Iot Based Energy Auditing System in Boys Hostel

DOI : 10.17577/IJERTCONV6IS07065

Download Full-Text PDF Cite this Publication

Text Only Version

Iot Based Energy Auditing System in Boys Hostel

R. Vengatesh 1, K. Subiramani 1, P. Thangamani1, M. Rajeshwaran1, S. Dinesh Kumar2

1UG scholar, Department of EEE, M.Kumarasamy College of Engineering, Karur.

2Assistant professor, Department of EEE, M.Kumarasamy College of Engineering, Karur.

Abstract—-In this paper, the importance of energy auditing and process of energy auditing are presented in detail. A sincere attempt has been made to conduct the energy audit at M.Kumarasamy College of Engineering, Karur, to estimate the Energy consumed in a day, week and month. Identification of area of energy wastage and estimation of energy saving potential in boys hostel and mess has been made by walk through energy audit. Also, detailed analysis of data collected is done by suggesting cost-effective measures to improve the energy efficiency of use. Estimation of implementation costs and payback periods for each recommended action has been made. The result & vital information generated through these activities are documented. The Energy Auditing for a day is the index of the consumption which normalize the situation of Energy crises by providing the conservation schemes.

  1. INTRODUCTION

    In energy audit is an inspection, survey and analysis of energy flows, for energy conservation in a building, processor system to reduce the amount of energy input to the system without negatively affecting the output(s).In commercial and industrial real estate, an energy audit is the first step in identifying opportunities to reduce energy. The main goal of our project is survey of energy consumption and to minimize the energy wastage and to identify the energy saving location in boys hostel and mess at M. Kumarasamy College of Engineering, Karur. Design and architect professionals as well as plant engineers have to recognize the importance of reducing overall energy consumption, whether it is a building, plant or process that is under their jurisdiction for design construction or operation. Energy use reduction or energy conservation has four main steps. The planning of energy conservation requires setting goals to meet within the time frame available, prioritizing the use of resources, and determining a schedule for implementation. Conducting a survey of existing facilities, process, equipment, operation, and maintenance is very important may be needed. The subject Energy Auditing is highly technical and it involves many engineering branches like Electrical, Mechanical, Chemical, etc. For an energy auditor, it is necessary that he should have complete knowledge of the system for which he is going to perform energy auditing. For example, in a process plant energy auditing. For example, in a process plant energy auditor will come across pumps, motors, fans and blowers and many other types of equipments. Besides this, a little background of finance is also needed.

  2. NEED OF AUDIT

    In energy audit is a survey and analysis of flow of energy. Auditing helps in reduction of energy bills improving the efficiency of energy consumption in the in hostel. This audit

    reduces the carbon footprint and helps to decrease unnecessary waste and pollution. This is very important to have a check on the energy saving and the devices consuming large amount of energy which can be replaced by the more efficient technologies.

  3. BENEFITS OF ENERGY AUDITING

In any industry, the three top operating expenses are often found to be energy (both electrical and thermal), labor and materials. If one were relate to the manageability of the cost or potential cost savings in each of the above components, energy would invariably emerge as a top ranker, and thus energy management function constitutes strategic area for cost reduction. Energy Audit will help to understand more about the ways energy and fuel used in any industry, and help in identifying where waste can occur and where scope for improvement exists. The Energy Audit would give a positive orientation to the energy cost reduction, preventive maintenance and quality control programs which are vital for production and utility activities. Such an audit program will help to keep focus on a variation which occur in the energy costs, availability and reliability of supply of energy, decide on appropriate energy mix, identify energy conservation technologies, retrofit for energy conservation equipment etc. In general, Energy Audit is the translation of conservation ideas into realities, by lending technically feasible solutions with economic and other organizational considerations within a specified time frame.

IV METHODOLOGY FOR ENERGY AUDIT

Structured methodology is helpful in carrying out the energy audit in a more efficient way. Methodology varies from one organization to another; however, the objectives of energy auditing should be fulfilled whatever methodology adopted should be known to the external auditor before hand, so that the energy auditor remains aware about the activities, He is supposed to do during the auditing phase. This can be discussed during bid discussion. Some of the steps for finalizing the methodology for preparation of single line diagram of electrical system.

The methodology adopted for this audit was a three step process comprising of:

  1. Data Collection: In preliminary data collection phase, exhaustive data collection was made using different methods such as observation, interviewing key persons, and measurements.

    Following steps were taken for data collection:

    • Visited each department, centre, laboratories, library, canteen, auditorium and other entities of the institution.

    • Information about the general electrical appliances was collected by observation and interviewing.

    • Obtained Site drawing of available building lay-out and Electricity distribution.

    • Collection of Electricity bill from the in-charge personnel.

    • The power consumption of appliances was measured using power analyzer in some cases (such as fans) while in other cases, rated power was used (CFL for example).

    • Information collected on redundant / non-operational energy systems

    • The details of usage of the appliances were collected by interviewing key persons e.g. Electrician, caretaker (in case of departments) etc.

    • Approximations and generalizations were done at places with lack of information.

  2. Data Analysis: Detailed analysis of data collected was done. Energy consumption per month in kWh is calculated based on each department and block-wise.

    The analysis of data is done in following way:

    • Power Flow diagram

    • Evaluation of collected data department wise analysis, block wise analysis and location wise analysis.

      Reasons for the Variance between connected load and actual consumption was evaluated.

    • The database prepared was further studied and the results have been graphically represented.

      This helped to identify the areas with maximum energy saving potential.

  3. Recommendation: On the basis of results of data analysis and observations, some steps for reducing power consumption were taken. The recommended measures will not affect the present working conditions and at the same time substantial energy savings will arise.

Following were the steps involved in this process:

  • The capital cost involved in replacing an appliance and/or process was estimated.

  • The energy saving by the move was calculated in terms of price of energy per year.

  • These two costs were compared to calculate the capital cost recovery time which is defined as the total time by which the saving in energy bill balances the capital cost involved.

  • If capital cost recovery time is less than the product life, the move can be supported.

Some other recommendations were also made which are based on lighting intensity, computer usage, fans and motion sensors.

  1. GOALS OF ENERGY AUDITING

    Generally goals of energy audit vary for different kinds of energy. The overall goals of energy auditing can be simplified as following:

    • Study of variation and improvement in power factor and load factors.

    • Clearly identifying the various types and costs of energy use.

    • Reduction in utility bills.

    • Also to understand how energy is possibly wasted.

    • Identify and analyze more cost-effective ways of consuming energy.

    The real power which is consumed by loads is mainly depend on power factor. Similarly improper employment of loads results in the wastage of energy hence a suggestive proposals are made to overcome the wastage.

    VI . POWER MONITORING KIT WITH SD CARD STORAGE AND WI-FI MODULE

    In this project, we used one power monitoring device. This device is used to calculate and store the energy consumption of one building in an hour, a day, a week, and a month. Through this device we can easily measure the energy utilization of one building or one room. So we can easily find the peak load timings and low load timings. By using that we made a chart of energy usage in a day and one week. In this project we calculate the boys hostel energy consumption. So, we fix the power monitoring and storing kit at the inlet power line of boys hostel. Before that we take the electrical equipments used in each room.

    Equipments used in north block:

    800

    700

    600

    500

    400

    300

    200

    100

    0

    Fan

    COMPONENTS

    LIGHT,CFL

    IRON BOX

    MOBILE AND LAPTOP CHARGER

    POWER

    Fig. 1 componenet usage

    (ii). POWER UTILIZATION IN ONE DAY (approx):

    Table. 1. ENERGY DATA BASE

    In new boys hostel (north block) there are three floors. Each floor has 20 rooms. Each room have one fan (70 W), two tube (fluorescent lamp) lights (40 W), one CFL (compact fluorescent lamp) lamps (11 W). Each floor 2 to 5 iron boxes and 60 mobile and 5 to 6 laptops are used.

    As per our project, first one week we fix the power

    1600

    1400

    Power usage

    1200

    1000

    800

    600

    400

    200

    0

    fan(16 hours)

    Light and CFL(TL-10 hrs,

    CFL-5 hrs) Iron box(2 hrs)

    mobile and laptop IroLnibgohxt (a2ndhrs) CFL(TL-10 hrs,

    CFL-5 hrs) fan(16 hours)

    monitoring and string device in inlet of the one room of boys hostel. Next we fix at the one floor. Next we fix one block. So, we can easily take the peak hours and energy saving locations.Through that we easily save the energy.

  2. CALCULATION OF ONE ROOM

We calculate approximately working hour. Because the accurate usage was measuring is impossible one.

(i). POWER USAGE IN ONE HOUR:

It is example of power usage in one working hour. But, in a day the mobile and laptop chargers are not used full time. These equipments and iron box are used some hours. So, we calculate approximate usage of power in one day.

4.30 PM to 8.30 AM

Timings

Fig. 2 power usage in one day

Fan =70 Watts*16 hrs =1120 w-h Tube Light =40 Watts*10 hrs =400 w-h CFL =11 Watts*5 hrs =55 w-h

Iron Box =750 watts*2 hrs =1500 w-h Mobile Charger=15 Watts*3hrs =135 w-h Laptop Charger=90 Watts*2 hrs =180 w-h

Total =3390 w-h Total Unit=3.39 units

One unit utilization cost is=6.35 Rs Cost of one day for single room=3.39*6.35

=21.52 Rs.

(iii). POWER USAGE IN A WEEK : EB-BIL COMPARISON OF TWO MONTHS:

1800

1600

1400

1200

1000

800

600

400

200

0

660000

640000

620000

EB-Bill

600000

580000

560000

540000

520000

651531

560852

500000

Jan-18

Feb-18

Light,CFL

mobiles and laptops

Fan

Iron box

Month

Fig. 3 power usage in a week

CALCULATIONS:

Energy usage in Monday =3.39 units Energy usage in Tuesday=3.39 units

Energy usage in Wednesday =3.39 units Energy usage in Thursday =3.39 units Energy usage in Friday =3.39 units

Energy usage in Saturday =3.39 units Energy usage in Sunday =3.95 units

Total energy in a week=24.29units Total cost in a week =154.24Rs. One having 20 floors=154.24*20 Ground floor cost =3084.83Rs

EB – BILL

Fig. 4 comparison of two months

VII.PROPOSING SYSTEM:

In existing system fans and lights are taking over power. Instead of using 70 Watts fan we change ES-40 Watts fan. Instead of using 40 Watts tube light we change 18 Watts LED tube light. Through that we achieve the energy saving.

80

60

North block Cost = 12339.32Rs

Floor lights =6*40 Watts

=240 Watts

=0.24unit*6.35Rs*7d

=10.668 W-H

Total Cost =12339.32+10.668

=12349.988 Rs.

40

20

0

Existing system

Proposing System

Fan Light

Fig. 5 comparison of equipment

Calculation for proposing system:

Fan =40 Watts*16 hrs =640 w-h Tube Light =18 Watts*10 hrs =180 w-h CFL =11 Watts*5 hrs =55 w-h

Iron Box =750 watts*2 hrs =1500 w-h Mobile Charger=15 Watts*3hrs =135 w-h Laptop Charger=90 Watts*2 hrs =180 w-h

Total =2690 w-h Total Unit=2.69 units

One unit utilization cost is=6.35 Rs Cost of one day for single room=2.69*6.35

=17.08 Rs.

WE SAVE 4.44Rs IN EACH DAY. WE SAVE 32.64Rs IN EACH WEEK.

WE SAVE 130.56Rs IN EACH MONTH.

  1. COST COMPARISION:

    Cost for a day

    25

    20

    Cost

    15

    Cost for a day

    10

    5

    0

    Existing Proposing

    Fig. 6. Cost for a day

    CALCULATION FOR LIGHT SYSTEM:

    40 Watts tube light energy in a day =40*10

    =320W-H

    18Watts tube light energy in a day =18*10

    =144W-H

    Saved energy =400-180

    =220 W-H

    Working hour in a day (approx) =8HRS

    IF WE APPLY THIS TYPE OF LED TUBE LIGHT MEANS,

    220watt-hour*323(10hrs) =71060 W-H One unit =1000 W-H

    One unit cost =6.35Rs LED Tube light cost = 448 Rs

    =70.55*6.35

    =448 RS

    323 DAYS ENOUGH TO TAKE THE PAYBACK AMOUNT

    AFTER 323 DAYS WE SAVE 1.397Rs EACH DAY THROUGH CHANGING LIGHT SYSTEM.

    By changing a Fan system we achieve high cost saving.

  2. CONCLUSION

    A famous quote Energy saved is Energy generated. This shows that apart from increasing the generation capacity at higher cost, one must go for the energy audit to save the electricity at much lower cost. Energy audit is a successful tool in identifying energy problems. By means of energy auditing the high power consuming equipments are identified and the sources of power loss can be detected. It identifies the poor quality equipment or the old equipment which causes energy losses. These problems can be limited by energy auditing and by means of this the energy bill can be reduced. By performing the cost-base analysis the energy consumption is analyzed effectively. Lighting loads in the institutions are considered as case studies and its reports before and after conducting energy audit are presented.

  3. REFERENCES

  1. M. S. Sujatha, Dr. Vijay Kumar, Under frequency load shedding for energy management using ANFIS / case study, International Journal Of Electrical Engineering and Technology, volume 4, issue2, Mar-Apr 2013, 93-104.

  2. Jian Zhang, Yuchen Zhang etc., How to reduce Energy Consumption by Energy Audits and Energy Management: The case of Province Jilin in China, IEEE, Technlogy Management in the Energy Smart World (PICMET), Jul-Aug, 2011, 1-5.

  3. Tarun B Patel, Ketan D Panchal, An Effective implementation of Energy Audit Methodology-A Case Study, IJAIEM, volume 4, issue3, March 2015, 260-268.

  4. Ali, A. Nazar. "Cascaded Multilevel Inverters for Reduce Harmonic Distortions in Solar PV Applications." Asian Journal of Research in Social Sciences and Humanities 6.Issue : 11 (2016): 703-715.

  5. Ali, A. Nazar. "A Single phase Five level Inverter for Grid Connected Photovoltaic System by employing PID Controller." African journal of Research 6.1 (2011): 306-315.

  6. ali, A.Nazar. "A SINGLE PHASE HIGH EFFICIENT RANSFORMERLESSINVERTER FOR PV GRID CONNECTED POWER SYSTEM USING ISPWM TECHNIQUE." International Journal of Applied Engineering Research 10.ISSN 0973-4562 (2015): 7489-7496.

  7. Ali, A. Nazar. "Performance Enhancement of Hybrid Wind/Photo Voltaic System Using Z Source Inverter with Cuk-sepic Fused Converter." Research Journal of Applied Sciences, Engineering and Technology 7.ISSN: 2040-7459; (2014): 3964-3970.

  8. Ali, A. Nazar. "Ride through Strategy for a Three-Level Dual Z- Source Inverter Using TRIAC." Scientific Research publication 7.ISSN Online: 2153-1293 (2016): 3911-3921.

  9. Ali, A. Nazar. "An ANFIS Based Advanced MPPT Control of a Wind-Solar Hybrid Power Generation System." International Review on Modelling and Simulations 7.ISSN 1974-9821 (2014): 638-643.

  10. Nazar Ali, A. "Performance Analysis of Switched Capacitor Multilevel DC/AC Inverter using Solar PV Cells." International Journal for Modern Trends in Science and Technology 3.05 (2017): 104-109.

[11]

Ali, A.Nazar. "FPGA UTILISATION FOR HIGH LEVELPOWER

[27]

Vikram, A. Arun, R. Navaneeth, M. Naresh Kumar, and R. Vinoth. "Solar

CONSUMPTION DRIVES BASEDONTHREE PHASE

PV Array Fed BLDC Motor Using Zeta Converter For Water Pumping

SINUSOIDAL PWM -VVVF CONTROLLER." International Journal

Applications." Journal of Science and Technology (JST) 2, no. 11 (2017):

of Communications and Engineering 4.Issue: 02 (2012): 25-30.

09-20.

[12]

ali, A.Nazar. "A SINGLE PHASE HIGH EFFICIENT

[28]

Nagarajan, L. Star Delta Starter using Soft Switch for Low Power Three

TRANSFORMERLESS INVERTER FOR PV GRID CONNECTED

Phase Induction Motors. Australian Journal of Basic and Applied

POWER SYSTEM USING ISPWM TECHNIQUE." International

Sciences, 9(21), 175-178.

Journal of Applied Engineering Research 10.ISSN 0973-4562 (2015):

[29]

Vinusha, S., & Nagarajan, L. (2015). CURRENT SOURCE INVERTER

7489-7496.

FED INDUCTION MOTOR DRIVE USING MULTICELL

[13]

JAIGANESH, R. "Smart Grid System for Water Pumping and

CONVERTER WITH ANFIS CONTROL.

Domestic Application using Arduino Controller." International

[30]

Nagarajan, L., & Nandhini, S. (2015). AN EFFICIENT

Journal of Engineering Research & Technology (IJERT) 5.13 (2017):

SOLAR/WIND/BATTERY HYBRID SYSTEM WITH HIGH POWER

583-588.

CONVERTER USING PSO.

[14]

Pau1l, M. Mano Raja, R. Mahalakshmi, M. Karuppasamypandiyan,

[31]

Subramanian, AT Sankara, P. Sabarish, and R. Jai Ganesh. "An Improved

A. Bhuvanesh, and R. Jai Ganesh."Classification and Detection of

Voltage follower Canonical Switching Cell Converter with PFC for VSI

Faults in Grid Connected Photovoltaic System."

Fed BLDC Motor." Journal of Science and Technology (JST) 2.10 (2017):

[15]

Ganesh, Rajendran Jai, et al. "Fault Identification and Islanding in DC

01-11.

Grid Connected PV System." Scientific Research Publishing

[32]

Compensator, D. S. (2015). AN ADAPTIVE CONTROL AND

7.Circuits and Systems, 7, 2904-2915. (2016): 2904-2915.

IMPROVEMENT OF POWER QUALITY IN GRID CONNECTED

[16]

Jaiganesh, R., et al. "Smart Grid System for Water Pumping and

SYSTEM USING POWER ELECTRONIC CONVERTERS.

Domestic Application Using Arduino Controller." International Journal for Modern Trends in Science and Technology 3.05 (2017):

[33]

Sabarish, P., Sneha, R., Vijayalakshmi, G., & Nikethan, D. (2017). Performance Analysis of PV-Based Boost Converter using PI Controller

385-390.

  1. Kalavalli,C., et al. Single Phase Bidirectional PWM Converter for Microgrid System. International Journal of Engineering and Technology (IJET) ISSN : 0975-4024 Vol 5 No 3 Jun-Jul 2013.

  2. Lilly Renuka, R., et al. Power Quality Enhancement Using VSI Based STATCOM for SEIG Feeding Non Linear Loads. International Journal of Engineering and Applied Sciences (IJEAS) ISSN: 2394-3661, Volume-2, Issue-5, May 2015.

  3. Karthikeyan,B. JEBASALMA. RESONANT PWM ZVZCS DC TO DC CONVERTERS FOR RENEWABLE ENERGY APPLICATIONS .International Journal of Power Control and Computation(IJPCSC)Vol 6. No.2 Jan-March 2014 Pp. 82- 89©gopalax Journals, Singaporeavailable at :www.ijcns.comISSN: 0976-268X.

  4. Gowri,N, et al. Power Factor Correction Based BridgelessSingle Switch SEPIC Converter Fed BLDC

  5. Motor.ADVANCES in NATURAL and APPLIED SCIENCES. ISSN: 1995-0772 AENSI PublicationEISSN: 1998-1090 http://www.aensiweb.com/ANAS2016 March 10(3): pages 190-197.

  6. Ramkumar,R., et al. A Novel Low Cost Three Arm Ac AutomaticVoltage Regulator ADVANCES in NATURAL and APPLIED SCIENCESISSN: 1995-0772 AENSI PublicationEISSN: 1998-1090 http://www.aensiweb.com/ANAS2016 March 10(3): pages 142-151.

  7. Kodeeswaran, S., T. Ramkumar, and R. Jai Ganesh. "Precise temperature control using reverse seebeck effect." In Power and Embedded Drive Control (ICPEDC), 2017 International Conference on, pp. 398-404. IEEE, 2017.

  8. Subramanian, AT Sankara, P. Sabarish, and R. Jai Ganesh. "An Improved Voltage follower Canonical Switching Cell Converter with PFC for VSI Fed BLDC Motor." Journal of Science and Technology (JST) 2, no. 10 (2017): 01-11.

  9. Murugesan.S, R. Senthilkumar."DESIGN OF SINGLE PHASE SEVEN LEVEL PV INVERTER USING FPGA."International Journal of Emerging Technology in Computer Science & Electronics, 2016, Vol.20, No.2, pp.207-2012.

  10. S. Murugesan, C. Kalavalli, " FPGA Based Multilevel Inverter With Reduce Number of Switches For Photovoltaic System", International Journal of Scientific Research in Science, Engineering and Technology(IJSRSET), Print ISSN : 2395-1990, Online ISSN : 2394- 4099, Volume 3 Issue 6, pp.628-634, September-October 2017.

with PSO Algorithm. Journal of Science and Technology (JST), 2(10), 17- 24.

  1. T.Vishnu Kumar, V. Suresh Kumar, T. Sumeet, M.Srimaha Hybrid Front end Interface DC-DC Converter with ANFIS Based Control of EMS System. International Journal of ScientificResearch in Science and Technology, Volume 3, Issue 8, Print ISSN: 2395-6011, 2017.

  2. T. Vishnu kumar, V. Suresh Kumar, A new approach to front end interface DC-DC converter International Journal of Multidisciplinary Research and Modern Education (IJMRME) ISSN(online): 2454-6119 Volume I, Issue II, 2015

  3. V.Suresh kumar, T. Vishnu kumar, A certain investigation for the battery charging system International Journal of Multidisciplinary Research and Modern Education (IJMRME) ISSN(online): 2454-6119 Vol.1 Issue.1 2015.

  4. S.Enimai, S.Jayanthi, T.Vishnu kumar Isolated Power System Design Using Modified P&O Technique Middle-East Journal of Scientific Research 24 (S2): 150-156, 2016, ISSN 1990-9233