Reliability Centered Maintenance of a Ply Industry : A Case Study

DOI : 10.17577/IJERTV5IS110228

Download Full-Text PDF Cite this Publication

Text Only Version

Reliability Centered Maintenance of a Ply Industry : A Case Study

Mithilesh Kumar Jha

Assistant Professor Department of Mechanical Engineering

Millia Polytechnic, Purnea Bihar

Rakesh Kumar

Assistant Professor Department of Mechanical Engineering

Millia Polytechnic, Purnea Bihar

Abstract Reliability centered maintenance (RCM) is a corporate level maintenance strategy that is implemented to optimize the maintenance program of a company. The final result of an RCM program is the maintenance strategies that should be implemented on each of the assets of the company. The maintenance strategies are optimized so that the functionality of the plant is the main trained using cost effective maintenance techniques. To get maximum reliability and availability achieved by minimizing the possibility of system or component failure is the focus of Reliability Centered Maintenance with this maintenance strategy the function of equipment is considered and possible failure modes and their causes are indentified. Maintenance techniques that are cost effective in minimizing the possibility of failure are then determined. RCM can be conducted and implemented in many ways one way can be based on rigorous FMEA and FMECA, complete with mathematically calculated probabilities of failure based on design or historical data, intuition or common-sense and/or experimental data and modeling, such approaches may be called classical or rigorous RCM. Other way may use more of CBM, Pm optimization and some FMEA and RCA but less of analysis and calculations and such approach are generally called streamlined RCM. This case studies has been done on Durga Ply Mills, which is situated at Purnea District in the state of Bihar. This is a field application of the development of a Reliability Centered Maintenance Strategy for ply manufacturing industry.

Keywords Reliability centered maintenanc, optimized, failure, FMEA, FMECA.

  1. PROBLEM IDENTIFICATION

    All the industries pay a huge amount of money and time for the plant maintenance purpose. This money is basically used for setup, equipment spare parts change, labour chrge. Also there is tiem required to restore back the system to its originsal condition. Huge time is consumed for this purpose and company has got some production losss to restrre back the system to its original position in that time. Therefore maintenance department has an important role to maintain plants and equipments at its maximum oprationg efficiency, reducting downtimes and ensuring operational safety, safeguard inventment by minimizing rate of deterioratin and achieveing this at optimum cost through budgeting and controls. With the help of Reliability centered maintenance methodilogy, reliability of each and every equipment and instrument can be found some serious questions like what are the majour causes of failure or fault and how easily they can be rectified? are to be

    answered using RCM methodology. The reliability prediction of ply manufactureing plant has become faithful to focus on the components having more failure frequencies and to be taken care of. RCM methodology will reduce the chances of failure of the equipment.

  2. MAINTANABILITY & RELIABILITY CENTERED MAINTENANCE

    Introduction

    Reliability is the ability of a system or component to perform its required functions under stated conditions for a specified period of time reliabiity engineering is a sub discipline within system engineering reliability is often measured as probablity of failure frequency of failures or in terms of availability a probability derived from reliability and maintainbility.

    Maintenance

    The definittion often stated maintenance as an activity carried out for any equipment to ensure its reliability to perform its function. Mintenance to most people is any activity crarried out on an asset in order to ensure that the assset continues to perfrorm its intended functions or to repair any equipment that has failed or to keep the equipment running or to restrore to its favourable operating condition. Over the years, the new strategies have been implemented as maintenance strategies which are intended to overcome the problems which are related to equipment berakdown.

    Inspection

    Inspection are used in order to uncover the hidden failures. In general, no maintenance action is performed on the component during an inspection unless the component is found failed, in which case a corrective maintenance aciton is initialed. However there might be cases where a partial restoration of the inspected item would be performed during an inspection for example, when checking the motor oil in a car between scheduled oil changes, one might occasionalilly and some oil in order to deep in at a constant level.

    Maintainability

    Like reliability it has its own unique and diverstified elements. It is a characteristics of the design and installation of a complex system. The time taken to repair a system depends on how it has been designed. Further the design and installation characteristics will also dictate the

    maintenance policies. On the other hand it is possible to define some of the maintenance policies in advance and take design decision accordingly. The process of designing involves decision regarding module size, test procedures, built-in redundancies, and degree of automation, inspection intervals, special test equipments and safety requirements and so on. The maintenance policy will cover issues regarding general repairs, repair or discard policies, emergency recorder policies, inventory control, provisioning of spare etc. The technician requirements involve education, experience, training, capability analysis etc. Therefore the definition of maintnability is the probability that a unit or a system will be respored to specified conditons within a given period when maintainbility actionis taken in accordance with prescribed procedures and resoueces. It is characteristic of the design and installation of the unit or system since maintainbility also is a probabiity in the same way a reliability, its value lies between zero to one.

    Availability

    Abailability is a performance criterion for repairable systems that accounts for both the reliability and maintaninbility properties of a component or system it is defined as the propbability that the system is operating properly when it is requested for use. That is availablity is the probability that a system is not failed or undrgoing repair action when it needs to be used.

    Down Time

    When a system is often unavaibale due to breakdown and is put back into operation after each breakdown with proper repairs, the meantime between breakdown was defined as the meantime between failures (MTBF). If we consider only the active repair time i.e, the time spent for actual repair, the menatime to repair (MTTR) is the statistical mean time for active repair. It is the total active repair time furing a given period divided by the number of malfunctions during the same interval, frequently, a system may become unavailable on account of periodic inspections and not because of breakdowns. The main difference betweeen MTBF and MTBM is perventive maintenance down time.

    Reliability Centered Maintenance

    RCMs roots trace back to the 1960s when it was advanced to improve the safety and reliability of commercial aircraft. Since then it has begun to move into the industrial sector as a result of work conducted by severeal authors. RCM is a procedure for determining maintenance strategies based on reliability techniques and encompasses condition monitoring and well known analysis mthods such as Failure Mode Effects and Criticality Analysis (FMECA). The primary objective of the RCM process is to identify ways to avoid or reduce the consequences fo failure which if allowed to occur will adversely impact personned safety environment health , mission accomplishement or enconomics. It is the ptimum mix of reactive preventtive predictive and proactive maintenance practices. It involves some design/redesign and redundancy also.

    Table 1. RCM Application

    Maintenance Strategy

    Action Required

    RCM Based Application

    Run to Failure (Reactive)

    Repair or replace upon Failure

    Non-critical and small items; Cost to control or detect failure exceeds benefits (Not cost- effective)

    Scheduled Change or restoration (preventive)

    Repair or replace on fixed time or cycle basis.

    Asset has a well documented MTBF and a small standard deviation; Subject to wear-out and failure pattern known.

    CBM

    (Predictive)

    Employ condition monitoring to detect early stage failures, Replacement or repair are scheduled on condition.

    Asset fails randomly critical nature justifies early detection techniques. Not subject to wear. PM induced failures.

    Minor Redisign and condition- control (Proactive)

    Changes in hardware loading or procedures, condition monitoring detects the presence of root cause of failure.

    Objective is to reduce the failure rate for a given time period; RCFA, FMEA, Age exploration

    Redundancy

    Deploy active shared-load or stand by edundant systems

    Critical asets (or mission) for which no other approach is acceptable

  3. PRESENT INVESTIGATION

    The present investigation involves the survey of the plan view of the plant, machineries and the operation of the different machine tools under the guedance of the plant and service department of the company. The present study aims to focus on the reliability and maintainability aspects and availability aspects of the ply manufactureing plant.

    Plywood

    Plywood is made of three or more thin layers of wood bonded together with an adhesive. Each layer of wood or ply is usually oriented with its grain running at right angles to the adjacent layers in order to reduce the shrinkage and improve the strength of the finished piece.

    Raw Materials

    Plywood may be mede from hardwoods, sofwoods, or a combination of the two. Some common hardwoods include ash, mahogeny, oak and teak. The most common hardwood used to make plywood is Douglas, fir redwood. The outer layers of plywood are known respectively as the face and the back. The face is the surface that is to be used or seen, while the back remains unused or hidden. The central layers of plywood are known as the core. In plywood with five or more ples, the intermediate layers are known as the crossband.

    Glue spreader Machine

    Glue spreader Machine

    Pressed Veneer Storage Space

    Pressed Veneer Storage Space

    Hot Press Machine

    Trimming of Veneer

    Trimming of Veneer

    Final Product Storage Space

    Final Product Storage Space

    Maintenance Department

    Maintenance Department

    Security Room

    Security Room

    Water Tube Boiler

    Fuel Storage Space

    Fuel Storage Space

    Wood Peel Storage

    Wood Peel Storage

    Glue Mixer Machine

    V. COLLECTION OF DATA

    The most essential precondition for reliability analysis or maintenance planning is the availability of relevant data. For the present analysis, failure data related to different constituents of Ply Manufacturing Plant duing last 5 years (Aug 2009 to July 2014) are collected from the maintenance department of the company. This data includes the following:

    Wood Peeling Machine or Veneer Lathe

    Wood Peeling Machine or Veneer Lathe

    No. of breakdowns related to different types of failure of Ply Manufacturing Plant and their components.

    Monthly available hours and breakdown hours for individual components of Ply Manufacturing Plant.

    Wood Log Storage Space

    Wood Log Storage Space

    Log Cutter Machine

    Log Cutter Machine

    The vaurious data on maintenance actions taken for Ply Manufacturing Plant has been colleted from daily breakdown record book supplid by maintenance section. From the daily maintenance record book, the failure hours, frequency of failures has been estimatted and plotted. To get an overview about the performance of the ply manufacturing plant during the period under study (Aug 2009 to July 2014).

    Table 2. Failure of the Component of Ply Manufacturing Plant

    Entrance Durga Ply Mill Purnea, Bihar

    Entrance Durga Ply Mill Purnea, Bihar

    Sl. No.

    Name of the Different Machinery/Componet

    Number of Failures (Aug 2009 to July 2014)

    1.

    Water Tube Boiler

    19

    2.

    Wood Peeling Machinge

    15

    3.

    9-Delight Pressing Machine

    11

    4.

    Glue Spreader Machine

    20

    5.

    Glue Mixer Maching

    15

    Sl. No.

    Name of the Different Machinery/Componet

    Number of Failures (Aug 2009 to July 2014)

    1.

    Water Tube Boiler

    19

    2.

    Wood Peeling Machinge

    15

    3.

    9-Delight Pressing Machine

    11

    4.

    Glue Spreader Machine

    20

    5.

    Glue Mixer Maching

    15

    Figure 1. Plan View Of The Plant

  4. STEPS INVOLVED IN MAKING PLYWOOD

    Veneer Manufacture

    It is usually accepted that manufacture includes all the process from the time, the log enters the yard to the stage where a dried, graded veneer ready for further processing into plywood has been produced. The logs are then cut into suitable lengths for peeling. These lengths are called peeler blocks or sometimes pillerbillets.

    Veneer Cutting

    Veneer cutting done on the veneer lathe machine. The loading of veneer on the lathe can be done manually with a hoist and log tonges or automatically with machanical loading and centring devices.

    Uses of Adhesives or Glue

    The pricnicpal difference between adhesives used in plywood manufacture is the degree to which they are

    30

    20 19

    10

    0

    Number of Failure

    20

    15 15

    11

    waterproof. To ascertain the degree of waterproofness of a glue line the standard association of Austtralia, under close direction from the plywood industries have defined a series of bond tests.

    Water

    Tube Boiler

    Wood

    Peeling Machine

    1. Delight

      Pressing Machine

      Glue

      Spreader Machine

      Glue

      Mixer Machine

      Glue Spreading Operation

      In the glue spreading operation the crossbands are spread on both sides simultaneously. Close control over the amount of adhesive spread is obtained by adjusting the spreader doctor roll gap.

      Figure 2. Number of Failure of Different Componetn (August 2009 to July 2014)

      1. ANALYSIS OF THE STUDY

        Failure Analysis

        These mechanical components are failed due to mechanical failure. The major and minor causes of failures are there which are shown in the tabular form:

        Table 3. Failure of the Different Component

        Sl.

        No.

        Name of Componet

        Failure Due to

        1.

        Failur of Boiler

        Spark plug problem, Back fire problem, knocking or detonation, water inlet filter, chock water outlet chock, stress rupture, water side corrosion, fatigue, damage during chemical cleaning, Mterial defects.

        2.

        Failure of wood peeling machine or veneer lathe

        Head stock problem, bearing problem, belt drive problem, motor problem, chuck problem, tail stock problem, carriage problem, saddle problem, cross slide problem, tool post problem, peeling teeth problem

        3.

        Failur of Pump

        Speed too low, broken impeller, air leak in suction line, excessive shaft misalignment, lubricant contamination,

        4.

        Failure of 9- Delight pressing machine

        Steam pressure problem, gap between plate problem, motor problem, excessive heat problem

        Failure Modes and effect Analysis (FMEA)

        Failure modes and effect analysis has been carried out to examine potential failure modes in the ply manufacturing plant components. It has been used to evaluate risk priorities for mitigating known threat- vulnerabilities. FMEA has been carrid out to select remedial actions that reduce cumulative impacts of lifecycle consequences from system failure.

        Fault Tree Analysis

        It is first developed in Bell Telephone Laboratories in 1962 for the U.S. Air forces for use with the minuteman system. Fault tree analysis is one of the symbolic Analytical logic techniques found in operation research and in system reliability. Fault tree diagrams are logic block diagrams that display the state of a system (Top event) in terms of the states of its components (basic events). It uses a graphic model of the pathways within a system that can lead to an undesirable loss event (or a failure).

        Primary Event Block

        Classic FTA Symbol

        Description

        Basic Event

        A basic initiating fault or failure event.

        Undeveloped Event

        An event which is no further developed. It is a basic event that does not need further resolutions.

        Transfer

        Indicates a transfer contribution to a sub tree

        Conditioning Event

        A specific condition or restriction that can apply to any gate.

        Combination Event

        An event resulting from combinations of more basic events.

        External Event

        An event that is normally expected to occur.

        Primary Event Block

        Classic FTA Symbol

        Description

        Basic Event

        A basic initiating fault or failure event.

        Undeveloped Event

        An event which is no further developed. It is a basic event that does not need further resolutions.

        Transfer

        Indicates a transfer contribution to a sub tree

        Conditioning Event

        A specific condition or restriction that can apply to any gate.

        Combination Event

        An event resulting from combinations of more basic events.

        External Event

        An event that is normally expected to occur.

        Table 5 Traditional Fault Tree Analysis

        Table 4. The FMEA Process

        Steps

        Types

        Step 1

        Identify Function

        Step 2

        Identify failure modes

        Step 3

        Identify dffects of the failure modes

        Step 4

        Determine severity

        Step 5

        Apply procedure for potential consequences

        Step 6

        Identify potential causes

        Step 7

        Determine occurances

        Step 8

        Calculate criticality

        Step 9

        Identify design or process control

        Steps 10

        Determikne Detection

        Steps 11

        RPN and final risk asessment

        Steps 12

        Take accounts to reduce risks

        Steps 13

        Identify root cause

        Steps 14

        Identify special characteristics

        Reliability Analysis

        The machines and equipments are selected for reliability analysis of a ply manufacturing plant are water tube boiler, wood peeling machine, 9-delight pressing machine, glue mixer machine, glue spreader machine.

        Hazard Model & Probability distribution

        The initial stage of reliability analysis is to predict the hazard model of the failures and to choose a distribution among various probability distributions like normal distribution, exponential distribution, poisson, distribution, weibull distribution etc.

        Graphical Evaluation for Reliability Prediction

        There are generally two ways for graphical evaluation viz. Exponential plot and Weibull plot. When the failure rate is

        constant, the distribution follows exponential probability law and when failure rate is not constant, i.e. non-linear hazard model follows Weibull distribution.

        Linear Regression Analysis: Selection of Distribution

        The observed data regarding the failures of different components of the manufacturing plant shows that the failure rates of the components are not constant. So the Weibull distribution model can be adopted. Moreover the technique of linear regression analysis confirms the suitability to use Weibull distribution for the different components of the ply manufacturing plant. The analysis determines the best-fit line in the least square sense. The least square test has been performed to obtain the increasing/decreasing rate of failures linear regression analysis has been carried out by using the probability equation.

        Weibull Distribution

        About all the distribution available for reliability calculations, the weibull distribution is the only unique to the field. Professor Wallodi Weibull (1887-1979) pointed out that normal distributions are not applicable for characterizing initial metallurgical strengths during his study on metallurgical failures. He then introduced a function that could embrace a great variety of distributions and used seven different case studies to demonstrate how this function allowed the data to select the most appropriate distribution from a broad family of Weibull distributions. Probably the most widely used distribution in reliability engineering.

        Computation of Maintenance Policy

        Breakdown occurs at random. It forms any of the following types of frequency distribution, exponential, normal, logarithmic, gamma or weibull. In a situation like this, statistical methods are used in laying down maintenance policy such as standard preventive maintenance cycle time (Ts), average time between breakdown (Ta) and average preventive maintenance time (Tm).

        Maintenance Policy for Wood Peeling Machine

        For this purpose the year (2014), data is collected. Breakdown and Maintenance cost data is collected from the Maintenance Department of the ply manufacturing plant.

        Table 7 Maintenance Cost Details of Wood Peeling Machine (year-2014)

        Mont h

        B/D Probabi lity

        Cum ulativ e Proba bility

        Expect ed B/D=n

        Cost Of B/D (Rs)

        Cost of P/M (Rs)

        Total Cost (Rs)

        Maint enan e cost p.m (Rs)

        Jan

        0.272

        0.272

        2.992

        9574

        4000

        13574

        13574

        Feb

        0

        0.272

        3.805

        12176

        4000

        16176

        8088

        Mar

        0

        0.272

        4.026

        12883

        4000

        16883

        5627

        Apr

        0.090

        0.362

        5.077

        16246

        4000

        20246

        5061

        May

        0.090

        0.452

        6.621

        21187

        4000

        25187

        5037

        June

        0

        0.452

        7.383

        23625

        4000

        27625

        4604

        July

        0.181

        0.633

        9.675

        30960

        4000

        34960

        4994

        Aug

        0

        0.633

        10.953

        35049

        4000

        39049

        4881

        Sept

        0.090

        0.723

        12.671

        40547

        4000

        44547

        4949

        Oct

        0.090

        0.813

        14.645

        46864

        4000

        50864

        5086

        Nov

        0.090

        0.903

        16.979

        54332

        4000

        58332

        5302

        Dec

        0.090

        0.993

        19.567

        62614

        4000

        66614

        5551

        Maintenance Cost

        15000

        10000

        5000

        Jan

        Feb Mar Apr May June July Aug Sept Oct Nov

        Dec

        Jan

        Feb Mar Apr May June July Aug Sept Oct Nov

        Dec

        0

        Figure 3 Maintenance Cost Pattern of Wood Peeling Machine

        Maintenance Policy for Glue Mixer Machine

        For this purpose the collection of the taken from year 2014. Breakdown and Maintenace cost data is collected from the Maintenance Department of the Ply-Manufacturing Plant.

        Table 8 Breakdown Details of Glue Mixer Machine (Year 2014)

        Sl. No.

        Month

        No. of Failure

        Breakdown Probability

        1

        May 2014

        1

        0.2

        2

        June 2014

        0

        0

        3

        July 2014

        0

        0

        4

        August 2014

        1

        0.2

        5

        September 2014

        1

        0.2

        6

        October 2014

        1

        0.2

        7

        November 2014

        0

        0

        8

        December 2014

        0

        0

        9

        January 2015

        0

        0

        10

        February 2015

        1

        0.2

        11

        March 2015

        0

        0

        12

        April 2015

        0

        0

        Sl. No.

        Month

        No. of Failure

        Breakdown Probability

        1

        May 2014

        1

        0.2

        2

        June 2014

        0

        0

        3

        July 2014

        0

        0

        4

        August 2014

        1

        0.2

        5

        September 2014

        1

        0.2

        6

        October 2014

        1

        0.2

        7

        November 2014

        0

        0

        8

        December 2014

        0

        0

        9

        January 2015

        0

        0

        10

        February 2015

        1

        0.2

        11

        March 2015

        0

        0

        12

        April 2015

        0

        0

        Table 6 Breakdown Details of Wood Peeling Machine

        Sl. No.

        Month

        No. of Failure

        Breakdown Probability

        1

        May 2014

        3

        0.272

        2

        June 2014

        0

        0

        3

        July 2014

        0

        0

        4

        August 2014

        1

        0.090

        5

        September 2014

        1

        0.090

        6

        October 2014

        0

        0

        7

        November 2014

        2

        0.181

        8

        December 2014

        0

        0

        9

        January 2015

        1

        0.090

        10

        February 2015

        1

        0.090

        11

        March 2015

        1

        0.090

        12

        April 2015

        1

        0.090

        Table 9 Maintenance cost details of Glue mixer machine (Year – 2014)

        Mo nth

        B/D Proba bility

        Cumula tive Probabi lity

        Expect ed B/D=N

        Cost Of B/D(R

        s)

        Cost Of P/M(

        Rs)

        Total Cost (Rs)

        Maint enanc e Cost P.M(

        Rs)

        1

        0.2

        0.2

        1

        3200

        4000

        7200

        7200

        2

        0

        0.2

        1.2

        3840

        4000

        7840

        3920

        3

        0

        0.2

        1.24

        3968

        4000

        7968

        2656

        4

        0.2

        0.4

        2.248

        7193

        4000

        11193

        2798

        5

        0.2

        0.6

        3.6496

        11678

        4000

        15678

        3133

        6

        0.2

        0.8

        5.1699

        16543

        4000

        20543

        3423

        7

        0

        0.8

        5.721

        18307

        4000

        22307

        3186

        8

        0

        0.8

        6.0816

        19461

        4000

        23461

        2932

        9

        0

        0.8

        6.6435

        21259

        4000

        25259

        2806

        10

        0.2

        1

        8.5412

        27331

        4000

        31331

        3133

        11

        0

        1

        9.8151

        31408

        4000

        35408

        3218

        12

        0

        1

        10.596

        33907

        4000

        37907

        3158

        Maintenance Cost

        8000

        6000

        4000

        2000

        0

        Maintenance Cost

        8000

        6000

        4000

        2000

        0

        Jan

        Feb Mar Apr May June July Aug Sept Oct Nov

        Dec

        Jan

        Feb Mar Apr May June July Aug Sept Oct Nov

        Dec

        Figure 4 Maintenance Cost Pattern of Wood Peeling Machine

      2. RESULT AND DISCUSSION

        Reliability Estimation

        Reliability estimation of the different components of the ply manufacturing plant provides the values of reliability which focuses on the performance of the components of the ply manufacturing plant during the period of August 2009 to July 2014.

        Table 10 Reliability of the Ply Manufacturing Plant Components

        Sl. No.

        Name of the Components

        Mean operation Hour (In hrs.)

        Reliability

        %

        1

        Water tube boiler

        456.06

        68.44

        2

        Wood peeling machine

        378.91

        66.68

        3

        9-Delight pressing machine

        420.03

        81.82

        4

        Glue spreading machine

        600.5

        55

        5

        Glue mixer machine

        558.16

        66.7

        From the above table it is found that the estimated reliability of the different component of the ply manufacturing plant is in the range of 55% to 81.82%. The reliability of the 9-Delight pressing machine is the maximum (81.82%) waheras the minimum (55%) reliability is for the glue spreading machine. So the reliability prediction of ply manufacturing plant has

        become fruitful to focus on the components. Glue spreading cachine should be taken care of. All the other components have moderate reliability.

        Availability of Different Component of the Ply- Manufacturing Plant

        As per the definition of operational availability, the availability of different component of the ply manufacturing plant is caluculated for a particular month starting from Aug 2009 to July 2014. After that the operational availability of each plant is calculated. A detailed list of estimated average operational availability of different cdomponents of th eplay manufacturing plant is given in the table below:

        Table 11 Estemated Maximum Availability of the Ply manufacturing plant component

        Sl. No.

        Name of the Components

        Average operational Availability

        1

        Water tube boiler

        0.9967

        2

        Wood peeling machine

        0.9949

        3

        9-Delight pressing machine

        0.9950

        4

        Glue spreading machine

        0.9965

        5

        Glue mixer machine

        0.9955

        Computation of Maintenance Policy

        From the table below The Maintenance cost for wood peeling machine in the 1st month is Rs.13574. The maintenance cost for wood peeling machine in the 2nd month is decreased to Rs.8088. The maintenance cost for wood peeling machine in the 3rd month is again decreased to Rs.5627. The maintenance cost for wood peeling machine decreases till 9th month but it again increased in 10th month. So in case of wood peeling machine, from the maintenance policy it does appear that Preventive maintenance policy is not suitable for wood peeling machine

        Table 12 Maintenance cost detais of wood peeling Machine (May 2014 to April 2015)

        Months

        Maintenance cost per Month (Rs.)

        May 2014

        13574

        June 2014

        8088

        July 2014

        5627

        August 2014

        5061

        September 2014

        5037

        October 2014

        4604

        November 2014

        4994

        December 2014

        4881

        January 2015

        4949

        February 2015

        5086

        March 2015

        5302

        April 2015

        5551

        Maintence Cost Details Of Glue Mixer Machine

        From table below it appears that total maintenance cost for the entire machine/month, there is no perfect relationship which suggest for ensuring non- stop uninterrupted production system combination of preventive and Breakdown maintenance policy is suitable for the machine available in the Ply- Manufacturing plant. The maintenance cost for Glue mixer machine for the 1st three month is Rs. 7200, Rs.3920; Rs.2656 from the 4th month maintenance cost is again increased. So in case of Glue mixer machine, from the maintenance policy it does appear that Preventive maintenance once in three month is suitable.

        Table 13 Maintenance Cost Details Of Glue Mixer Machine (May 2014 to April 2015)

        Months

        Maintenance cost per Month (Rs.)

        May 2014

        7200

        June 2014

        3920

        July 2014

        2656

        August 2014

        2798

        September 2014

        3133

        October 2014

        3423

        November 2014

        3186

        December 2014

        2932

        January 2015

        2806

        February 2015

        3133

        March 2015

        3218

        April 2015

        3158

      3. CONCLUSION

        From the present studies we found the following conclusion:

        1. The Maintenance policy is necessary to decide the frequency of maintenance to determine how frequently maintenance should be done so that the equipment are highly reliable when needed.

        2. It is necessary to deal again with breakdown frequencies of the ply manufacturing plant component.

        3. Since the preventive maintenance program costs more than the breakdown maintenance program, We should look to preventive maintenance scheduling alternatives such as providing preventive maintenance only every second or third month.

        4. Therefore detail and continuous study is required for analyzing the benefits obtained in terms of maintenance cost, operational effectiveness for ply manufacturing plant components on reliability aspects.

      4. FURTHER SCOPE OF THE STUDY

        The present investigation can be extended meaningfully for further study in the following areas:-

          1. The study can be carrying out to development of a detailed maintenance plan to improve availability of components.

          2. The detailed study can be carry out for the effects of the proposed guidelines on the overall MTBF improvement of the ply manufacturing plant components.

          3. The study can also be carry out on the preventive Maintenance policy is necessary to decide the frequency of maintenance of the other component of the ply manufacturing plant like- wood peeling machine, water tube boiler.

          4. The study can be done the effects of the proposed guidelines on the reliability of the ply manufacturing plant.

          5. Detailed study of the effects of the proposed guidelines on the availability of the ply manufacturing plant can also be carrying out.

          6. Reliability and Availability of the other machines or components can be evaluated by further study.

    1. REFERENCES

  1. Isermann R., process fault detection based on modelling and estimation methods-Asurvey, Automatica, Vol.20, No.4, pp. 387-404, 1984.

  2. Mohandas K., Chaudhuri D., and Rao B.V.A., Optimal periodic replacement for a deteriorating production system with inspection and minimal repair. Reliability Engg. Syst. Saf.,Vol.37, pp 73-77, 1992.

  3. Pan Z. And Nonaka Y., Importance analysis for the systems with common cause failures, Reliability Engineering and system safety, Vol.50, pp. 297-300, 1995.

  4. VaurioJ.K.,The probabilistic modelling of external common cause failure shocks in redundant systems, Reliability Engineering and system safety, Vol.50, pp. 98- 107, 1995.

  5. Hontelez J.A.M., Burger AH.H, and Wijnmalen D.J.D., Optimum condition base maintenance policies for deteriorating systems with partial information , Reliability Engg. Syst. Saf. Vol. 51, No.3, pp 267-274, 1996.

  6. Tseng S.T.,Optimal preventive maintenance policy for deteriorating production systems, IIE Trans., Vol.28, No.4, pp. 687-694,1996.

  7. Ogunyemi O.T. and Nelson P.I., Prediction of gamma failure times, IEEE Transaction on reliability, Vol.46, No.3, pp. 400-405, 1997.

Mr. Mithilesh Kumar Jha obtained his Bachelor degree from Maghad University Gaya, Bihar. In addition, master degree from MAKAUT formally known as WBUT from West Bengal. Presently working as Assistant

Professor in the Department of Mechanical Engineer in Millia Polytechnic Purnea, Bihar.

Mr. Rakesh Kumar obtained his Bachelor degree from SIT VTU, Belgaum, Bangalore. In addition, master degree from NITTTR Kolkata. Presently working as Assistant Professor in the Department of Mechanical Engineer in Millia Polytechnic Purnea, Bihar.

Leave a Reply