors is low. Specifically, in terms of the number of articles published, the number of articles published by the core authors is not

        high.The visual analysis of the author cooperative relationship map was generated by the author through CiteSpace software. There were 635 nodes and 152 connections, and the network density was 0.0008, indicating that although there are a lot of researchers in this field, there is a loose cooperative relationship.

      2. Analysis of the number of articles issued by research institutions and the cooperative relations

    Visual analysis of the partnership is conducted through CiteSpace software. There are 534 nodes and 67 lines in the map. The analysis results show that the network density is 0.0005, indicating that the partnership between the research institutions is not close enough.

    3

  4. KEYWORD CO-OCCURRENCE MAP ANALYSIS IN INTERNATIONAL CONTRACTING PROJECT

    RISK RESEARCH

    1. Keyword word frequency analysis

      Visual analysis of the keywords through CiteSpace software, the selection standard is "TopN (50)", "Pathfinder", "Pruningslicednetworks", "and" Pruningthemergednetwork " to generate the keyword word frequency map and keyword clustering map of international contracting project risk research, and analyze the hot topics in this field. The node type selects "Keywords" to plot the co-occurrence map of the keywords.

      The atlas contains 225 nodes and 604 connecting lines. After the centrality calculation, the hot spot keywords of the first 30 times of occurrence frequency are listed. As can be seen in Table Table 3, International Engineering (653, 0.33),

      Risk management (245, 0.47), risk (194, 0.21) Contractors (172, 0.34), At more than 100 times, And has a relatively high centrality degree, In the first echelon of hot research keywords in this field; The occurrence frequency of the second tier hot spot keywords is 40-100 times, Including project management (71, 0.07), exchange rate risk (60, 0.29)

      Risk identification (60, 0.19), Risk analysis (54, 0.10), Risk

      control (48, 0.07), financial risk (47, 0.02), Risk prevention

      (46, 0.09) Subcontractor (41, 0.56); The third echelon appears between 10-40 times, Such as tender offer, Belt and Road, overseas projects, risk evaluation, claims, financial management engineering projects, foreign exchange risk, bidding and strategy, etc. The above main hot spot keywords first appeared in the time, in 2001 and 2009 more. In addition, some keywords do not appear more frequently but are more central, which are hot words in this field, such as risk factors (13,0.51), project bidding (7,0.28), Chinese enterprises

      (10,0.19), cost control (8,0.17), hydropower station (2,0.15) and letter of credit (4,0.11). Therefore, it can be shown that the risk subject of international contracting projects not only involves contractors but also subcontractors, and the risk categories are mainly exchange rate risk and financial risk, including risk identification, risk analysis, risk prevention and control, risk control, risk evaluation, claim and so on. In addition, scholars through project management, financial management, contract management and other keywords research, comprehensively respond to the risk changes of international contract projects.

      Table 3 Key topics of domestic and international contracting projects from 2000 to 2021

      order numbe

      r

      keyword

      word frequenc

      y

      centrad

      The first

      year

      order number

      keyword

      word frequency

      centrad

      The first year

      1

      International engineering

      653

      0.33

      2001

      16

      contract management

      40

      0.15

      2009

      2

      risk management

      245

      0.47

      2001

      17

      contracting of project

      33

      0.26

      2003

      3

      risk

      194

      0.21

      2001

      18

      tender offer

      32

      0.11

      2009

      4

      contractor

      172

      0.34

      2000

      19

      Belt and Road

      32

      0.02

      2015

      5

      project management

      71

      0.07

      2004

      20

      risk management and control

      31

      0.16

      2013

      6

      exchange rate risk

      60

      0.29

      2005

      21

      Overseas projects

      29

      0.07

      2009

      7

      risk identification

      60

      0.19

      2006

      22

      countermeasures

      29

      0.00

      2009

      8

      risk analysis

      54

      0.10

      2003

      23

      risk evaluation

      26

      0.04

      2007

      9

      manage

      50

      0.18

      2001

      24

      claim indemnity

      24

      0.11

      2001

      10

      Risk Management

      48

      0.07

      2010

      25

      financial management

      22

      0.11

      2013

      11

      financial risk

      47

      0.02

      2013

      26

      project item

      22

      0.03

      2008

      12

      Risk prevention

      46

      0.09

      2008

      27

      exchange risk

      2

      0.06

      2007

      13

      be on guard

      44

      0.10

      2001

      28

      tender

      20

      0.02

      2005

      14

      the way to deal with a situation

      44

      0.08

      2008

      29

      risk prevention and control

      18

      0.08

      2009

      15

      sub-contractor

      41

      0.56

      2001

      30

      policy

      17

      0.36

      2007

    2. Keyword cluster analysis

    Through CiteSpace software, 11 main clusters were obtained, and the Q value was 0.8076, indicating the network community structure and the clustering effect is good; the S value was 0.9399, greater than 0.9, indicating that the clustering results are convincing. The clustering results with remarkable structure and good results can help us to analyze and grasp the overall characteristics and development trend of international contracting project risk research.(Q value interval is [0,1), Q> 0.3 means

    that the community structure is significant; the average profile value of S> 0.7 indicates that the clustering is highly efficient and convincing.4

  5. HOT TOPIC OF INTERNATIONAL CONTRACTING PROJECT RISK RESEARCH

    The keywords in the literature were clustered to form a keyword cluster map and analyze the chart (Table 4). It can be seen that there are 11 key keywords in the field of international contracting project risk. In terms of cluster scale, the scale of clu ster # 0 international project is the largest (22), followed by cluster # 1 exchange rate risk (20) and # 2 risk factor (19); From the perspective of average profile value, each cluster size is greater than 0.945, among which the cluster # 4 contractor and # 8 risk is the largest (1.00), and the cluster profile managed by # 5 is the smallest (0.846).

    Table 4 2000-2021

    clustering

    Cluster

    size

    Cluster

    profile

    The main keywords

    # 0 International engineering

    22

    0.932

    International engineering; risk control; risk evaluation; overseas engineering; coping strategy

    # 1 Exchange rate risk

    20

    0.973

    Exchange rate risk; risk response; contract risk; construction enterprise; exchange rate changes

    # 2 Risk factors

    19

    0.912

    Risk factors; risk identification; project contracting; risk assessment; risk avoidance

    # 3 Subcontractor

    18

    0.951

    Subcontractor; risk prevention; political risk; project subcontracting; general contractor

    # 4 The contractor

    18

    1

    Contractor; international works; contract terms; fidic; risk management

    # 5 Management

    17

    0.846

    Management; claims; project management; tax risk; engineering

    # 6

    Countermeasures

    16

    0.894

    Countermeasures; problems; contract management; international projects; general contracting

    # 7 Compliance management

    15

    0.918

    Compliance management; risk control; Angola; enterprise "going out"; host country

    #8 risk

    14

    1

    Risk; prevention; analysis; construction project; risk management

    # 9 Risk analysis

    13

    0.873

    Risk analysis; foreign exchange risk; performance guarantee; countermeasures; buyer's credit

    #10Belt and Road

    11

    0.981

    Belt and Road; Chinese enterprises; letter of credit; railway; epidemic risk

    According to the classification of cluster labels (Table 5), the research hotspots of engineering project risk management are analyzed from three aspects: risk involved object, risk theory research and risk practice response. In terms of risk objects, scholars mainly pay attention to the risks of contractors in international projects. Ma Jianjun believes that in the process of business transformation and upgrading, in order to effectively prevent major business risks, it is necessary to establish their own unique business risk management system, so as to guide the sound and rapid development of international project contracting business.5 Liu Lin believes that in the process of the country's continuous promotion of "Belt and Road" construction, the initiative to "go global" have provided a good internal and external environment for China's outbound investment. However, the complex geopolitical risks, imperfect economic and legal systems, cultural differences and unstable public relations have led to many challenges in China's outbound investment. In light of domestic and international situations, encouraging Chinese enterprises to "go global" through the establishment of international governance system, developing diversified investment models, and establishing people-to-people and cultural exchange mechanisms, which is a good condition for achieving win-win outbound investment and cooperation against the context of "Belt and Road".6 From the point of risk basic theory research, different from the domestic project common traditional risk, scholars in the field is more focused on the international contracting project exchange rate risk, liu junying liu think international engineering exchange rate influence factors, it is difficult to predict, the contractor should take international project life cycle as the main line of the project exchange rate risk take appropriate measures to manage.7 Zhu Yi systematically identified and classified the risk factors of international contracting projects through literature research and expert interview, and applied AHP method to analyze the risk factors, and finally found the classification system of risk factors according to the weight value and changes.8 In terms of risk practice response, Liu Qiang established the basic framework of risk management of overseas engineering projects through practical engineering cases, analyzed the main process and management control points of enterprise-level and project-level risk management, and summarized the methods and experience of Chinese enterprises in the risk management of overseas international engineering projects. The implementation methods of the risk management system and framework in the international engineering project are discussed and analyzed. 9 in recent years, When China's international engineering contracting enterprises conduct their international business, Often subject to sanctions by the World Bank, the Asian Development Bank and other international multilateral banks due to compliance

    management and other factors, According to Juna, Given that international engineering contractors are often sanctioned by international multilateral banks such as the World Bank and the Asian Development Bank due to compliance management and other factors, The Contractor shall be aware of the rules and standards established by the US Department of Justice, ICC, International Bank, and International Organization for Standardization, International rules and standards should be integrated into the enterprise management system, Combined with the daily compliance management work of the enterprise, Establish a practical compliance management system, So as to explore and form the best compliance management practies in line with their own situation.10 In response to the risk of sudden outbreak in recent years, Liu Xinwei believes that COVID-19 continues to spread around the world, and overseas Chinese projects have suffered a great impact. While suffering from economic losses, enterprises are faced with the systemic risks of force majeure and a large number of potential legal disputes. International contracting project enterprises should be problem-oriented and designed to cope with the risk of the epidemic.11

    Table 5 Keyword cluster classification table

    classify

    Cluster name

    Risk research object

    # 0 International Works;

    # 3 Subcontractor;

    # 4 Contractor;

    # 10 Belt and Road

    Risk methodology

    # 1 Exchange rate Risk

    # 2 Risk Factor # 8 risk

    Risk practice theory

    # 5 Management

    # 6 Countermeasures

    # 7 Compliance management

  6. THE EVOLUTION TREND OF DOMESTIC DIGITAL GOVERNANCE RESEARCH

    The keyword timeline clustering of CiteSpace software can visualize the evolution trend of a research field in a certain time range, which is conducive to scholars to investigate the relevant research progress and frontier dynamics in a relatively long-term scope based on a historical perspective. This study is presented by the keyword timeline clustering and keyword emergence analysis.

    1. Keyword timeline clustering map analysis

      CiteSpace The time variables are introduced into the graph network, and the time line cluster graph is generated through the clustered keywords, sketching the historical trajectory and time span of the development of specific keywords in each cluster. According to the timeline map information of keywords, the risk study of international contracting projects from 2000 to 2021 can be generally divided into the following three stages (Table 6).

      The first stage is the initial period of 2000-2005. At this stage, the CPC Central Committee established and implemented the "going global" strategy, and the number of domestic enterprises going global and the amount of contracts increased significantly. Scholars mainly study from a macro perspective, focusing on international engineering, contractors, engineering contractors, subcontractors, risks and other basic content.

      The second stage is the rising period from 2006 to 2010. With the continuous extension and expansion of the research content, a clear research context is gradually formed. This stage mainly focuses on the theoretical and practical response of risk identification, risk early warning, risk control, risk prevention, bidding risk, contract risk, contract management, insurance company, insurance claim and other specific risks.

      The third stage is the breakthrough period 2011-2021. This stage begins to focus more on and refine, and starts in the direction of refinement and internationalization. Contract management, tax risk, contract text, overseas operation, host country, integration ability, compliance management, the whole chain, epidemic prevention and control risk control stage research hotspot, related research to the micro level, contract management, contract text, tax risk, epidemic prevention and control shows that research context keywords more detailed, overseas management, host country, territorial management, integration ability, the whole chain of keywords show that enterprises in this stage has attention in the host country to carry out the whole chain of localized management risk.

      Table 6 Timeline clustering stage of international contracting projects

      stage

      time

      keyword

      stage

      2000-2005

      International engineering, engineering contracting, subcontractors, contractors, risk, exchange rate risk, project financing, project management, claim management

      stage

      2006-2010

      Risk identification, risk early warning, bidding risk, risk early warning, risk control, risk prevention, contract risk, bid quotation, contract management insurance company, insurance claim

      phase III

      2011-2021

      Contract management, risk management and control, tax risk, contract text, overseas operation, localization, host country, integration ability, compliance management, the whole chain, epidemic

      prevention and control

    2. Present analysis of key words

    Through CiteSpace software, 2009 documents were sorted by present years, and the visual view spectrum of key keywords in international contracting project risk research from 2000 to 2021 was detected. According to the analysis results, it can be divided into three stages: the first stage is 2000-2010. claim, project bidding, foreign exchange risk and contractor are the research focus of this stage. These two keywords not only last for a long time, but also have large strength, which

    are the only keywords with more than 10 strength. The second stage is from 2010 to 2015. Related research mainly focuses on keywords such as going out, project contracting, Libya, contract amount, financial risk, and political risk. The third stage is from 2015 to 2021. Belt and Road, tax risk, risk prevention and control, and epidemic prevention and control have become new hot spots in the risk research of international contracting projects, which deserve further attention.

  7. STUDY CONCLUSIONS AND FUTURE PROSPECTS

  1. Study Conclusion

    In this study, 2009 international contracting project risk research papers from China Knowledge Network (CNKI) from 2000 to 2021 were taken as the research object, and the development process and hot topics of international contracting project risk research were analyzed and discussed. The research conclusions can be summarized as the following points.

    First, from the overall trend of the research, the international contracting project risk research rapid development, research heat continues to rise, the relevant research published with the international contracting project business completed steady growth, under the "area" initiative, with the development of the international engineering contracting industry in the field is still a research hotspot.

    Second, from the author and research institutions present map, international contracting project risk research core author group has been formed, but between scholars, research network density is low, research between scholars and institutions cooperation is not close enough, between

    colleges, scholars, cooperation between enterprise width and depth is still have development space. Secondly, the main research institutions in this field are mainly state-owned enterprises that carry out international contracting project business, supplemented by universities and law firms. In the next step, private enterprises should pay attention to the experience accumulation and research in this field when going out to carry out international project contracting business.

    Third, from the perspective of keyword co-occurrence map, keywords with high word frequency include international engineering, risk management, risk, contractor, project management, exchange rate risk, risk identification, risk analysis, etc. Based on the keyword cluster analysis map, this study summarizes the three hot topics of domestic and international contracting project risk research, including three aspects of risk related objects: risk object, risk theory research and risk practice response of engineering project risk management.

    Fourth, based on the keyword timeline map and keywords appear results, combing the domestic and international contracting project risk research development process and

    evolution trend, put forward can the field research is divided ito starting stage (2000-2005), rising period (2006-2010) and breakthrough (2011-2021), and through the analysis of time line map and keywords present information summarizes the forefront of the research direction, for future research has certain significance.

  2. Research outlook

First, on the cooperation network, it is suggested to strengthen the horizontal and vertical cooperation between enterprises, schools and scholars. International contracting projects involve multiple disciplines, involving not only traditional business risks such as engineering quotation in multiple fields, engineering construction, engineering management, financial management, contract management and tax planning, but also political risk, exchange rate risk, legal risk, social risk and other risks that are different from domestic contracted projects. As the risk practice of international contracting projects gradually advances to localization, this field requires researchers who understand language, national conditions, technology and management to make in-depth analysis and interpretation. Therefore, scholars from different institutions and disciplines should strengthen cooperation to jointly promote the deepening research in this field.

Second, in terms of research topics, we should continue to pay attention to the successful risk response cases of international contracting projects in various countries, summarize the experience of preventing risks, defusing risks and reducing risk losses in practice and enrich the practical theories in this field.

Thirdly, in terms of research content, the risk research in various relevant fields of the host country should be carried out under the localized diversified management strategy, and the risks should be continuously refined and improved, so as to lay a foundation for the high-quality development of enterprises' localized international contracting projects in the host country.

MAIN REFERENCES:

[1] Zhang Lei, and Li Xingen."Knowledge map of domestic science and technology ethics research based on bibliometric analysis of CSSCI papers from 1998 to 2021. Journal of Southwest University for Nationalities (Humanities and Social Sciences Edition) 43.07 (2022): 224-232.

[2] Jiang Chunlin. Price and scientometrics."Science and Science and technology management".09(2001):20-22.

[3] Ma Jianjun. Discussion on the management of risk management of international engineering contractors."International Engineering and Labor Service.07(2018):77-78.

[4] Liu Lin. Research on the win-win path of foreign investment cooperation under the background of "Belt and Road"."Modernization of the shopping mall.18(2022):54-56. doi:10.14013/j.cnki.scxdh.2022.18.005.

[5] Sun Xiaodan, Wang Bo, and Liu Junying. Coping with the exchange rate risks of international engineering contracting projects."International economic cooperation.09(2008):57-60

[6] Zhu Yi, et al. Study on EPC international engineering risk factor grading based on the general contractor's perspective. Project

Management Report 26.05 (2012): 1-6.

[7] Liu Qiang, and Jiang Yongxin."International engineering project risk management framework and case analysis."Project Management Technology 7.12 (2009): 59-64.

[8] Ju Na."International Engineering third-party Compliance Management best practices."International Engineering and Labor Service.07(2019):55-57.

[9] Liu Xinwei. In response to the risk of the epidemic, international projects should be alert of ten easy mistakes."China's foreign trade.09(2020):40-41.