- Open Access
- Total Downloads : 270
- Authors : Ademola Abdulkareem, C. O. A. Awosope, Anthony U. Adoghe, Okelola. M. O
- Paper ID : IJERTV3IS030541
- Volume & Issue : Volume 03, Issue 03 (March 2014)
- Published (First Online): 09-04-2014
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Reliability Analysis of Circuit Breakerin the Nigerian 330-kV Transmission Network.
1Ademola Abdulkareem, 2C. O. A. Awosope, 3A. U. Adoghe, 4Okelola. M. O
1,2,3Electrical and Information Engineering Department, School of Engineering, College of Science and Technology, covenant University, Ota, Nigeria
4Ladoke Akintola University, Ogbomosho, Nigeria.
Abstract This paper is concerned with using the fault analysis to establish the requirements for the proper selection of circuit breaker; A Case Study of Power Holding company of Nigeria (PHCN) 330-kV Transmission Grid System. The work is modelled for Fault Analysis and it is written in a flexible MATLAB programs to accommodate addition or reduction in the Transmission Grid System. It aimed at establishing the Circuit Breaker Capacity at any point in the system. The result is then compared with the existing circuit breaker capacity of PHCN 330-kV system. The short-circuit fault is simulated by combining a solution of algebraic equations describing the changes in the network with a numerical solution of the differential equations. Two MATLAB programs were written and simulated; one for Lord Flow study to know the pre-fault bus voltages based on Gauss-Seidel Method; the other for Short Circuit Studies which made use of Thevenins theorem application. The highest Circuit Breaker Capacity established by the result of this study is relatively lower and the investments needed for this are smaller compared with the normal practice with PHCN system. This reveals that PHCN system can be protected with this low capacity circuit breaker with a reduced cost effectiveness and equal sensitivity which is a break-through in terms of Circuit Breaker Capacity in the field of power system protection.
Keywords Fault studies, circuit breaker, 330kV transmission grid, MATLAB program, Gauss Seidel load flow solution
-
INTRODUCTION
The current trends of erratic power supply and system collapse in Nigeria have made this study a paramount importance to the nations power industry. The purpose of an electrical power system is to generate and supply electrical energy to consumers with reliability and economy. The operation of a power system is affected by disturbances that could be due to natural occurrences such as lightning, wind, trees, animals, and human errors or accidents. These disturbances could lead to abnormal system conditions such as short circuits, overloads, and open circuits. Short circuits, which are also referred to as faults, are of the greatest concern because they could lead to damage to equipment or system elements and other operating problems including voltage drops, decrease in frequency, loss of synchronism, and complete system collapse. There is, therefore, a need for a device or a group of devices that is capable of recognizing a disturbance and acting automatically to alleviate any ill effects
on the system element or on the operator. Such capability is provided by the protection system. The protection system is designed to disconnect the faulted system element automatically when the short circuit currents are high enough to present a direct danger to the element or to the system as a whole. The objective of the system will be defeated if adequate provision for fault clearance is not made. The installation of switchgear alone is insufficient, discriminative protective gear, designed according to the characteristics and requirements of the power system must be provided to control the switchgear [1]. Security of supply, therefore, can be better by improving plant design, increasing the spare capacity margin and arranging alternative circuits to supply loads. Majority of the faults are unsymmetrical. However, the circuit breaker rated MVA breaking capacity is based on 3phase fault MVA. Since a 3phase fault inflicts greatest damage to the power system, except in a situation where a single line to ground fault is very close to a solidly grounded generators terminal. In this instance the severity of single line to ground fault is greater than that of 3phase balance fault.
-
BRIEF REVIEW OF SHORT-CIRCUIT ANALYSIS
Fault studies form an important part of power system analysis. In the context of electrical fault-calculation, a power system fault may be defined as any condition or abnormality of the system which involve the electrical failure of the primary equipment, the primary equipment implying equipment such as generators, transformers, busbars, overhead lines and cables and all other items of plant which operate at power system voltage (330kV for this case).
Faults on power system are divided into three-phase balanced faults and unbalanced faults. The different types of unbalanced faults are single line-to-ground fault (LG), line-to-line fault (LL), and double line-to-ground fault (LLG). The problem consists of determining the voltages and currents during various types of faults. The information gained from fault studies are usedfor proper relay setting and coordination. The three-phase balanced fault (LLL) information is used to select and set phase relays.
Majority of the faults are unsymmetrical and the current which a breaker must interrupt is usually asymmetrical since it still
contains some of the decaying dc component [2]. However, the circuit breaker rated MVA breaking capacity is based on three-phase balanced fault MVA. Since a three-phase fault inflicts greatest damage to the power system, except in a situation where LG fault is very close to a solidly grounded generators terminal. In this instance the severity of single line to ground fault is greater than that of three-phase balanced fault.
The condition of the power system during the fault condition can be explained from the equation for short circuit studies. The equation for the short circuit uses the sequence
components theory in the method of calculation.
Vp
=
GenIpo
Bus p
ypo
In an attempt to establish short circuit studies, various forms
Figure 1: A typical fault model at bus P
of faults were simulated to obtain the current which the
breaker must interrupt and comparison was made between LLL fault and LG fault either of which is likely to cause
I po
Pp jQ
p
*
(3)
greater damage to a power system. This current is properly called the required symmetrical interrupting capacity or simply the rated symmetrical short-circuit current. [3]
-
PROBLEM FORMULATION (LOAD REPRESENTATION)
During sub-transient period, power system loads, other than motors are represented by the equivalent circuit as static impedance or admittance to ground.The symmetrical three phase fault current in per unit is given by
V p
Where; Pp and Qp = the scheduled bus load.
VP = the calculated voltage which can only be determined if Qip is given or known
The injected current Ipo flows from bus P to ground, that is, to bus 0.
The magnitude and power factor angle of Ipo remain constant.
y I po .
= 0
(1)
po V p
Where 0 is the per unit Perfault bus voltage and =
the p.u reactance to the point of Fault
(4)
The base current
= ×103
3
(2)
-
NETWORK PERFORMANCE EQUATION
Where SB is the base MVA and VB is the line to line base voltage in kV
The interrupting rating of a circuit breaker was specified in
The Gauss-Seidel Method of solution used for the load flow
equation can be applied to describe the performance of a network during a su-transient period, using the bus
KVA or MVA.
admittance matrix with ground as reference. The voltage
From (2), it implies that the interrupting KVA equal 3 times
equation for bus P is given by:
the kV of the bus to which the breaker is connected times the current which the breaker must be capable of interrupting
Pp
jQp Lp
p1
k 1 '' k
when its contact part. This current is of course, lowers than the momentary current and depends on the speed of the breaker [2].
V p
* YLpqV q q1
V
p
1
YLpqV q ….(5)
q p1
Also, for the purpose of short circuit analysis in order to select appropriate circuit breaker to clear a fault instantly before transient condition on a power system, pre-fault condition of the system (i.e, pre-fault voltages and currents) should be
where;
YLpq Y pq Lp ; Lp
Pp jQ
Y pp
known and this can be obtained from the load flow solution for the power system. Detail of the initial value of the current for a constant current representation is obtained from model of
Theterm
p in equation (5) represents the load current at bus P.
V
*
p
fig 1.
for the cons tantload current representation,
Pp jQp k
k
| I po | p p…………………………………(6)
V p *
where;
p
the power factor angle,
p
and k the angle of voltage with respect to the reference.
When the constant power is used to represent the load, (Pp jQp) Lp will be constant but the bus voltage Vp will change in
o
f
V
jX
I ' '
f
……………………………………………………..(9)
Z
any iteration [4]. When the load at bus P is represented by a
static admittance to ground, the impressed current at the bus is TH
zero and the
Pp
jQp Lp
V
*
0
p
(7)
-
COMPARISON OF SLG FAULT AND THREE- PHASE FAULT (LLL) CURRENTS
This comparison[5]is necessary because of the earlier
For a sub-transient analysis in short circuit studies, the parameters of equation (5) must be modified to include the effect of the equivalent element required to represent synchronous, induction and loads. The line parameters YLpq must be modified for the new elements and additional line parameter must be calculated for each new network element.
V. METHOD OF SOLUTION
The methods and concepts employed to implement this work includes:
-
Developing an algorithm and hence a programme for fault level calculation at the location of fault in a 330-kV transmission Grid system.
-
Determine the fault current for various types of fault simulation.
-
Recommend the appropriate circuit breaker capacity to clear any detected fault.
Note that it is necessary to do a load flow calculation before one can proceed on fault analysis. This is important so as to know the pre-fault voltages and currents necessary for further calculation. The network representation for the short circuit studies includes among other things, the Grid components parameter i.e the generators system buses, transmission lines and transformers. Modification of the admittance matrix to impedance matrix is done on the load flow calculation [4] to reflect fault analysis.
These pre-fault conditions can be obtained from the result of
statement in this project study that single line-to-ground fault is more severe than that of 3-phase fault if the fault is located very close to the terminal of a solidly grounded generator.
The fault impedance can be assumed to be zero because of the enormous effect of the fault current. In addition, if the impedances Z1, Z2 and Z0 are assumed to be pure reactances (X1, X2 and X0), then for a 3-phase fault.
Ia
E ………………………………………………………………….(10).
1
jX
and that of sin gle line to ground fault is given as;
I
3E …………………………………………….(11).
1
2
0
a jX jX jX
The three practical possibilities are as follow;
-
Fault at the terminals of neutral solidly grounded generator, (for generator X0<< X1), and it is assumed that X1 = X2 for sub-transient condition which is the case for the short circuit studies. At this instance single line to-ground fault is more severe than a 3-phase fault
-
If a generator is grounded through a reactance Xn, this does not have any effect on a 3-phase fault current, but a single line-to-ground fault will have a fault current:
load flow solution by Gauss-Seidel iteration method using YBUS, the flowchart of which is illustrated in Fig.2.
The pre-fault machine currents are calculated from load flow
I a jX X
3E
2 X
0 3X n
1
by Gauss-Seidel iterative method from:
-
to this end the relative severity of 3-phase fault
V
I Pki
jQ
ki ;i 1,2,………., m…………………………………(8)
and single line-to-ground fault will depend on the value of Xn.
ki *
ki
where;
-
For a fault on a transmission line (which is the case study) X0>> X1 so that for a fault on a line
Pki
Q
and
ki
the scheduled
or calulated
machine real and
sufficiently far away from the generator
retaercmtiivnealst,er3-mphinasae l fapuoltwceurrsr.ent is more than single line-to-ground fault current.
V
ki
* the last iteration
voltage.
m the number of machines in the system.
The network is then modified to correspond to the desired representation for short circuit studies. Being a linear network of several voltage sources, further calculation can be computed by application of Thevnins theorem [5].
Figure 2: Flow Chart for Load-Flow Solution: Gauss-Seidel Iteration
Figure 3: Flow Chart for 3-Phase Symmetrical Fault
3
5
14
Beni
Omotos
120
0.0
0.0
0.228
n
ho
04
36
3
5
5
18
Beni
Oshogb
251
0.0
0.0
0.954
n
o
08
76
9
3
10
8
Sape
Aladja
63
0.0
0.0
0.239
le
02
19
3
11
8
Delta
Aladja
32
0.0
0.0
0.239
02
19
3
12
5
Ikeja
Benin
280
0.0
0.0
1.162
10
77
0
9
12
9
Ikeja
Aiyede
137
0.0
0.0
0.521
04
41
9
6
12
13
Ikeja
Papanlat
30
0.0
0.0
0.057
o
01
09
1
1
12
14
Ikeja
Omotos
160
0.0
0.0
0.304
ho
05
48
7
6
12
15
Ikeja
Akangb
18
0.0
0.0
0.257
a
02
17
2
2
12
17
Ikeja
Egbin
62
0.0
0.0
0.257
02
17
2
2
12
18
Ikeja
Oshogb
252
0.0
0.0
0.521
o
04
41
9
6
13
9
Papa
Aiyede
60
0.0
0.0
0.114
lanto
02
18
1
2
17
16
Egbi
Aja
14
0.0
0.0
0.257
n
02
17
2
2
18
9
Osho
Aiyede
115
0.0
0.0
0.437
gbo
04
34
1
9
18
27
Osho
Jebba(T
157
0.0
0.0
0.597
gbo
S)
05
47
6
7
20
21
Kadu
Kano
230
0.0
0.0
0.874
na
08
69
2
9
20
23
Kadu
Jos
197
0.0
0.0
0.748
na
07
59
0
9
20
24
Kadu
Shiroro
96
0.0
0.0
0.364
na
03
29
4
2
23
22
Jos
Gombe
265
0.0
0.0
1.01
09
81
5
24
25
Shiro
Katamp
144
0.0
0.0
0.598
-
-
-
RESULT OF SYSTEM MODELING
There is a necessity to have the knowledge of pre-fault voltages and currents in order to proceed with the calculation of the fault currents and hence achieving the aims of the research study. Hereunder are one-line diagram of the existing National 330-kV Network (Fig.4) and the systems data(Table) employed in the load flow calculation:
Figure 4: The 28-Bus System of the Nigerian Transmission 330-kV Grid as a Case Study [6]
Table 1: Transmission line data on 33kV, 100MVA base (All values are in per unit) [7]
BU S – NO FR O M
B U S
– N O T O
FRO M BUS
TO BUS
LENG
TH(km
)
R(
pu)
X(
pu)
ADMIT TANCE
(b/2)
1
2
Alao
ji
Afam
25
0.0
09
0.0
07
0.104
1
4
Alao
ji
Onitsha
138
0.0
49
0.0
42
0.524
3
4
New
Have n
Onitsha
96
0.0
03
0.0
29
2
0.365
4
6
Onits
ha
Okpai
80
0.0
09
0.0
07
0.104
5
4
Beni n
Onitsha
137
0.0
04
9
0.0
41
6
0.521
5
7
Beni
n
Ajaokut
a
195
0.0
07
0.0
56
0.745
5
10
Beni n
Sapele
50
0.0
01
8
0.0
13
9
0.208
5
11
Beni
n
Delta
107
0.0
02
0.0
19
0.239
ro
e(Abuja
)
05
2
40
1
24
27
Shiro
Jebba(T
244
0.0
0.0
0.927
ro
S)
06
70
7
2
26
28
Beni
Kainji
734
0.0
0.0
1.178
n
11
94
Kebb
1
2
i
27
19
Jebb
Jebba(T
8
0.0
0.0
0.0322
a(GS
S)
00
02
)
3
2
28
27
Kain
Jebba(T
81
0.0
0.0
0.308
ji
S)
02
24
9
6
16
IKEJA-WEST
-5.1500
-2.2900
17
AJAOKUTA
0.0000
0.0000
18
BENIN
-2.4000
-1.1200
19
ONITSHA
-1.0200
-0.4400
20
ALADJA
-1.5600
-0.8500
21
ALAOJI
-2.1600
-1.0400
22
NEW-HAVEN
-1.1000
-0.1800
23
AKANGBA
-3.0750
-1.5400
24
AJA
0.0000
0.0000
25
KATAMPE
(ABUJA)
0.0000
0.0000
26
AIYEDE
0.0000
0.0000
27
PAPALANTO
0.0000
0.0000
28
OMOTOSHO
0.0000
0.0000
Table 2; Voltage-Control Bus Data
-
LOAD FLOW RESULTS
BU
S NO.
BUS NAME
QG
QD
QMI N
QMA X
VSP
SLAC
K BUS
1
KAINJI
0.0000
0.000
–
2.790
1.050
0
2.790
0
0
0
2
JEBBA
0.0000
0.240
–
3.230
1.000
0
3.230
0
0
0
3
SHIROR
0.0000
0.180
–
2.000
1.000
O
0
2.000
0
0
0
4
SAPELE
0.0000
0.000
–
4.670
1.000
0
4.670
0
0
0
5
DELTA
0.0000
0.370
–
3.430
1.000
(IV)
0
3.430
0
0
0
6
AFAM
0.0000
0.000
–
36700
1.000
(IV)
0
3670
0
0
7
EGBIN
0.0000
0.000
–
5.820
1.000
0
5.820
0
0
0
The bus-bar pre-fault voltage, pre-fault current and pre-fault powers, which flow out of the bus bars, are tabulated in Table 4 hereunder
Table 3: Load Bus Data
BUS NO
BUS NAME
ACTIVE
REACTIVE
POWER (PG)
POWER (QG)
8
JEBBA (T.S)
-0.7200
-0.4300
9
BIRNIN- KEBBI
-0.3900
-0.1800
10
KADUNA
-1.6100
-0.8200
11
KANO
-2.0400
-0.8000
12
JOS
-0.9800
-0.3460
13
GOMBE
-1.5300
-1.0800
14
OSOGBO
-1.5600
-0.8800
15
IBADAN
-1.8000
-0.9300
Table 4; Output of Load-Flow Results (in p.u )
BUS NO.
VOLTAGE
POWER ANGLE
POWER FLOW
CURRENT
1
1.0500
0.0000
2.4787
2.3605
2
1.0000
-0.4060
7.2392
7.2394
3
1.0000
-8.1200
3.6954
3.6954
4
1.0000
12.9979
7.0150
7.0150
5
1.0000
13.9877
3.6998
3.6998
6
1.0000
18.2990
4.4075
4.4075
7
1.0000
2.0316
4.3869
4.3869
8
1.1219
-3.8503
0.8403
0.7443
9
1.0081
-0.6090
0.4238
0.4208
10
1.0173
-12.9984
1.8070
1.7760
11
1.0050
-21.0013
2.1898
2.1982
12
1.0601
-21.4268
1.0387
0.9522
13
1.0599
-27.4552
1.8735
1.7563
14
1.0220
-0.5700
1.7934
1.7518
15
1.0042
-2.3010
2.0273
2.0202
16
0.9899
-0.1259
5.6455
5.6960
17
1.0417
10.4510
0.0022
0.0020
18
1.0201
10.6305
1.1065
1.0860
19
1.0340
11.9994
0.4296
0.4068
20
0.9980
13.3385
1.8026
1.8015
21
1.0005
17.3005
2.4028
2.4018
22
1.0350
10.2956
1.1223
1.0764
23
0.9875
-0.5500
3.4326
3.4798
24
1.0002
2.0225
0.0164
0.0168
-
RESULT OF SHORT CIRCUIT STUDIES
In the short circuit studies, a base current of 174.9546A and a base voltage of 330kV are computed together with the load flow output result of the pre-fault condition in the input data for the various fault current calculations using the Power System Matlab Programming.[9].
Simulations were made for different types of short circuit faults i.e, 3-phase fault; single line-to-ground fault, line- to-line fault and double line-to-ground fault. The summary of is shown in Table 5.
MVAsc 3 phase 3 Vpf 1 I sc .
where;
MVAsc 3 phase 3 phase short circuit MVA.
VALUE)
Fault Current Result (IN ACTUAL
Vpf 1 Pr e fault line voltage in kV.
BASE CURRENT = 1,749.546kA BASE MVA = 100MVA
BASE VOLTAGE = 330kV
TABLE 5: TYPE OF FAULT (SUMMARY)
I sc Short circuit current in kA.
If voltages and currents are in per unit values on a 3-phase basis, then,
MVAsc (3-phase) = |V|pre-fault x |I|sc xMVAbase
BUS NO.
3- PHASE
SLG.
LL.
DLG
1
21878
11296
19335
19684
2
11688
4321
9897
10369
3
12082
6345
9879
9802
4
15568
8442
12680
12582
5
9157
4913
7723
7675
6
2312
1382
2255
2196
7
24989
13021
21958
22013
8
2228
1180
2012
2032
9
10012
5014
9146
8887
10
5826
2798
4988
5102
11
1895
894
1687
1698
12
1768
852
1485
1551
13
1062
598
986
993
14
8896
4140
7734
7984
15
28984
13982
24968
25437
16
21787
9603
18475
19004
17
5719
2870
4970
5042
18
20593
10143
18042
18275
19
3678
1830
3234
3290
20
9006
4367
7911
7960
21
2218
1150
2019
2050
22
2462
1146
2203
2239
23
25432
11951
22204
22597
24
20998
10246
18269
18804
For example: The Short Circuit Current from the output result of the program for the short circuit studies is 29036A with a pre-fault voltage of 331.4520kV.
MVAsc 3 phase 3 Vpf 1 I sc .
3 330kV 28,971kA
16,559MVA
From the summarized result in Table 5 above, it can be inferred that 3-phase fault causes greatest magnitude of fault current to the system and hence, should be a point of reference upon which the circuit breaker to clear faults on 330kV transmission line is based.
-
CONCLUSION AND RECOMMENDATION
To select the most appropriate size of Circuit Breaker for the Grid System, it has to be borne in mind that rated momentary current and rated symmetrical interrupting currents are required for the computation of circuit breaker ratings. Symmetrical current to be interrupted is computed by using sub-transient reactance for synchronous generators. Momentary current (rms) is then calculated by multiplying the symmetrical momentary current by a factor of 1.6 to account for the presence of D.C. offset current.
The 3-phase short circuit MVA to be interrupted can be computed as in the following equation [8]
-
CONCLUSION
From the above, and as a result of the research study, it can be concluded that the Circuit Breaker capacity for PHCN 330kV Transmission Grid should be 20,000MVA. The research result is a break-through in terms of Circuit Breaker Capacity in the field of Power System Protection.
The Birnin-Kebbi bus (B8) on which the receiving end voltage is higher than the sending end voltage, it is agreed upon and confirmed that the line is an open-ended one. This is what causes the abnormality. The solution to it is to connect a reactor to the line.
-
RECOMMENDATIONS
-
From the Nameplate of a Sf6 Gas Circuit Breaker (manufactured by GEC ALSTHOM T & D) on 330kV Transmission Line at the Area Transmission station in Osogbo:
Line Voltage VL = 362kV, Frequency f = 50Hz,
Short Circuit Current Isc = 40kA Line Current IL = 400A,
Current Interruption Capacity = 3,150A.
From the above data, the capacity of the Circuit Breaker is calculated to be 25,080.09569MVA. This is too high compared with the result of this project (i.e, 20,000MVA capacity) and it will be expensive in term of cost. The higher value of 25,080.09569MVA apart from cost, it will be more insensitive to any fault detected.
It is therefore recommended that the result of this paper should be of value to PHCN in the daily operation of the National Grid.
REFERENCES
-
W. D. Stevenson, Element of Power System Analysis, McGraw-Hill New York, 1982.
-
J. J. Grander, and W. D. Stevenson, PowerSystem Analysis, New York.
McGraw-Hill, 1994
-
H. Saadat Power System Analysis Published by McGraw-Hill publishing company limited, New
York 2006.
-
Braess, D. and Grebe, E. A. Numerical Analysis of load-Flow Calculation Methods, .IEEE Trans,
1981 July, No. 7, Vol. Pas-100, pp. 3642-3647.
-
B. R. Gupta, Power System Analysis and Design, Revised Edition, 2011
-
PHCN National Control Centre Oshogbo, 2010, one line diagram of the 28 bus systems of Nigerian
Transmission 330-kV Grid
-
PHCN Line Parameters for 330-kV Circuits, 2011.
-
I. J. Nagrath and D. P. Kothari, Power System Engineering, Fifth Print, 1998
-
Brown, H. W., et al, Digital Calculation of Three-Phase Short Circuits by Matrix Method, AIEE Trans, 1960, Vol. 79, pp. 1277