Monitoring System For Project Cost Control In Construction Industry

DOI : 10.17577/IJERTV3IS071388

Download Full-Text PDF Cite this Publication

Text Only Version

Monitoring System For Project Cost Control In Construction Industry

,

Pramod M* K. Phaniraj**, V. Srinivasan***

*Post graduate student: Construction Engineering and Management, Manipal Institute of Technology, Manipal, Karnataka-567104

**Associate Professor: Civil engineering department, Manipal institute of technology, Manipal, Karnataka-567104

*** Visiting Professor: Civil engineering department, Gopalan College of Engineering, Bangalore, Karnataka

Abstract Effective cost monitoring and controlling has gained much attention in the construction industry due to excessive cost escalation, project delays and underperformance. The absence of a well-established effective system for monitoring and controlling project cost is the main reason for cost escalation and delays in the project. This necessitates implementation of a monitoring system in a construction project and to adopt the most effective one out of all the known systems. This study considers Earned Value analysis and Earned Schedule concept as the two monitoring systems which can be used to monitor a construction project.

Keywordsmonitoring systems; Earned Value; Earned Schedule; (key words)

  1. INTRODUCTION

    In a project, plans are usually drawn to ensure that work is carried out to the desired quality; in the allowed time; and according to budget. However, in a construction project, divergences are bound to happen and are common. Such divergences are nevertheless expected because of the nature of construction work and the uncertainties associated with it. In the case where the dierences between the plan and the actual work performance are large, control action is normally required to try to bring the actual performance on course with the desired state of the plan.

    Progress on the project is required to be monitored and compared as the work proceeds in order to be able to identify and measure these dierences. There are a number of systems that are traditionally used in construction to monitor and report on the progress of the work. But there is no certainty as to which of these monitoring system is the best to be implied for a construction project. The effectiveness of the monitoring system in showing deviations of project performances varies considerably from one system to another.

  2. LITERATURE REVIEW

    1. Earned Value Analysis

      Earned Value analysis is a method of measuring performance. Earned Value is a program management technique that uses work in progress to indicate what will happen to work in the future (Bhosekar & Vyas, 2012). Earned Value is an enhancement over conventional accounting methods. Conventional approaches focus on planned expenditure and actual costs. Whereas Earned Value goes one step further and examines actual completion. This gives managers better understanding of probable risk areas. Hence with stronger picture, managers can create risk mitigation plans based on actual cost, schedule and actual development of the work

      Earned value formula and interpretations

      are:

      Monitoring systems that we consider in this study

      NAME

      FORMULA

      INTERPRETATION

      Cost Variance (CV)

      EV AC

      Negative is over budget Positive is under budget

      Scheduled Variance (SV)

      EV PV

      Negative is behind schedule Positive is ahead of schedule

      Cost Performanc e Index (CPI)

      EV / AC

      I am [only] getting paisa out of every rupee

      Schedule Performanc e Index (SPI)

      EV / PV

      I am [only] progressing at % of the rate originally planned

      • Earned value analysis.

      • Earned schedule.

        Estimate At Completion (EAC)

        BAC / CPI

        AC + ETC CPI

        As of now how much do we expect the total project to cost

        AC + BAC – EV

        AC + (BAC EV) / CPI

        Estimate To Completion (ETC)

        EAC AC

        How much more will the project cost?

        Time estimate at completion (EAC)t

        (BAC / SPI) /

        (BAC / months)

        How much time will the project need?

        Variance At Completion (VAC)

        BAC – EAC

        How much over budget will we be at the end of the project?

        Schedule performance index: it gives an idea about how much work is completed with respect to the work planned in terms of time.

        Schedule performance index: SPI(t) = ES/AT

        • Time Estimate At Completion: as the name suggests it gives the estimated time of the project at completion

      EAC t = AT + ( PD ES) / SPI t

    2. Earned Schedule Analysis

    For more than 30 years earned value management has been providing valuable insight into project cost and schedule status during project execution. A study of more than 700 completed major programs over three decades has shown that earned value provides insight into the project health when as little as 15 percent of the work is complete. However, while traditional earned value management did an excellent job of estimating the final cost of the project, it failed to do the same for estimating the finish date. Lately, new work in the application of earned value management principles has created novel approaches to obtain Schedule information from the application of earned value management, and have resulted in means to predict the project completion date (Stratton, 2007).

    According to Stratton (2007), the concept of Earned Schedule corrects the fundamental weakness of the classical EVM concept and proposes the schedule performance indicators which are time and not cost-based.

    Earned Schedule terms and formulae

    • Earned schedule: The value of ES is equal to the cumulative time to the beginning of that increments plus a fraction of it. The fractional amount is equal to the portion of EV extending into the incomplete time increment divided by the total PV planned for that same time period.

    Earned Schedule: ES = C + I

    Where, C = number of time increments where EV >=PV I = (EV – PVc) / (PVc+1 PVc)

    Schedule variance: it is the time difference between the actual time elapsed or taken to complete the work and the earned schedule. In other words the schedule variance gives the real delay for a given point of time.

    Schedule variance: SV(t) = ES AT

  3. RESEARCH METHODOLOGY

    From the literature review it is evident that the most practiced monitoring system is the Earned Value Management (EVM) analysis. It is also known that EVM indicators related to schedule which are schedule variance and schedule performance index are flawed and misleading towards the end of the project.

    And by the introduction of Earned Schedule concept and the studies undergone, it is definitely one of the better practice to monitor a project. Hence in this project we will be considering Earned Value Analysis and Earned Schedule Analysis for research purpose.

    1. Research process

      • Data collection from schedule and monthly reports

      • Using Primavera to find out Earned Value terms.

      • Using spreadsheet to find out Earned schedule terms.

      • Compare the results of Earned Value and Earned Scheule analysis

      • Do the above process for an ongoing project and completed project.

    2. Research data

      The required data for the study is of a residential apartment situated in Bangalore. The apartment has four blocks which has similar plan and each block consists of 13 floors. One set of data is from Block 1 which has already been completed with total project duration of 19 months and the next set of data is from block 4 which is in progress at present.

    3. Research Method

    The data collected is fed into primavera, through scheduling and progress tracking the Planned Value, Earned Value and Actual Cost for each month are obtained. The illustration of this can be found in the annexure.

    Earned Value and Earned Schedule analysis is carried out in the spreadsheet from results obtained from Primavera and results are tabulated and compared. The same method is done for the second set of data.

  4. DATA ANALYSIS AND RESULTS

    1. Ongoing project

      Budget At Completion = INR 9,45,95,950.00 Planned Project Duration = 27 months

      month

      cumulative planned value

      cumulative earned value

      cumulative ac

      cost

      may

      0.00

      0.00

      june

      79,650.00

      73,650.00

      73,65

      july

      24,25,238.27

      22,50,325.68

      22,50,32

      august

      48,68,500.00

      50,55,650.00

      50,56,42

      september

      70,67,123.56

      69,96,750.29

      70,39,40

      october

      97,07,300.00

      97,11,350.00

      97,67,27

      november

      131,88,597.08

      126,90,422.22

      127,85,84

      december

      166,36,283.33

      147,55,813.63

      148,70,15

      january

      199,65,820.61

      193,34,064.91

      194,71,32

      february

      223,04,147.62

      216,28,211.44

      217,73,39

      march

      265,06,117.66

      250,77,052.94

      252,37,67

      april

      292,15,518.96

      284,13,190.93

      286,17,45

      may

      334,67,054.42

      324,56,275.00

      327,18,60

      SPI

      SPIt

      Table 1: CV, PV and AC values in INR

      SV vs SVt

      0.2

      5,00,000.00

      0.1

      -0.4

      -15,00,000.00

      -0.5

      -0.6

      MONTHS

      -20,00,000.00

      SCHEDULE VARIANCE(SV)

      SCHEDULE VARIANCE[SV(t)]

      1.04

      1.02

      1.00

      0.98

      0.96

      0.94

      0.92

      0.90

      0.88

      0.86

      1.05

      1.00

      0.95

      0.90

      0.85

      0.80

      -10,00,000.00

      -0.2

      -0.3

      -5,00,000.00

      0

      -0.1

      0.00

      MONTHS

      COST

      Figure 1: SV vs SVt

      SPI vs SPIt

      months

      SCHEDULE PERFORMANCE INDEX [SPI(t)]

      SCHEDULE PERFORMACE INDEX(SPI)

      month

      SCHEDULE VARIANCE(SV)

      SCHEDULE PERFORMACE

      INDEX(SPI)

      ESTIMATE AT COMPLETION

      (EACt)

      may

      0.00

      0

      2

      june

      -6000.00

      0.924670433

      2

      july

      -174912.59

      0.927878183

      2

      august

      187150.00

      1.038440998

      27.0041537

      september

      -70373.27

      0.990042162

      27.1646050

      october

      4050.00

      1.000417212

      27.1554855

      november

      -498174.86

      0.96222685

      27.2030192

      december

      -1880469.70

      0.886965757

      27.2092112

      january

      -631755.70

      0.96835814

      27.1916808

      february

      -675936.18

      0.969694597

      27.1812480

      march

      -1429064.72

      0.946085476

      27.1729357

      april

      -802328.03

      0.972537608

      27.1941047

      may

      -1010779.42

      0.969797778

      27.2182251

      Figure 2: SPI vs SPIt

    2. Completed project

      Table 2: EV parameters

      Table 3: ES parameters

      Budget At Completion = INR 8,35,75,650 Project duration = 20 months

      month

      cumulative

      planned value

      cumulative

      earned value

      cumulative

      actual cost

      october

      1022871.44

      936278.09

      940023.2

      november

      2856985.74

      2720058.98

      2738484.5

      december

      5572885.76

      5380615.44

      5429082.47

      january

      9346928.65

      9092712.65

      9177675.09

      february

      13650042.97

      13326315.61

      13444966.12

      march

      19258200.16

      18771926.22

      18927072.14

      april

      25677600.16

      25168628.61

      25360131.23

      may

      32097000.16

      31514929.85

      31738051.71

      june

      38269500.16

      37651532.44

      37893946.63

      july

      44688900.16

      44056335.76

      44305887.65

      august

      51355200.16

      50790958.47

      51049055.86

      september

      57280800.16

      56908767.34

      57180854.93

      october

      63718541.30

      63414691.77

      63712953.61

      november

      69247337.72

      68703173.98

      69025671.24

      december

      73894348.42

      73467909.27

      73814641.95

      january

      77915643.97

      77457207.62

      77829325.05

      february

      80635776.51

      80171750.29

      80563484.48

      march

      82659651.04

      82360301.79

      82769119.09

      april

      83575649.99

      83575649.99

      83995380

      month

      SCHEDULE VARIANCE[SV(t)]

      SCHEDULE PERFORMANCE

      INDEX [SPI(t)]

      ESTIMATE AT COMPLETION

      (EACt)

      may

      0

      0

      27

      june

      -0.075329567

      0.924670433

      29.19959267

      july

      -0.074570884

      0.962714558

      28.04569617

      august

      0.076598425

      1.025532808

      26.32777789

      september

      -0.032007876

      0.991998031

      27.21779596

      october

      0.001533988

      1.000306798

      26.991719

      november

      -0.143100358

      0.97614994

      27.65968514

      december

      -0.545429475

      0.922081504

      29.2815764

      january

      -0.189742792

      0.976282151

      27.65593939

      february

      -0.289068286

      0.967881302

      27.89598265

      march

      -0.340093981

      0.965990602

      27.95058249

      april

      -0.296127425

      0.973079325

      27.74696708

      may

      -0.237744558

      0.980187953

      27.54573743

      Table 4: PV, EV and AC

      SPI vs SPIt

      1.02 1.02

      1.00

      1

      0.98

      0.98

      0.96

      0.96

      0.94 0.94

      0.92 0.92

      0.90 0.9

      0.88 0.88

      0.86

      0.86

      MONTHS

      SCHEDULE PERFORMANCE INDEX(SPI)

      SCHEDULE PERFORMANCE INDEX [SPI(t)]

      SPI

      SPIt

      month

      SCHEDULE VARIANCE(SV)

      SCHEDULE PERFORMANCE

      INDEX(SPI)

      ESTIMATE AT COMPLETION (EACt)

      october

      -86593.35

      0.91534288

      19.07599995

      november

      -136926.76

      0.952072998

      19.12870489

      december

      -192270.32

      0.965498966

      19.17114651

      january

      -254216

      0.972802189

      19.17753628

      february

      -323727.36

      0.976283785

      19.16916601

      march

      -486273.94

      0.974749772

      19.1570309

      april

      -508971.55

      0.980178383

      19.14456687

      may

      -582070.31

      0.981865274

      19.13451768

      june

      -617967.72

      0.983852213

      19.12232888

      july

      -632564.4

      0.985845156

      19.10762325

      august

      -564241.69

      0.989012959

      19.09654967

      september

      -372032.82

      0.993505104

      19.09084126

      october

      -303849.53

      0.99523138

      19.08936375

      november

      -544163.74

      0.992141738

      19.08918726

      december

      -426439.15

      0.994229069

      19.08967073

      january

      -458436.35

      0.994116248

      19.09127919

      february

      -464026.22

      0.994245405

      19.09283756

      march

      -299349.25

      0.996378532

      19.09431156

      april

      0

      1

      19.09542098

      Figure 4: SPI vs SPIt

    3. Results

    Table 5: EV parameters

    october november december january february march april

    may june july august

    september october november december january february march april

    Table 6: ES parameters

    MONTHS

    Figure 3: SV vs SVt

    From the results obtained from the ongoing project, the Earned value analysis suggests that the EV at the end of 12 months is INR 3,24,56,275 for a PV of INR 3,34,67,054.42 which has an AC of INR 3,27,18,600

    month

    SCHEDULE VARIANCE[SV(t)]

    SCHEDULE PERFORMANCE

    INDEX [SPI(t)]

    ESTIMATE AT COMPLETION

    (EACt)

    october

    -0.08465712

    0.91534288

    20.75724891

    november

    -0.074655522

    0.962672239

    19.73672786

    december

    -0.070794329

    0.97640189

    19.45920034

    january

    -0.067359065

    0.983160234

    19.32543582

    february

    -0.075230946

    0.984953811

    19.29024467

    march

    -0.086708329

    0.985548612

    19.27860257

    april

    -0.079286468

    0.988673362

    19.21767161

    may

    -0.090673631

    0.988665796

    19.21781868

    june

    -0.100116277

    0.988875969

    19.21373417

    july

    -0.09853949

    0.990146051

    19.1890883

    august

    -0.084640909

    0.992305372

    19.1473316

    september

    -0.062783991

    0.994768001

    19.09993082

    october

    -0.047198159

    0.996369372

    19.06923328

    november

    -0.098423544

    0.992969747

    19.13452052

    december

    -0.091766337

    0.993882244

    19.11695285

    january

    -0.114002153

    0.992874865

    19.13634906

    february

    -0.170589563

    0.98996532

    19.19259152

    march

    -0.147908996

    0.991782834

    19.15741971

    april

    0

    1

    19

    which implies that the project is behind schedule by INR

    10.11 lakhs (SV). It is sometimes confusing to say that a project is behind schedule in terms of money. And hence we have used Earned Schedule analysis to find the actual delay of the project. According to ES analysis the ES value at the end of 12 months is 11.7623 months. Which means we have accomplished only 11.7623 months of work in 12 months. It also suggests we are behind schedule by 0.2377 months (SVt). Further when we compare the schedule variances and the schedule indices of EV and ES analysis (figure 12 & figure 13) it was observed that the parameters from EV analysis follow the same trend as of the ES analysis till January, from January till May the EV parameters deviate a bit.

    SV vs SVt

    MONTHS

    0 0.00

    -0.02 -100000.00

    -0.04

    -200000.00

    -0.06

    -0.08 -300000.00

    -0.1 -400000.00

    -0.12

    -500000.00

    -0.14

    -0.16 -600000.00

    -0.18 -700000.00

    SCHEDULE VARIANCE[SV(t)] SCHEDULE VARIANCE(SV)

    COST

    From the results obtained from the completed project, the Earned value analysis suggests that the EV at the end of 12 months is INR 8,35,75,649.99 for a PV of INR 8,35,75,649.99 which has an AC of INR 8,39,95,380.00 which implies that the project has been completed as the EV and PV value are the same. But the CV of the project is INR 4.2 lakhs. Further when the EV parameters SV and SPI were compare to the ES parameters SVt and SPIt, it was observed that the EV parameters follow similar trend with ES parameters throughout the project duration. But the EACt values derived from EV analysis says the project would complete in 19.1 months where as we already know that the project has been completed in 19 months

  5. CONCLUSIONS AND RECOMMENDATIONS

  1. Conclusions:

    This study has helped us to find out the behaviour of Earned Value Analysis and the Earned Schedule Analysis parameters on two projects, one being completed and one in progress.

    From the ongoing project it was seen that the EVA schedule parameters were flawed towards the later stages and deviated from the actuals and the ES parameters gave us appropriate data regarding the actual delay of the project.

    From the completed project it was observed that both the EVA and ES parameters seemed to follow same trend, however the EACt value derived from EVA seem to be inaccurate. And once again the ES parameters gave us the actuals of the project without any problem.

    Hence here are the conclusions of this study,

    • Earned Value Analysis is a great monitoring system for project cost control when the required information are cost oriented.

    • Earned Value Analysis parameters seem to deviate from actuals in later stages of the project.

    • Earned Schedule Analysis gives us more accurate results in terms of time.

  2. Recommendations:

When we want to establish a monitoring system which could help us control cost, we need to consider a system which could give us accurate results both in terms of cost and time. Since Earned Schedule Analysis uses the EVM data to find the Schedule Variances in terms of time, we still need to use the Earned Value analysis to acquire the cost details. Hence we need to use both the systems for effective monitoring of the project.

Further studies may be conducted on other projects such as early finish projects and late finish projects to see if the system is capable of finding accurate results. It would be beneficial if the Earned Schedule concept is integrated into the Earned Value Analysis so that the results acquired from the system is accurate both in terms of cost and time.

REFERENCES

  1. Abba, W., 1997. Earned Value Management: reconnciling government and commercial practices. Program Manager, Issue 26, pp. 58-67.

  2. Al-Jibouri, S. H., 2003. Monitoring Systems And Their Effectiveness For Project Cost Control In Construction. international journal of project management 21, pp. 145-154

  3. Anbari, F. T., 2003. Earned Value Project Management Methods and Extensions. Project Management Journal, Issue 34, pp. 12-23.

  4. Bhosekar, S. K. & Vyas, G., 2012. Cost Controlling Using Earned Value Analysis In Construction Industries. International Journal of Engineering and Innovative Technology, 1(4).

  5. Christensen, D. S., 1998. The Costs and Benefits of the Earned Value Management Process. Acquisition Review Quarterly .

  6. Cleland, D. I. & Ireland, L. R., 2002. Project Management (Strategic Design and Implementation). 4th ed. London: McGraw Hill, Inc.

  7. Cooke, B. & William, P., 2004. Construction Planning, Programming and Control. s.l.:blackwell publishing Ltd.

  8. Henderson, K., 2004. Earned Schedule: A Breakthrough Extension to Earned Value Theory?. A Retrospective Analysis of Real Project Data.

  9. Lipke, W., 2011. Earned Schedule – Schedule performance analysis from EVM measures. PM World Today, january .XIII(I).

  10. Lipke, W., 2011. Further Study of the Normality of CPI and SPI(t). PM World Today, XIII(X).

  11. Locke, B., 2008. A Neat Solution for the EVM schedule Problem.

    Project Management Journal, Issue 38.

  12. Stratton, R. W., 2007. Applying Earned Schedule Analysis to EVM data for Estimatinfg Completion date. AACE International Transactions EVM.04.

Leave a Reply