Impact of FACTS Devices on Bilateral Transactions of Deregulated Power System

DOI : 10.17577/IJERTV3IS041811

Download Full-Text PDF Cite this Publication

Text Only Version

Impact of FACTS Devices on Bilateral Transactions of Deregulated Power System

  1. Catherine Divya

    PG Scholar

    Electrical and Electronics Engineering Kamaraj College of Engineering and Technology

    Virudhunagar, Tamilnadu, India

    Dr. S. Nagalakshmi

    Assistant Professor Electrical and Electronics Engineering

    Kamaraj College of Engineering and Technology Virudhunagar, Tamilnadu, India

    AbstractThis paper concerns the optimal location and control of Flexible AC Transmission System (FACTS) devices using Differential Evolution (DE) for achieving Security Constrained Optimal Power Flow (SCOPF) for Bilateral model of deregulated electricity market. This approach uses AC load flow equations with the constraints on power system generation, transmission line flow, magnitude of bus voltages, and FACTS device settings. For the proposed method two types of FACTS devices namely, Thyristor Controlled Series Compensator (TCSC), Static VAR Compensator (SVC) are used. The bilateral transactions are modeled using secured bilateral transaction matrix utilizing the AC distribution factor with slack bus contribution.In this work, SCOPF is performed considering the installation cost of FACTS devices during normal operating condition. To validate the proposed approach simulations are performed on IEEE 6 bus system. The impact of FACTS devices on bilateral transactions of the deregulated power system is analysed based on the economical aspect as well as security aspect. The results indicate that by optimal location and control of FACTS devices is determined by DE algorithm reduces the active power generation bidding cost as well as the installation of FACTS devices. Among the two FACTS devices, SVC gives minimum cost of active power generation bidding and minimum installation cost than TCSC.

    Keywords Differential Evolution(DE) algorithm, Flexible Alternating Current Transmission System (FACTS), Security Constrained Optimal Power Flow (SCOPF), Static Var Compensator (SVC), Thyristor Controlled Series Compensator (TCSC).

    1. INTRODUCTION

      In recent years, rapid growth of power demand due to the growing population necessitates the electric utilities to serve more power through their networks and also to maintain system security [1]. Due to the increased demand electric power system is changing into Deregulated Structure. In general, deregulated power system consists of three models namely pool, bilateral and hybrid [2]. In this paper, SCOPF is considered in bilateral model of deregulated power system. In the bilateral model, the bilateral transactions take place directly between the buying and selling entities.Basics about bilateral transactions are studied, under a deregulated environment, electricity consumers and suppliers will be permitted to establish various bilateral service contracts [3]. The bilateral transactions are modeled using secured bilateral

      transaction matrix utilizing AC Distribution Factor with slack bus contribution [4, 5]. For pure bilateral model, the reactive power support is obtained from synchronous generators.The operation of power systems under a mix of physical bilateral transactions and pool-supplied demand, all subject to some degree of combined pool/bilateral coordination is examined [6].

      Better system operating conditions are achieved when sufficient security and economy are accounted which is known as Security Constrained Optimal Power Flow (SCOPF).The SCOPF is an extension of OPF problem which takes into account constraints arising from the operation of the system under a set of postulated contingencies. The SCOPF problem is a nonlinear, non-convex, large-scale optimization problem, with both continuous and discrete variables [7, 8].

      As a solution to this problem, either the existing transmission lines must be effectively utilized, or new transmission lines should be added to the existing system. Environmental right-of-way and cost problems are major hurdles for power transmission network expansion. Hence there is an interest for better utilization of existing power system capabilities. Flexible AC Transmission Systems (FACTS) devices have gained a great interest in transmission system due to recent advances in power electronics [9, 10].

      SCOPF with FACTS devices using conventional methods and computational algorithms have been carried out. Sensitivity based approach was proposed to locate Thyristor Controlled Series Compensator (TCSC) and Unified Power Flow Controller (UPFC), considering voltage and angle sensitivities with respect to changes in the system load [11]. Continuation Power Flow (CPF) was used for obtaining the size and locations of the series compensators to increase the security of the system. This study identifies critical lines that can initiate cascading line outages and optimal location and parameter settings of series and shunt compensators [12]. Population based computational intelligent techniques such as Genetic Algorithm (GA), Evolutionary Programming (EP) and Particle Swarm Optimization (PSO) were used to determine optimal location of FACTS devices. EP was proposed to obtain optimal placement of multi-type FACTS devices for simultaneously maximizing the total transfer capability whereas minimizing the total system real power loss and the results are better when compared to loss sensitivity index

      method [13]. The optimal location for single and multi-type a,b,c – cost coefficients of the generator.

      FACTS devices to improve system security was determined using PSO [14]. Among the available algorithms to solve optimization problems DE is simple, accurate, robust, few

      ICTCSC

      ICSVC

      0.0015s2 0.7130s 153.75

      0.0003s2 0.3051s 127.38

      (3)

      (4)

      parameters to set, and also finds the optimum in almost every run[15].

      In this paper, DE is used for finding the optimal location

      Where,

      s Q2 Q1

      s – Operating range of FACTS devices in MVAR;

      (5)

      and parameter setting of TCSC and SVC to achieve Secured optimal power flow in bilateral model of deregulated power system. The objective of this work is performed in two steps. The first step is to obtain secured bilateral transaction matrix which has minimum overall deviation from the proposed

      Q2 – Reactive power flow in the line after installing FACTS devices in MVAR;

      Q1 – Reactive power flow in the line before installing

      FACTS devices in MVAR;

      transaction matrix. Then, the second step is to optimally locate TCSC and SVC to minimize both the active power generation cost and installation cost of FACTS devices satisfying the equality and inequality constraints. In order to validate the performance, simulations are performed on IEEE 6 bus system and the results are analyzed.

    2. MODELING OF FACTS DEVICES

      1. Modeling of TCSC

        TCSC consists of series compensating capacitor shunted by thyristor controlled reactor. It is modeled as a

      2. Equality Constraints

        Power balance equation

        Pi (V , ) Pdi Pgi 0

        Qi (V , ) Qdi Qgi 0

      3. Inequality Constraints Power generation limit

      P P P

      min max

      gi gi gi

      Q min Q Q max

      i=1Nb (6)

      i=1Nb (7)

      i=1Ng (8)

      i=1Ng (9)

      controllable reactance, inserted in series with the transmission line to adjust line impedance and thereby control power ow to increase the network security as shown in Fig.1 [16].

      i j

      XTCSC Xij

      Fig. 1 Block diagram of TCSC

      gi gi gi

      Bus voltage limits

      i i i

      V min V V max

      Apparent lineflow limit

      l l

      S S max

      FACTS device constraints

      0.8* Xij XTCSC 0.2* Xij

      i=1Nb (10)

      l=1Nl (11)

      (12)

      Xij new Xij XTCSC

      Where, Xijnew – reactance after the location of TCSC

      (1)

      100 QSVC 100

      Where,

      (13)

      Xij – reactance of the transmission line XTCSC – reactance of the TCSC

      B. Modeling of SVC

      Pgi , Qgi

      Pdi , Qdi

      • real and reactive power generation at bus i;

      • real and reactive power demand at bus i;

        SVC is modelled as shunt connected static VAR generator or absorber, QSVC whose output is adjusted to

        Vi – Voltage magnitude at bus i;

        exchange capacitive or inductive compensation and is inserted

        V min ,V max

        – minimum and maximum voltage limits;

        directly to the load bus as shown in Fig. 2 [17]. i i

        P min , P max

      • minimum and maximum limits for real power

        i gi gi

        generation;

        QSVC

        Fig. 2 Block diagram of SVC

    3. PROBLEM FORMULATION

      Nb Ng Sl

      S

      max

      l

      X ij

        • The total number of buses;

        • The total number of generator buses;

        • The apparent power flow in transmission line;

        • Maximum power flow limit;

        • Reactance of the transmission line;

      A. Objective function

      The objective function is to minimize the active power generating cost, which is expressed as:

      – Reactance of the TCSC;

      X

      TCSC

      D. Determination of Secured Bilateral Transaction Matrix

      g

      MiniN Ci (Pgi ) ICFACTS

      Where,

      i gi gi gi

      C (P ) aP 2 bP c – cost curve of ith generator;

      (2)

      The lossless bilateral contract model is formulated using the contracts as controllable variables and the system security limits as binding constraints [9]. There are some intrinsic

      properties associated with this transaction matrix, namely column, row, range and flow rules [8], [9]. The bilateral transactions between sellers and buyers are deemed to be secured only if the transaction matrix satisfies all the intrinsic properties.

      Pfb – Bilateral real power flow.

      • AC Distribution Factor

        n

        AC Distribution Factor is defined as change in real power flow in transmission line connected between bus-i and bus -j (Pij) due to unit change in power injection at any bus-n (Pn).

        • Bilateral Model of Deregulated Power System Bilateral model is one in which the customers are free to

      contract directly with power generating companies to

      ACDF ij

      Pij

      Pn

      (21)

      obtain lowest rate and most desirable service. It is also called as direct access model. It is shown in fig.3

      To obtain fairness in the competitive environment, the

      line flow sensitivity at the slack bus should not be zero corresponding to the injections at the slack bus. To attain this, a shift factor as defined in [13] has been obtained and added to the calculated values of ACDF. The modified values of ACDF obtained are

      ACDFs k new ACDFs k P_shiftfactor

      n

      P _ shiftfactor

      n

      1. Pij

      2. Pi

        • Pij

          Pj

          (22)

          Fig.3. Bilateral Model of Deregulated Power System

          • Objective function

        The objective is to find secured bilateral transaction matrix T which has overall minimum deviation from the proposed transaction matrix T0 satisfying equality and inequality constraints.

    4. IMPLEMENTATION OF DE FOR SCOPF WITH

      FACTS DEVICES

      Storn presented classical DE algorithm in 1995 which consists of four steps namely initialization of population, mutation, crossover or recombination and selection [18].

        1. Initialization

          DE searches for global optimum point in a D- dimensional real parameter space. The population members

          Min b t

          t 0 2

          are randomly initialized using Equation (22).

          i j ij ij ij

          (14)

          ( 0 )

          (22)

          where tij0- ijth element of proposed transaction matrix T0 , tij –

          Xi, j

          Where

          X j min

          rand [0,1] ( X j max

          X j min )

          1. 1,Np

          2. 1,D

            ijth element of secured bilateral transaction matrix T, bij – constant assumed to be 1 for all (i,j) terms.

            • Equality constraints

          Real and reactive power balance equations

          Np – population size; D dimension;

          Xi,j(0) – initially generated target vector;

          rand [0,1] – uniformly distributed random number between 0 and 1;

          Pgi

          – Pdi

          Pi

          j nb

          (15)

          i – number of population; j – number of variables;

          Qgi – Qdi Qi

          j nb

          (16)

          Xjmax – maximum value of the individual;

          Real power generation for bilateral transactions

          Xjmax – minimum value of the individual.

          Considering the variables that should be optimized (i.e.,

          Pgbi

          tij

          j

          j nb

          (17)

          the location and the parameter setting of FACTS device). These parameters are randomly initialized within feasible

          Real power demand for bilateral transactions

          ranges.

          Pdb j

          tij

          i

          i nb

          (18)

        2. Mutation

          Mutation is a change or perturbation with a random element. The difference of any two of these three vectors is

          Real power balance equation for bilateral transactions

          Pgbi Pdbj

          (19)

          scaled by a scaling factor F and the scaled difference is added to the third one to obtain the donor vector using Equation

          i j (23).

          Power flow equations for bilateral model

          Pfb ACDF Pgb – Pdb

          (20)

          Vi, j ( t ) X r1, j( t ) F ( X r2, j( t ) X r3, j( t ) )

        3. Crossover

          (23)

          where

          Pgb – Bilateral real power generation, Pdb – Bilateral real power demand, ACDF – AC distribution factor,

          To enhance the potential diversity of population, a crossover operation is performed after generating the donor vector through mutation. The trial vector is determined using Equation (24)

          Ui, j

          ( t )

          Vi, j( t )

          X i, j( t )

          if rand(0,1) Cr else

          (24)

          TABLE III. SECURED BILATERAL TRANSACTION MATRIX

          Value of transaction between generator and load bus (p.u)

          T(1,4)=0.1

          T(1,5)=0.4

          T(2,4)=0.1

          T(3,4)=0.1

          T(3,5)=0.3

          T(3,6)=0.2

        4. Selection

      The next step is to select target vector or trial vector using the Equation (25) for next generation.

      Xi, j

      ( t 1 )

      Ui, j (t)

      if f (Ui, j( t ) )

      f( X i, j( t ) )

      (25)

      X i, j(t) else

      where f (.) – Fitness function

      If the trial vector yields an equal or lower value of fitness function, it replaces the corresponding target vector in next generation; otherwise the target vector is retained in the population. Hence, the population gets either better or remains the same in fitness status, but never deteriorates. Stop the process and print the best individual if the stopping criterion is satisfied, else go back to mutation.

    5. RESULTS AND DISCUSSION

      1. Tools and Test systems

        Programming codes for DE was developed using MATLAB 7.10.0 and SCOPF was solved with modified version of Matlab power simulation package MATPOWER 4.0b4 [19]. DE algorithms has been tested on IEEE 6 bus test system .The initial parameter values adopted for PSO and DE algorithms are presented in TABLE I. Simulations are performed in a computer with Intel i3 processor 2.66GHz and 4GB RAM.

        In order to verify the effcts of optimal location of FACTS devices four cases were investigated.

        Case 1: SCOPF without FACTS & without considering line limits

        Case 2: SCOPF without FACTS considering line limits Case 3: SCOPF with TCSC considering line limits Case 4: SCOPF with SVC considering line limits.

        TABLE IV. BIDDING COST OF IEEE 6 BUS SYSTEM

        Generator Number

        Bidding Cost

        1

        11 ($/Mwhr)

        2

        15 ($/Mwhr)

        3

        12 ($/Mwhr)

        Case 1

        Case 2

        Case 3

        Case 4

        Pg1

        107.87 MW

        60 MW

        60 MW

        60 MW

        Pg2

        50 MW

        40.MW

        40 MW

        40 MW

        Pg3

        60MW

        110MW

        110 MW

        40 MW

        TABLE V. REAL POWER GENERATION PROFILE FOR IEEE 6 BUS SYSTEM

        TABLE I. INITIAL PARAMETER VALUES OF DE

        Parameters

        Values

        Population Size

        20

        Number of iterations

        200

        Number of variables

        2

        Scaling Factor

        0.8

        Crossover Ratio

        0.8

        Convergence criteria

        10-6

      2. IEEE 6 bus test system

        IEEE 6 bus system has 6 buses, 11 transmission lines, 3 generators and 3.The data for the system are on 100 MVA base. The real and reactive power demand for base case is 210 MW, 210 MVAR respectively.

        • Results for bilateral model

      The proposed bilateral transaction matrix is given in TABLE II and the secured bilateral transaction matrix is determined and is given in TABLE III.

      TABLE II. PROPOSED BILATERAL TRANSACTION MATRIX

      Value of transaction between generator and load bus (p.u)

      T(1,4)=0.2

      T(1,5)=0.4

      T(2,4)=0.4

      T(3,4)=0.1

      T(3,5)=0.3

      T(3,6)=0.7

      TABLE VI. REACTIVE POWER GENERATION PROFILE FOR IEEE 6 BUS SYSTEM

      Case 1

      Case 2

      Case 3

      Case 4

      Qg1

      55.79

      MVAR

      15.95

      MVAR

      55.37

      MVAR

      79.84

      MVAR

      Qg2

      46.21

      MVAR

      74.35

      MVAR

      43.71

      MVAR

      89.57

      MVAR

      Qg3

      77.22

      MVAR

      89.62

      MVAR

      79.26

      MVAR

      100

      MVAR

      In TABLE V, real power generation values of three generators are summarized. From this table it is clear that real power generation at all the three generators are within their limits. In TABLE VI, reactive power generation values are given. From the results it is understood that reactive power generation at all the generators are satisfying the limits. Real power values and reactive power values are plotted in Fig.4 and Fig.5.

      Fig.4. Real power generation profile

      Fig.5.Reactive power generation profile

      TABLE VII. OPTIMAL GENERATION PROFILE FOR IEEE 6 BUS SYSTEM

      Cases of Analysis

      Case1

      Case2

      Case3

      Case4

      Location of FACTS

      devices

      Line 9

      (3-6)

      Bus 5

      FACTS

      device settings

      X TCSC=

      -0.16 p.u.

      QSVC=

      -73.96

      MVAR

      Total

      active power generation

      cost

      2375.49

      ($/hr)

      2389.84

      ($/hr)

      2372.56

      ($/hr)

      2370.25

      ($/hr)

      Installation cost of FACTS

      devices

      151.34

      ($/hr)

      129.78

      ($/hr)

      Total cost

      2375.49

      ($/hr)

      2389.84

      ($/hr)

      2523.9

      ($/hr)

      2500.03

      ($/hr)

      In TABLE VII, location and parameter setting of TCSC and SVC, active power generation cost, installation cost of FACTS devices are given. Active power generation cost is calculated with the use of bidding cost which is given in TABLE IV. From TABLE VII it is understood that active power generation cost is 2372.56($/hr) while using DE algorithm, which gives the result as line 9(3-6) is the best location of placing TCSC.

      In addition to that parameter setting of TCSC has found by DE algorithm and minimum cost of active power generation has obtained. It shows that effectiveness DE such as less computation time and minimum active power generating cost by the placement of TCSC at optimal location and its parameter setting.

      Optimal location of SVC and Parameter setting of SVC has found by the proposed method. By placing SVC at optimal location (bus 5) the active power generating cost has further reduced from 2372.56($/hr) to 2370.25($/hr).Comparison between cost of active power generation, installation cost of FACTS devices, total cost are plotted in Fig.6.

      Fig.6. Comparison of total cost at all cases Apparent power flow in IEEE 6 bus system with TCSC in

      line 3-6and SVC in bus 5 are summarized in TABLE VIII.

      TABLE VIII. APPARENT POWER FLOW PROFILE (IN P.U.) FOR

      IEEE 6 BUS SYSTEM

      Line

      i-j

      MVA

      limit

      Case 1

      Case 2

      Case 3

      Case 4

      1-2

      0.4

      0.0524

      0.0632

      0.0461

      0.0418

      1-4

      0.6

      0.3552

      0.3991

      0.5111

      0.3271

      1-5

      0.4

      0.2560

      0.2816

      0.2312

      0.2255

      2-3

      0.4

      0.1156

      0.1057

      0.0356

      0.0404

      2-4

      0.6

      0.6427

      0.6000

      0.5894

      0.5069

      2-5

      0.3

      0.2422

      0.2314

      0.2582

      0.2027

      2-6

      0.9

      0.2787

      0.2764

      0.3157

      0.2816

      3-5

      0.7

      0.3334

      0.3120

      0.2909

      0.2406

      3-6

      0.8

      0.7759

      0.7536

      0.6984

      0.6405

      4-5

      0.2

      0.0527

      0.0519

      0.6310

      0.1379

      5-6

      0.4

      0.0902

      0.0770

      0.0723

      0.0731

      From TABLE VIII it is understood that while placing TCSC at line 3-6 with the parameter setting obtained, the loading of the line 2-4 has now reduced to 98.23%, while placing SVC in bus 5 the loading of line 2-4 has further reduced to 84.48%.

      2660

      Total cost of active power generation($/hrr)

      2640

      2620

      2600

      2580

      2560

      2540

      2520

      0 5 10 15 20 25 30 35 40 45 50

      Number of iterations

      Fig.7 Convergence characteristics of DE algorithm with TCSC

      2660

      Total cost of active power generation($/hr)

      2640

      2620

      2600

      2580

      2560

      2540

      2520

      2500

      0 5 10 15 20 25 30 35 40 45 50

      Number of iterations

      Fig.8 Convergence characteristics of DE algorithm with SVC

      From Fig.7 and Fig.8, it is understood that in both the cases DE convergences faster with optimal value of objective function.

      TABLE IX. STATISTICAL DETAILS OF DE ALGORITHM UNDER NORMAL OPERATING CONDITION

      Compared item

      With TCSC

      With SVC

      Fcost-Best ($/hr)

      2523.9

      2500.03

      Fcost-Worst ($/hr)

      2652.52

      2598.05

      Fcost-Average ($/hr)

      2588.21

      2549.04

      Standard deviation

      9.80359915E-12

      4.617035E-12

      Statistical details of DE algorithm for IEEE 6 bus system is shown in TABLE IX. From the standard deviation value given in TABLE IX it is clear that DE is more robust.

    6. CONCLUSION

In deregulated electricity market, because of environmental right-of-way and cost problems, various techniques are utilized to solve the problems of power transmission network without network expansion. Installation of TCSC and SVC devices in a power system improves the system security under normal and contingency operating conditions. The effectiveness of TCSC and SVC devices greatly depends on where the devices are located. In this work DE algorithm was used to obtain the optimal location of TCSC and SVC for SCOPF problem. Minimization of active power generation cost and installation cost of TCSC, SVC are considered as optimization criterion.

Simulations were performed on IEEE 6 bus test system. From the results it is understood that, DE is more effective, easy to use, robust algorithm having less computational time and faster convergence characteristics for optimal location FACTS devices in transmission system to SCOPF problem for Bilateral Model of deregulated electricity market.

Among the two FACTS devices used, SVC gives minimum cost of active power generation and minimum installation cost than TCSC. To conclude, for optimal location FACTS devices in transmission system to SCOPF problem for Bilateral Model of deregulated power system with FACTS devices using the computational intelligence algorithm, DE with SVC gives better performance.

REFERENCES

  1. J. Wood Allen and F.Wollenberg Bruce, Power generation operation and control ,2nd ed. John Wiley & Sons Inc; 1996.

  2. M. Shahidepour and M. Alomoush, Restructured Electrical Power Systems, Operation, Trading, and Volatility, Marcel Dekker, Inc. New York, 2001.

  3. J. W. M. Cheng, F. D. Galiana, and D. T. McGills, Studies of bilateral contracts with respect to steady state security in a deregulated environment, IEEE Transactions on Power systems, Vol.13,No.30, pp. 1020-1025,1998.

  4. S. Nagalakshmi, N. Kamaraj, Comparison of computational intelligence algorithms for loadability enhancement of restructured power system with FACTS devices Swarm and Evolutionary Computation,Vol. 5 ,pp.1727,2012.

  5. Kumar, S. Chanana, New secure bilateral transaction determination and study of pattern under contingencies and UPFC

    in competitive hybrid electricity markets, International Journal on Electrical Power and Energy Systems, pp. 23-33,2009.

  6. F. D. Galiana, I. Kockar, and P. Cuervo, Combined pool/bilateral dispatch: Part I: Performance of trading strategies, IEEE Transactions on Power Systems,Vol.1,No.7, pp. 9299,2002.

  7. O. Alsac and B. Stott, Optimal load flow with steady-state security, IEEE Transactions on Power App. Syst., Vol. PAS- 93, No. 3, pp. 745751, May/Jun.1974.

  8. J. Monticelli, M. V. P. Pereira, and S. Granville, Security- constrained optimal power flow with post-contingency corrective rescheduling ,IEEE Trans. Power Syst., Vol. 2, No. 1, pp. 175 182,Feb. 1987.

  9. Hingorani, N.G. and Gyugyi, L., Understanding FACTS: concepts and technology of Flexible AC Transmission Systems, New York, IEEE Press, 2001.

  10. F.D.Galiana et al, Assessment and control of the impact of FACTS devices on power system performance, IEEE Transactions on Power Systems, Vol.11, No.4, pp. 1931-1936, 1996.

  11. J.G. Singh, S.N. Singh, S.C. Srivastava, Placement of FACTS Controllers for Enhancing Power System Loadability, IEEE Power India Conference, 2006.

  12. R. Rajaraman, F. Alvarado, A. Maniaci, R. Camfield, S. Jalali, Determination of location and amount of series compensation to increase power transfer capability,IEEE Transactions on Power Systems, Vol. 13, No. 2,pp. 294300, 1998

  13. W. Ongsakul, P. Jirapong, Optimal allocation of FACTS devices to enhance total transfer capability using evolutionary programming, IEEE International Symposium on Circuits Systems ISCAS,Vol. 5,pp. 41754178,2005.

  14. M. Saravanan, S. MaryRajaSlochanal, P. Venkatesh, J. Prince Stephen Abraham,Application of particle swarm optimization technique for optimal location of FACTS devices considering cost of installation and system loadability, International Journal of Electric Power Systems Research, Vol. 77, pp. 276283,2007.

  15. A.A. Abu El Ela, M.A. Abido, S.R. Spea, Differential evolution algorithm for emission constrained economic power dispatch problem, International Journal of Electrical Power Systems Research,Vol. 80, No.10, pp.1286-1292,2010.

  16. W.Ongsakul ,P. Bhasaputra, Optimal power flow with FACTS devices by hybrid TS/SA approach, Electrical Power and Energy Systems ,vol. 24,pp. 851857,2002.

  17. D. Mondal, A. Chakrabarti, A. Sengupta, Optimal placement and parameter setting of SVC and TCSC using PSO to mitigate small signal stability problem , Electrical Power and Energy Systems, vol. 42, pp.334-340,2012.

  18. R. Storn and K. Price, Differential Evolution A Simple and Efficient adaptive scheme for global optimization over continuous spaces, Technical Report, International Computer Science Institute, Berkley, pp. 1-12,1995

  19. Ray D. Zimmerman, Carlos E. Murillo-Sanchez and Deqiang (David) Gan, MATPOWER: MATLAB power system simulation package

    Biography

    1. Catherine Divya is pursuing her postgraduate degree in Power Systems Engineering at Kamaraj College of Engineering & Technology, Virudhunagar, Anna University, Chennai, Tamil Nadu. She completed her undergraduate degree in Electrical & Electronics Engineering in the year 2012 at KLN College of Engineering, Anna University, Chennai, Tamil Nadu. Her main area of interest includes application of FACTS technology and computational intelligence techniques to solve power system problems.

S.Nagalakshmi has completed Ph.D. in the faculty of Electrical Engineering at Anna University, Chennai, Tamil Nadu. She completed her postgraduate degree in Power Systems Engineering in the year 2000 and undergraduate in Electrical & Electronics Engineering in the year 1999 at Madurai Kamaraj University, Tamil Nadu. She is working as Assistant Professor in the Department of Electrical & Electronics Engineering, Kamaraj College of Engineering &Technology, Virudhunagar, Tamil Nadu. Her main research area of interest includes power system restructuring,

Leave a Reply