- Open Access
- Total Downloads : 1089
- Authors : Pramod M , K. Phaniraj, V. Srinivasan
- Paper ID : IJERTV3IS071388
- Volume & Issue : Volume 03, Issue 07 (July 2014)
- Published (First Online): 29-07-2014
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Monitoring System For Project Cost Control In Construction Industry
,
Pramod M* K. Phaniraj**, V. Srinivasan***
*Post graduate student: Construction Engineering and Management, Manipal Institute of Technology, Manipal, Karnataka-567104
**Associate Professor: Civil engineering department, Manipal institute of technology, Manipal, Karnataka-567104
*** Visiting Professor: Civil engineering department, Gopalan College of Engineering, Bangalore, Karnataka
Abstract Effective cost monitoring and controlling has gained much attention in the construction industry due to excessive cost escalation, project delays and underperformance. The absence of a well-established effective system for monitoring and controlling project cost is the main reason for cost escalation and delays in the project. This necessitates implementation of a monitoring system in a construction project and to adopt the most effective one out of all the known systems. This study considers Earned Value analysis and Earned Schedule concept as the two monitoring systems which can be used to monitor a construction project.
Keywordsmonitoring systems; Earned Value; Earned Schedule; (key words)
-
INTRODUCTION
In a project, plans are usually drawn to ensure that work is carried out to the desired quality; in the allowed time; and according to budget. However, in a construction project, divergences are bound to happen and are common. Such divergences are nevertheless expected because of the nature of construction work and the uncertainties associated with it. In the case where the dierences between the plan and the actual work performance are large, control action is normally required to try to bring the actual performance on course with the desired state of the plan.
Progress on the project is required to be monitored and compared as the work proceeds in order to be able to identify and measure these dierences. There are a number of systems that are traditionally used in construction to monitor and report on the progress of the work. But there is no certainty as to which of these monitoring system is the best to be implied for a construction project. The effectiveness of the monitoring system in showing deviations of project performances varies considerably from one system to another.
-
LITERATURE REVIEW
-
Earned Value Analysis
Earned Value analysis is a method of measuring performance. Earned Value is a program management technique that uses work in progress to indicate what will happen to work in the future (Bhosekar & Vyas, 2012). Earned Value is an enhancement over conventional accounting methods. Conventional approaches focus on planned expenditure and actual costs. Whereas Earned Value goes one step further and examines actual completion. This gives managers better understanding of probable risk areas. Hence with stronger picture, managers can create risk mitigation plans based on actual cost, schedule and actual development of the work
Earned value formula and interpretations
are:
Monitoring systems that we consider in this study
NAME
FORMULA
INTERPRETATION
Cost Variance (CV)
EV AC
Negative is over budget Positive is under budget
Scheduled Variance (SV)
EV PV
Negative is behind schedule Positive is ahead of schedule
Cost Performanc e Index (CPI)
EV / AC
I am [only] getting paisa out of every rupee
Schedule Performanc e Index (SPI)
EV / PV
I am [only] progressing at % of the rate originally planned
-
Earned value analysis.
-
Earned schedule.
Estimate At Completion (EAC)
BAC / CPI
AC + ETC CPI
As of now how much do we expect the total project to cost
AC + BAC – EV
AC + (BAC EV) / CPI
Estimate To Completion (ETC)
EAC AC
How much more will the project cost?
Time estimate at completion (EAC)t
(BAC / SPI) /
(BAC / months)
How much time will the project need?
Variance At Completion (VAC)
BAC – EAC
How much over budget will we be at the end of the project?
Schedule performance index: it gives an idea about how much work is completed with respect to the work planned in terms of time.
Schedule performance index: SPI(t) = ES/AT
-
Time Estimate At Completion: as the name suggests it gives the estimated time of the project at completion
-
EAC t = AT + ( PD ES) / SPI t
-
-
Earned Schedule Analysis
For more than 30 years earned value management has been providing valuable insight into project cost and schedule status during project execution. A study of more than 700 completed major programs over three decades has shown that earned value provides insight into the project health when as little as 15 percent of the work is complete. However, while traditional earned value management did an excellent job of estimating the final cost of the project, it failed to do the same for estimating the finish date. Lately, new work in the application of earned value management principles has created novel approaches to obtain Schedule information from the application of earned value management, and have resulted in means to predict the project completion date (Stratton, 2007).
According to Stratton (2007), the concept of Earned Schedule corrects the fundamental weakness of the classical EVM concept and proposes the schedule performance indicators which are time and not cost-based.
Earned Schedule terms and formulae
-
Earned schedule: The value of ES is equal to the cumulative time to the beginning of that increments plus a fraction of it. The fractional amount is equal to the portion of EV extending into the incomplete time increment divided by the total PV planned for that same time period.
Earned Schedule: ES = C + I
Where, C = number of time increments where EV >=PV I = (EV – PVc) / (PVc+1 PVc)
Schedule variance: it is the time difference between the actual time elapsed or taken to complete the work and the earned schedule. In other words the schedule variance gives the real delay for a given point of time.
Schedule variance: SV(t) = ES AT
-
-
RESEARCH METHODOLOGY
From the literature review it is evident that the most practiced monitoring system is the Earned Value Management (EVM) analysis. It is also known that EVM indicators related to schedule which are schedule variance and schedule performance index are flawed and misleading towards the end of the project.
And by the introduction of Earned Schedule concept and the studies undergone, it is definitely one of the better practice to monitor a project. Hence in this project we will be considering Earned Value Analysis and Earned Schedule Analysis for research purpose.
-
Research process
-
Data collection from schedule and monthly reports
-
Using Primavera to find out Earned Value terms.
-
Using spreadsheet to find out Earned schedule terms.
-
Compare the results of Earned Value and Earned Scheule analysis
-
Do the above process for an ongoing project and completed project.
-
-
Research data
The required data for the study is of a residential apartment situated in Bangalore. The apartment has four blocks which has similar plan and each block consists of 13 floors. One set of data is from Block 1 which has already been completed with total project duration of 19 months and the next set of data is from block 4 which is in progress at present.
-
Research Method
The data collected is fed into primavera, through scheduling and progress tracking the Planned Value, Earned Value and Actual Cost for each month are obtained. The illustration of this can be found in the annexure.
Earned Value and Earned Schedule analysis is carried out in the spreadsheet from results obtained from Primavera and results are tabulated and compared. The same method is done for the second set of data.
-
-
DATA ANALYSIS AND RESULTS
-
Ongoing project
Budget At Completion = INR 9,45,95,950.00 Planned Project Duration = 27 months
month
cumulative planned value
cumulative earned value
cumulative ac
cost
may
0.00
0.00
june
79,650.00
73,650.00
73,65
july
24,25,238.27
22,50,325.68
22,50,32
august
48,68,500.00
50,55,650.00
50,56,42
september
70,67,123.56
69,96,750.29
70,39,40
october
97,07,300.00
97,11,350.00
97,67,27
november
131,88,597.08
126,90,422.22
127,85,84
december
166,36,283.33
147,55,813.63
148,70,15
january
199,65,820.61
193,34,064.91
194,71,32
february
223,04,147.62
216,28,211.44
217,73,39
march
265,06,117.66
250,77,052.94
252,37,67
april
292,15,518.96
284,13,190.93
286,17,45
may
334,67,054.42
324,56,275.00
327,18,60
SPI
SPIt
Table 1: CV, PV and AC values in INR
SV vs SVt
0.2
5,00,000.00
0.1
-0.4
-15,00,000.00
-0.5
-0.6
MONTHS
-20,00,000.00
SCHEDULE VARIANCE(SV)
SCHEDULE VARIANCE[SV(t)]
1.04
1.02
1.00
0.98
0.96
0.94
0.92
0.90
0.88
0.86
1.05
1.00
0.95
0.90
0.85
0.80
-10,00,000.00
-0.2
-0.3
-5,00,000.00
0
-0.1
0.00
MONTHS
COST
Figure 1: SV vs SVt
SPI vs SPIt
months
SCHEDULE PERFORMANCE INDEX [SPI(t)]
SCHEDULE PERFORMACE INDEX(SPI)
month
SCHEDULE VARIANCE(SV)
SCHEDULE PERFORMACE
INDEX(SPI)
ESTIMATE AT COMPLETION
(EACt)
may
0.00
0
2
june
-6000.00
0.924670433
2
july
-174912.59
0.927878183
2
august
187150.00
1.038440998
27.0041537
september
-70373.27
0.990042162
27.1646050
october
4050.00
1.000417212
27.1554855
november
-498174.86
0.96222685
27.2030192
december
-1880469.70
0.886965757
27.2092112
january
-631755.70
0.96835814
27.1916808
february
-675936.18
0.969694597
27.1812480
march
-1429064.72
0.946085476
27.1729357
april
-802328.03
0.972537608
27.1941047
may
-1010779.42
0.969797778
27.2182251
Figure 2: SPI vs SPIt
-
Completed project
Table 2: EV parameters
Table 3: ES parameters
Budget At Completion = INR 8,35,75,650 Project duration = 20 months
month
cumulative
planned value
cumulative
earned value
cumulative
actual cost
october
1022871.44
936278.09
940023.2
november
2856985.74
2720058.98
2738484.5
december
5572885.76
5380615.44
5429082.47
january
9346928.65
9092712.65
9177675.09
february
13650042.97
13326315.61
13444966.12
march
19258200.16
18771926.22
18927072.14
april
25677600.16
25168628.61
25360131.23
may
32097000.16
31514929.85
31738051.71
june
38269500.16
37651532.44
37893946.63
july
44688900.16
44056335.76
44305887.65
august
51355200.16
50790958.47
51049055.86
september
57280800.16
56908767.34
57180854.93
october
63718541.30
63414691.77
63712953.61
november
69247337.72
68703173.98
69025671.24
december
73894348.42
73467909.27
73814641.95
january
77915643.97
77457207.62
77829325.05
february
80635776.51
80171750.29
80563484.48
march
82659651.04
82360301.79
82769119.09
april
83575649.99
83575649.99
83995380
month
SCHEDULE VARIANCE[SV(t)]
SCHEDULE PERFORMANCE
INDEX [SPI(t)]
ESTIMATE AT COMPLETION
(EACt)
may
0
0
27
june
-0.075329567
0.924670433
29.19959267
july
-0.074570884
0.962714558
28.04569617
august
0.076598425
1.025532808
26.32777789
september
-0.032007876
0.991998031
27.21779596
october
0.001533988
1.000306798
26.991719
november
-0.143100358
0.97614994
27.65968514
december
-0.545429475
0.922081504
29.2815764
january
-0.189742792
0.976282151
27.65593939
february
-0.289068286
0.967881302
27.89598265
march
-0.340093981
0.965990602
27.95058249
april
-0.296127425
0.973079325
27.74696708
may
-0.237744558
0.980187953
27.54573743
Table 4: PV, EV and AC
SPI vs SPIt
1.02 1.02
1.00
1
0.98
0.98
0.96
0.96
0.94 0.94
0.92 0.92
0.90 0.9
0.88 0.88
0.86
0.86
MONTHS
SCHEDULE PERFORMANCE INDEX(SPI)
SCHEDULE PERFORMANCE INDEX [SPI(t)]
SPI
SPIt
month
SCHEDULE VARIANCE(SV)
SCHEDULE PERFORMANCE
INDEX(SPI)
ESTIMATE AT COMPLETION (EACt)
october
-86593.35
0.91534288
19.07599995
november
-136926.76
0.952072998
19.12870489
december
-192270.32
0.965498966
19.17114651
january
-254216
0.972802189
19.17753628
february
-323727.36
0.976283785
19.16916601
march
-486273.94
0.974749772
19.1570309
april
-508971.55
0.980178383
19.14456687
may
-582070.31
0.981865274
19.13451768
june
-617967.72
0.983852213
19.12232888
july
-632564.4
0.985845156
19.10762325
august
-564241.69
0.989012959
19.09654967
september
-372032.82
0.993505104
19.09084126
october
-303849.53
0.99523138
19.08936375
november
-544163.74
0.992141738
19.08918726
december
-426439.15
0.994229069
19.08967073
january
-458436.35
0.994116248
19.09127919
february
-464026.22
0.994245405
19.09283756
march
-299349.25
0.996378532
19.09431156
april
0
1
19.09542098
Figure 4: SPI vs SPIt
-
Results
Table 5: EV parameters
october november december january february march april
may june july august
september october november december january february march april
Table 6: ES parameters
MONTHS
Figure 3: SV vs SVt
From the results obtained from the ongoing project, the Earned value analysis suggests that the EV at the end of 12 months is INR 3,24,56,275 for a PV of INR 3,34,67,054.42 which has an AC of INR 3,27,18,600
month
SCHEDULE VARIANCE[SV(t)]
SCHEDULE PERFORMANCE
INDEX [SPI(t)]
ESTIMATE AT COMPLETION
(EACt)
october
-0.08465712
0.91534288
20.75724891
november
-0.074655522
0.962672239
19.73672786
december
-0.070794329
0.97640189
19.45920034
january
-0.067359065
0.983160234
19.32543582
february
-0.075230946
0.984953811
19.29024467
march
-0.086708329
0.985548612
19.27860257
april
-0.079286468
0.988673362
19.21767161
may
-0.090673631
0.988665796
19.21781868
june
-0.100116277
0.988875969
19.21373417
july
-0.09853949
0.990146051
19.1890883
august
-0.084640909
0.992305372
19.1473316
september
-0.062783991
0.994768001
19.09993082
october
-0.047198159
0.996369372
19.06923328
november
-0.098423544
0.992969747
19.13452052
december
-0.091766337
0.993882244
19.11695285
january
-0.114002153
0.992874865
19.13634906
february
-0.170589563
0.98996532
19.19259152
march
-0.147908996
0.991782834
19.15741971
april
0
1
19
which implies that the project is behind schedule by INR
10.11 lakhs (SV). It is sometimes confusing to say that a project is behind schedule in terms of money. And hence we have used Earned Schedule analysis to find the actual delay of the project. According to ES analysis the ES value at the end of 12 months is 11.7623 months. Which means we have accomplished only 11.7623 months of work in 12 months. It also suggests we are behind schedule by 0.2377 months (SVt). Further when we compare the schedule variances and the schedule indices of EV and ES analysis (figure 12 & figure 13) it was observed that the parameters from EV analysis follow the same trend as of the ES analysis till January, from January till May the EV parameters deviate a bit.
SV vs SVt
MONTHS
0 0.00
-0.02 -100000.00
-0.04
-200000.00
-0.06
-0.08 -300000.00
-0.1 -400000.00
-0.12
-500000.00
-0.14
-0.16 -600000.00
-0.18 -700000.00
SCHEDULE VARIANCE[SV(t)] SCHEDULE VARIANCE(SV)
COST
From the results obtained from the completed project, the Earned value analysis suggests that the EV at the end of 12 months is INR 8,35,75,649.99 for a PV of INR 8,35,75,649.99 which has an AC of INR 8,39,95,380.00 which implies that the project has been completed as the EV and PV value are the same. But the CV of the project is INR 4.2 lakhs. Further when the EV parameters SV and SPI were compare to the ES parameters SVt and SPIt, it was observed that the EV parameters follow similar trend with ES parameters throughout the project duration. But the EACt values derived from EV analysis says the project would complete in 19.1 months where as we already know that the project has been completed in 19 months
-
-
CONCLUSIONS AND RECOMMENDATIONS
-
Conclusions:
This study has helped us to find out the behaviour of Earned Value Analysis and the Earned Schedule Analysis parameters on two projects, one being completed and one in progress.
From the ongoing project it was seen that the EVA schedule parameters were flawed towards the later stages and deviated from the actuals and the ES parameters gave us appropriate data regarding the actual delay of the project.
From the completed project it was observed that both the EVA and ES parameters seemed to follow same trend, however the EACt value derived from EVA seem to be inaccurate. And once again the ES parameters gave us the actuals of the project without any problem.
Hence here are the conclusions of this study,
-
Earned Value Analysis is a great monitoring system for project cost control when the required information are cost oriented.
-
Earned Value Analysis parameters seem to deviate from actuals in later stages of the project.
-
Earned Schedule Analysis gives us more accurate results in terms of time.
-
-
Recommendations:
When we want to establish a monitoring system which could help us control cost, we need to consider a system which could give us accurate results both in terms of cost and time. Since Earned Schedule Analysis uses the EVM data to find the Schedule Variances in terms of time, we still need to use the Earned Value analysis to acquire the cost details. Hence we need to use both the systems for effective monitoring of the project.
Further studies may be conducted on other projects such as early finish projects and late finish projects to see if the system is capable of finding accurate results. It would be beneficial if the Earned Schedule concept is integrated into the Earned Value Analysis so that the results acquired from the system is accurate both in terms of cost and time.
REFERENCES
-
Abba, W., 1997. Earned Value Management: reconnciling government and commercial practices. Program Manager, Issue 26, pp. 58-67.
-
Al-Jibouri, S. H., 2003. Monitoring Systems And Their Effectiveness For Project Cost Control In Construction. international journal of project management 21, pp. 145-154
-
Anbari, F. T., 2003. Earned Value Project Management Methods and Extensions. Project Management Journal, Issue 34, pp. 12-23.
-
Bhosekar, S. K. & Vyas, G., 2012. Cost Controlling Using Earned Value Analysis In Construction Industries. International Journal of Engineering and Innovative Technology, 1(4).
-
Christensen, D. S., 1998. The Costs and Benefits of the Earned Value Management Process. Acquisition Review Quarterly .
-
Cleland, D. I. & Ireland, L. R., 2002. Project Management (Strategic Design and Implementation). 4th ed. London: McGraw Hill, Inc.
-
Cooke, B. & William, P., 2004. Construction Planning, Programming and Control. s.l.:blackwell publishing Ltd.
-
Henderson, K., 2004. Earned Schedule: A Breakthrough Extension to Earned Value Theory?. A Retrospective Analysis of Real Project Data.
-
Lipke, W., 2011. Earned Schedule – Schedule performance analysis from EVM measures. PM World Today, january .XIII(I).
-
Lipke, W., 2011. Further Study of the Normality of CPI and SPI(t). PM World Today, XIII(X).
-
Locke, B., 2008. A Neat Solution for the EVM schedule Problem.
Project Management Journal, Issue 38.
-
Stratton, R. W., 2007. Applying Earned Schedule Analysis to EVM data for Estimatinfg Completion date. AACE International Transactions EVM.04.