Stakeholders Perspective of the Impact of Risk Factors on Cost, Time and Quality of Building Construction Projects

DOI : 10.17577/IJERTV3IS10189

Download Full-Text PDF Cite this Publication

Text Only Version

Stakeholders Perspective of the Impact of Risk Factors on Cost, Time and Quality of Building Construction Projects

Calistus Ayegba1*, Augustine Edoka Ijigah 2, Adakole Edwin Agbo 3,

  1. Department of Building, Federal University of Technology Minna Niger State, Nigeria

  2. Department of Building, Federal University of Technology Minna Niger State, Nigeria

  3. Department of Building, Federal University of Technology Minna Niger State, Nigeria

Abstract

The paper considers the stakeholders perspective of the impact of risk factors on cost, time and quality of building construction projects. In the study, stakeholders perceptive of the impact of risk factors on cost of building construction projects as well as stakeholders perceptive of the impact of risk factors on time duration of building construction projects and stakeholders perceptive of the impact of risk factors on quality of building construction projects were assessed. Data for the study was obtained Data for the study was collected via a structured questionnaire administered to respondents in Abuja, Port-Harcourt, Kaduna and Lagos state. The questionnaires are designed to assess the views of respondents on the impact of risk factors on cost, time and quality of building construction projects. Respondents were asked to rate their perceptions regarding the severity of risk factors on a five point Likert ordinal scale where 5 = Very Severe, 4 = Severe, 3 = Neutral, 2 = Less Severe and 1 = Not Severe. Data obtained from the survey were analysed using Relative Severity Index (RII) method. The Relative Severity index (RII) was calculated using the formula: RII = nW÷N (for 0RII5) Where W= the weight assigned to each strategy by the respondents, n = number of respondents, N = the total number of respondents. The limits of definition of RII were: 0 RII1 = Not Severe, 1RII2 = Less Severe, 2RII3

= Neutral, 3RII4 = Severe, 4RII5 = Very Severe. The mean relative severity index was then calculated and a rank ordering of these variables were then assigned based on the calculated relative index (RII). Findings revealed that 6% and 91% of the impact of risk factors on cost of building

construction projects were perceived to be very severe and severe respectively, 3% of these factors have neutral impact while none of the factors were seen to be of less severity or not having severe impact on the cost of building construction projects. Furthermore, on stakeholders perceptive of impact of risk factors on time duration of building construction projects, improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking with relative index of 4.290, 4.142, 4.110, 4.108 and 4.002 respectively while on stakeholders perceptive of impact of risk factors on quality of building construction projects corruption/bribery, competition from other companies in form of employing lowest bid to get the contract, poor quality of procured materials, design changes and shortage of skilful workers were ranked overall as the top 34 risk factors identified from literature review.

Keywords: Risk Management, Risk factors, Cost, Time, Quality, Construction Industry.

  1. Construction industry development is a common and contemporary goal of many urban development policies in various countries [2] and [3]. Development of the construction industry also requires knowledge of risk management policies. It is a well establish fact that every stage of the construction process, from initial investment appraisal through to construction and use of the built facility, is subject to risk for all the parties involved. Indeed, compared to other industries, the Nigeria construction industry has a particularly poor record in this regard with high number of construction related risks occurring each year [12] and [20]. In recent

    times, the nature, incident and impact of risk in construction have become a topic of interest because of the effects on quality, time and cost of construction projects [9], [12] and [20]. Risk is important to contractors as well as clients and consultants within the construction industry; however, the problems of risk assessment are complex and poorly understood in practice[18]. In a related development [1] pointed out that construction activities are full of risk which include those that may relate to external, commercial, design, construction and operation. However, they have to be considered for effective management in order to retain the initial objective of the project. Risk is defined as the probability that an unfavorable outcome will occur [15]. According to [6], risk is the probability that an adverse event occurs during a stated period of time. [1], [18] and [7] stated that projects have life cycles or a sequence of stages and activities from origin to completion and there is always a degree of risk associated with each stage. [11] and [23] pointed out that too often this risk is not dealt with satisfactorily which has resulted into poorly performed projects in the industry. They submit that the way out is the integration of risk management techniques into the estimation of construction projects cost and time, as this will help considerably to avoid excessive overrun.

    Many approaches have been suggested for the classification of risks. However, all of them pointed to the identifying the primary source of risk central to construction activities which triggered the risk. [12] Identified physical, design, environmental, logistics, financial, legal political, construction and operational risk while [6] classified risks into natural and human risks, subdivision of each of these classifications were also listed. The classification of risk are therefore combined into physical, political, environmental, management, legal, technical and market risk. [16] Listed the following as six major processes involved in project risk management: Risk management planning, risk identification, qualitative risk analysis, quantitative risk analysis, risk response planning and risk monitoring and control. Each risk management process results in a specific deliverable which is used as the foundation for the subsequent process.

    Track record of successful construction projects would have been greatly improved if more companies had included risk as an integrated part of the project control and quality system [12]. Therefore it is necessary to understand the nature or risks before any management of risk can occur as risk comes in many forms and often the nature of risk depends on the situation.

  2. Statement of Problem

    The Nigerian construction industry has been associated with repeated construction time overrun, construction cost overrun and low quality construction products in recent years but according to [5], [11] and [12] required attention to risk management will reduce project time overrun, cost overrun as well as improve the quality of products and cases of abandoned projects. Construction itself is prone to a variety of risks, such as financial, management, environmental and technical related risks, mainly because of the materials used, nature of design, methods of construction, locations and layout, physical structure and the use to which buildings are put [4]. Previous study by [14], [13] and [21] suggests the application of risk management model of project characteristic to manage the risks inherent in construction project but according to

    [16] quantitative analytical techniques for managing risk has been rarel used due to limited understanding and experience of the stakeholders in the construction industry. Risk management of construction projects gives the most emphasis to environmental, economic and social issues. Previous researches has identified what constitute risk factors on construction projects but stakeholders perspective on the impacts of these risk factors on cost, time and quality of construction projects as not been well looked into. Based on this the study set out to analyze stakeholders perspective of the impact of risk factors to the cost, time and quality of construction projects so as to reduce construction cost and time overruns as well as improve the quality of construction products.

  3. Research Methodology

    Data for the study was collected via a structured questionnaire designed to assess the views of respondents on the impact of risk factors on cost, time and quality of building construction projects. Respondents were asked to rate their perceptions regarding the severity of risk factors on a five point Likert ordinal scale where 5 = Very Severe, 4 = Severe, 3 = Neutral, 2 = Less Severe and 1 = Not Severe.

    The study was carried out on building construction shareholders in Abuja, Port-Harcourt, and Kaduna and Lagos state. These places where selected due to the high rate of construction activities in these places. The population for the study comprised of clients/developers, contractors and consultants who are involved in construction risk management. A total of 70 questionnaires were distributed but 57 (81.43%) of the data were retrieved. Hinkel et al (1998) however believes that the minimum sample size that allows normal distribution assumptions to be

    used rather than using a t-distribution is 30. Hence the sample size of 70 is justifiable.

    Data obtained from the survey were analysed using Relative Severity Index (RII) method. The Relative Severity index (RII) was calculated using the formula: RII = nW÷N (for 0RII5) Where W= the weight assigned to each strategy by the respondents,

    n = number of respondents, N = the total number of respondents. The limits of definition of RII were: 0 RII1 = Not Severe, 1RII2 = Less Severe, 2RII3 = Neutral, 3RII4 = Severe, 4RII5 = Very Severe. The mean relative severity index was then calculated and a rank ordering of these variables were then assigned based on the calculated mean RII.

  4. Results and Interpretation

    Table 1. Stakeholders perceptive of impact of risk factors on cost of building construction projects

    Clients

    Mean

    Consultants

    mean

    Contractors

    mean

    Average

    Mean

    rank

    Increase of labour cost

    4.210

    5

    4.435

    2

    4.627

    1

    4.424

    1

    Improper planning & budgeting

    3.540

    19

    4.377

    3

    4.234

    3

    4.050

    2

    Inadequate forecast about market

    demand

    4.345

    2

    3.568

    9

    4.021

    5

    3.978

    3

    Change of government policies

    4.214

    4

    3.723

    8

    3.678

    9

    3.872

    4

    Design changes

    4.022

    6

    4.563

    1

    3.490

    15

    3.858

    5

    Internal management problems

    3.765

    13

    4.344

    4

    3.456

    19

    3.855

    6

    Improper project organization-

    structure

    3.876

    9

    4.203

    5

    3.472

    18

    3.850

    7

    Material shortage & thief

    4.432

    1

    3.276

    24

    3.798

    8

    3.835

    8

    Improper verification of contract

    document

    4.231

    3

    3.387

    23

    3.566

    14

    3.728

    9

    Poor quality of procured materials

    3.768

    12

    3.547

    11

    3.453

    22

    3.589

    10

    Rise in Fuel Prices

    3.910

    8

    3.245

    25

    3.423

    24

    3.526

    11

    Increase of material cost

    2.345

    34

    3.985

    6

    4.326

    2

    3.552

    12

    Bureaucracy

    3.432

    24

    3.563

    10

    3.567

    11

    3.521

    13

    Poor communication

    3.657

    17

    3.450

    19

    3.456

    19

    3.521

    13

    Fluctuation of Inflation Rate

    3.456

    23

    3.442

    21

    3.567

    11

    3.488

    15

    Fluctuation of Interest Rate

    4.002

    7

    2.458

    30

    3.985

    7

    3.482

    16

    Change of top management

    3.573

    18

    3.210

    26

    3.650

    11

    3.478

    17

    Unknown site condition

    3.432

    24

    3.457

    13

    3.434

    23

    3.441

    18

    Fluctuation of Exchange rate

    3.789

    10

    2.453

    31

    4.000

    6

    3.414

    19

    Breach of contract by project partners

    3.432

    24

    3.532

    12

    3.243

    28

    3.402

    20

    Corruption/ bribery

    3.675

    15

    2.345

    34

    4.129

    4

    3.383

    21

    Change in climatic condition

    3.218

    28

    3.423

    22

    2.457

    31

    3.327

    22

    Environmental Impact of the project

    3.456

    22

    3.456

    14

    3.236

    29

    3.327

    22

    Law of arbitration clause in contract

    agreement

    2.678

    32

    2.678

    28

    3.456

    19

    3.271

    24

    Improper project feasibility studies

    3.456

    21

    3.452

    18

    2.888

    30

    3.265

    25

    Change in Bank Formalities &

    Regulations

    2.721

    31

    3.456

    14

    3.567

    12

    3.248

    26

    Stiff environmental regulations

    3.456

    20

    2.769

    27

    3.472

    17

    3.232

    27

    Dispute

    3.671

    16

    2.345

    33

    3.657

    10

    3.224

    28

    Lack of enforcement of legal judgment

    2.967

    29

    3.443

    20

    3.245

    27

    3.218

    29

    Absence of team work

    3.772

    11

    3.456

    14

    2.345

    33

    3.191

    30

    Competition from other companies

    2.453

    33

    3.453

    17

    3.423

    24

    3.110

    31

    Shortage of skilful workers

    3.359

    27

    2.451

    32

    3.475

    16

    3.095

    32

    Accidents on site

    2.789

    30

    3.983

    7

    2.234

    34

    3.002

    33

    Healthy working Environment for the

    workers

    3.675

    14

    2.568

    29

    2.456

    32

    2.900

    34

    Figure 1. Stakeholders perceptive of the impact of risk factors on cost of building construction projects

    The study identified 34 major risk factors from literature to get the stakeholders perceptive of the impact of these risk factors on cost of building construction projects. The options Very Severe, Severe, Neutral, Less Severe and Not Severe were use to evaluate the responses, the result is presented in table 2 and figure 1. Figure 1 indicates that 6% and 91% of the impact of risk factors on cost of building construction projects were perceived to be very severe and severe respectively, 3% of these factors have neutral impact while none of the factors were seen to be of less severity or not having severe impact on the cost of building construction projects. As indicated in table 2, increase of labour cost, improper planning and budgeting, inadequate forecast about market demand, change of government policies and design changes were ranked overall as the top 34 risk factors with impact on cost of building construction projects. These findings is consistent with the results of other researches that has reported increase labour cost and improper planning and budgeting as a major risk factor on cost (Florence and Linda, 2006 and Windapo et al, 2010).

    Table 2. Stakeholders perceptive of impact of risk factors on time of building construction projects

    Clients

    Mean

    Designers

    mean

    Contractors

    mean

    Average

    Mean

    rank

    Improper planning & budgeting

    4.201

    6

    3.987

    4

    4.683

    1

    4.290

    1

    Inadequate forecast about

    market demand

    3.987

    9

    4.210

    3

    4.230

    3

    4.142

    2

    Increase of material cost

    4.214

    5

    3.876

    7

    4.241

    2

    4.110

    3

    Increase of labour cost

    4.219

    4

    4.321

    1

    3.786

    11

    4.108

    4

    Improper project

    organization-structure

    4.356

    2

    3.550

    19

    4.102

    4

    4.002

    5

    Improper project

    feasibility studies

    4.100

    8

    3.893

    5

    3.800

    10

    3.931

    6

    Poor communication

    4.106

    7

    3.567

    17

    3.890

    8

    3.854

    7

    Design changes

    3.768

    12

    4.321

    1

    3.462

    21

    3.850

    8

    Change of government

    policies

    3.982

    10

    3.890

    6

    3.670

    15

    3.847

    9

    Bureaucracy

    4.243

    3

    3.245

    9

    3.876

    3.788

    10

    Improper verification of

    contract document

    3.765

    13

    3.569

    16

    3.988

    6

    3.774

    11

    Material shortage & thief

    3.678

    16

    3.675

    13

    3.897

    7

    3.750

    12

    Shortage of skilful

    workers

    4.400

    1

    3.256

    29

    3.567

    18

    3.741

    13

    Change in Bank

    Formalities & Regulations

    3.524

    21

    3.592

    15

    4.029

    5

    3.715

    14

    Change of top

    management

    3.567

    19

    3.560

    18

    3.672

    14

    3.599

    15

    Lack of enforcement of

    legal judgment

    3.287

    26

    3.789

    8

    3.670

    16

    3.582

    16

    Dispute

    3.725

    15

    3.241

    30

    3.684

    12

    3.550

    17

    Corruption/ bribery

    3.478

    22

    3.450

    22

    3.674

    13

    3.534

    18

    Rise in Fuel Prices

    3.743

    14

    3.420

    25

    3.435

    24

    3.532

    19

    Fluctuation of Exchange

    rate

    3.561

    20

    3.651

    14

    3.247

    29

    3.486

    20

    Poor quality of procured

    materials

    3.429

    24

    3.367

    26

    3.650

    17

    3.482

    21

    Absence of team work

    3.456

    23

    3.478

    21

    3.456

    22

    3.463

    22

    Fluctuation of Inflation

    Rate

    3.245

    29/p>

    3.679

    12

    3.456

    23

    3.460

    23

    Unknown site condition

    3.679

    16

    2.980

    31

    3.468

    20

    3.375

    24

    Fluctuation of Interest

    Rate

    3.095

    31

    3.347

    28

    3.564

    19

    3.335

    25

    Law of arbitration clause

    in contract agreement

    3.783

    11

    2.760

    33

    3.426

    26

    3.323

    26

    Change in climatic

    condition

    3.574

    18

    2.876

    32

    3.430

    25

    3.293

    27

    Breach of contract by

    project partners

    3.278

    27

    3.768

    9

    2.678

    34

    3.241

    28

    Stiff environmental

    regulations

    3.324

    25

    3.432

    23

    2.967

    32

    3.241

    28

    Accidents on site

    3.214

    30

    3.168

    30

    3.267

    28

    3.216

    30

    Environmental Impact of the project

    2.984

    32

    3.768

    11

    2.870

    33

    3.207

    31

    Healthy working Environment for the

    workers

    2.578

    33

    3.423

    24

    3.320

    27

    3.107

    32

    Internal management

    problems

    3.276

    28

    2.659

    34

    3.103

    31

    3.012

    33

    Competition from other

    companies

    2.245

    34

    3.493

    19

    3.241

    30

    2.993

    34

    Figure 2 Stakeholders perceptive of the impact of risk factors on time duration of building construction projects.

    To obtain respondents view on the impact of risk factors on time duration of building construction

    projects. A range of risk factors from literature was presented to the respondents for them to decide on the impact of the risk factors on time duration of building construction projects. The rating value of 5, 4, 3, 2, and 1 were assigned to the options Very Severe, Severe, Neutral, Less Severe and Not Severe respectively. The results are ranked in table 3 in which shortage of skillful workers, design changes and improper planning and budgeting were ranked 1st by the client, consultants and contractor respectively. Improper project organization structure, increase in labour cost and increase in material cost were ranked 2nd with relative index of 4.356, 4.321 and 4.241 by the client, consultants and contractors respectively while improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking. Considering the results in table 3, the

    various high relative index of these factors shows that the respondents highly agree that these risk factors has very severe and severe impacts on the time duration of building construction projects in presented in figure 2 where only 3% of these factors has neutral impact while none of the factors were

    seen to be of less severity or not having severe impact on the time duration of building construction projects.

    Table 3. Stakeholders perceptive of impact of risk factors on quality of building construction projects

    Clients Mean

    Designers mean

    Contractors mean

    Average Mean

    Rank

    Corruption/ bribery

    4.201

    6

    3.987

    6

    4.683

    1

    4.290

    1

    Competition from other

    companies

    3.987

    10

    4.210

    4

    4.230

    4

    4.142

    2

    Poor quality of procured

    materials

    3.987

    11

    4.210

    5

    4.230

    5

    4.142

    2

    Design changes

    4.219

    5

    4.321

    3

    3.786

    13

    4.109

    4

    Shortage of skilful

    workers

    4.210

    7

    3.435

    21

    4.627

    2

    4.091

    5

    Unknown site condition

    3.540

    23

    4.377

    1

    4.234

    3

    4.050

    6

    Poor communication

    4.356

    1

    3.550

    14

    4.102

    6

    4.003

    7

    Improper verification of

    contract document

    4.356

    2

    3.550

    15

    4.102

    7

    4.003

    7

    Absence of team work

    3.765

    15

    4.344

    2

    3.456

    25

    3.855

    9

    Change of government

    policies

    4.106

    8

    3.567

    12

    3.890

    11

    3.854

    10

    Improper project

    organization-structure

    3.982

    12

    3.890

    7

    3.670

    16

    3.847

    11

    Improper project

    feasibility studies

    4.243

    3

    3.245

    28

    3.876

    12

    3.788

    12

    Internal management

    problems

    3.765

    16

    3.569

    11

    3.988

    9

    3.774

    13

    Dispute

    4.231

    4

    3.387

    25

    3.566

    23

    3.728

    14

    Bureaucracy

    3.524

    24

    3.592

    10

    4.029

    8

    3.715

    15

    Law of arbitration clause

    in contract agreement

    3.287

    30

    3.789

    8

    3.670

    17

    3.582

    16

    Lack of enforcement of legal judgment

    3.725

    18

    3.241

    30

    3.684

    14

    3.550

    17

    Improper planning &

    budgeting

    3.743

    17

    3.420

    24

    3.435

    28

    3.533

    18

    Change in Bank

    Formalities & Regulations

    3.910

    13

    3.245

    29

    3.423

    29

    3.526

    19

    Rise in Fuel Prices

    3.567

    22

    3.560

    13

    3.672

    15

    3.510

    20

    Change in climatic

    condition

    3.429

    27

    3.367

    26

    3.650

    19

    3.482

    21

    Fluctuation of Inflation

    Rate

    3.429

    28

    3.367

    27

    3.650

    20

    3.482

    21

    Fluctuation of Interest

    Rate

    4.002

    9

    2.458

    33

    3.985

    10

    3.481

    23

    Healthy working Environment for the

    workers

    3.573

    21

    3.210

    31

    3.650

    21

    3.478

    24

    Stiff environmental

    regulations

    3.456

    25

    3.478

    18

    3.456

    26

    3.463

    25

    Fluctuation of Exchange

    rate

    3.245

    31

    3.679

    9

    3.456

    27

    3.460

    26

    Increase of material cost

    3.432

    26

    3.532

    16

    3.243

    30

    3.402

    27

    Increase of labour cost

    3.679

    19

    2.980

    32

    3.468

    24

    3.376

    27

    Change of top

    management

    2.721

    33

    3.456

    19

    3.567

    22

    3.248

    29

    Accidents on site

    3.324

    29

    3.432

    22

    2.967

    32

    3.241

    30

    Inadequate forecast about

    market demand

    3.671

    20

    2.345

    34

    3.657

    18

    3.224

    31

    Material shortage & thief

    3.772

    14

    3.456

    20

    2.345

    34

    3.191

    32

    Breach of contract by

    project partners

    3.218

    32

    3.423

    23

    2.457

    33

    3.033

    33

    Environmental Impact of

    the project

    2.245

    34

    3.493

    17

    3.241

    31

    2.993

    34

    Also the rating value of 5, 4, 3, 2, and 1 were assigned to the options Very Severe, Severe, Neutral, Less Severe and Not Severe respectively in obtaining Shareholders perceptive of impact of risk factors on quality of building construction projects. Table 4 below shows the ranking of the results in which corruption/bribery, competition from other companies in form of employing lowest bid to get the contract, poor quality of procured materials, design changes and shortage of skilful workers were ranked overall as the top 34 risk factors which impacts on quality of building construction projects while accident on site, inadequate forecast about market demand, material shortage and thief, breach of contract by project partners and environmental impact of the project were ranked as the risk factors that have the least (of the 34 risk factors from literature) impact on the quality of building construction Projects. Also the results in table 4 show that there is a positive nearness responds from the consultants and contractors than that of the clients which might be as a result of the professional views in their responses.

  5. Conclusion and Recommendations

    The study has established that among the impact of the various risk factors on cost of building construction projects, increase of labour cost, improper planning and budgeting, inadequate forecast about market demand, change of government policies and design changes top the list while among

    the impact of the various risk factors on time duration of building construction projects, improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking. Also, among the impact of the various risk factors on quality of building construction projects, corruption/bribery, competition from other companies in form of employing lowest bid to get contracts, poor quality of procured materials, design changes and shortage of skilful workers top the list.

    Based on the outcome of the study the following recommendations are made towards improving risk management so as to reduce cost and time overrun and improve the quality of building construction project.

    1. to reduce cost overrun of building construction projects, efforts should be made to mitigate increase in labour cost through adequate planning and budgeting and adequate forecast about market demand as well as taking into consideration other risk factors such as change of government policies and design changes .

    2. Proper planning and budgeting, proper project organization structure, adequate forecast about market demand, practice of bulk purchase of construction materials in case of rise in cost of the materials as well as in-house ownership and management of labour to mitigate labour cost in case of increase in labour cost should be put into consideration to reduce time overrun of building construction projects.

    3. to improve the quality of building construction projects, efforts should be made to curb corruption/bribery practices which most often will result in inadequate funds left for the actual project execution, encouraging the award of contract not just based on the lowest bidder but also based on some degree of quality assurances, providing detail construction material l schedules as part of contract documents, involving all stake holders to have input during design stages of the projects and encouraging skill acquisition in construction trades and training of construction craftsmen so as to mitigate shortage of skilful workers in the construction industry.

References

  1. Ashworth, A and Hogg, K. W.(2002). Procedure for the Quantity Surveyors, 11th edition, Blackwell Science Ltd., Oxford, 2002.

  2. Berke, P.R. and Conroy, M.M. (2000). Are we planning for sustainable development? Journal of the American Planning Association, Winter 66 (1) (2000), 21-33.

  3. Chan, E.H.W. and Lee, G.K.L. (2008). A sustainability evaluation of government-led urban renewal projects,

    Journal of Facilities, Emerald Group Publishing Limited 26 (13) (2008), 526-541.

  4. Chapman, R.J. (2001). The controlling influence on effective risk identification and assessment for construction design management. International Journal of Project Management 19 (2001), 147-160.

  5. Dada J.O. and Jagboro, G.O (2007) An evaluation of the impact of risk on project cost overrun in the Nigerian construction industry, Journal of Financial Management of Property and Construction, 12 (1) (2007), 37-44.

  6. Edward, P.J. and Bowen,P.A.(1998) Risk and risk management in construction: A Review and Future

    Directions for Research in Engineering and Construction.

  7. Florence, Y.Y.L. and Linda, H.(2006) Risks faced by Singapore firms when undertaking construction projects in India. International Journal of Project Management 24 (38) (2006), 261270.

  8. Hyun-Ho, C.H.C. and Seo, J.W.(2004) Risk assessment methodology for underground construction projects. Journal of Construction

    Engineering and Management (ASCE), 12 (2004),

    258-272.

  9. Joshua, O.D (2010). Strategies for mitigating risk in construction projects. The 40th Annual General Meeting/ Conference of the Nigeria Institute of Building (NIOB), Asaba, Delta State, July, 7th-11th (2010).

  10. Odeyinka, H.A.(2000). On an evaluation of the use of insurance in managing construction risks, Construction Management and Economics, 18 (2000), 519-524.

  11. Odeyinka, H.A.; Lowa, J.G.and Kaka,A. (2008). On an evaluation of risks factors impacting construction cash flow forecast, Journal of Financial Management of Property and Construction, 13 (1) (2008), 5-17.

  12. Ojo, G.K. (2010). An assessment of the construction site risk-related factors. The 40th Annual General Meeting/ Conference of the Nigeria Institute of Building (NIOB), Asaba, Delta State, July, 7th-11th 2010.

  13. Osama, A.J. and Salman, A. (2003). Risk assessment in construction, Journal of Construction Engineering and Management (ASCE) 129 (5) (2003), 492-500.

  14. Prashant, K. and Chris, H. (2001). Exchange rate risk management in international construction ventures, Journal of Management in Engineering (ASCE), 17 (4) (2001), 186-191.

  15. Project Management Institute (PIM) (1996). Project Management Body of Knowledge, PA., Pennsylvania, (1996).

  16. Shen, L.Y.(1997). Project management in Hong Kong, International Journal of Project Management, 15 (2) (1997), 101-105.

  17. Shen, L.Y.; Wu, G.W.C. and Ng, C.S.K. (2011) Risk assessment for construction joint ventures in China. Journal of Construction Engineering and Management (ASCE) 127 (1) (2011), 76-81.

  18. Shou, Q.W.; Mohammad, F.D. and Muhammad, Y.A.(2004). Risk management framework for construction projects in developing countries, Construction Management and Economics 22 (30) (2004), 237252.

  19. Tah, J.H.M. and Carr,V. (2000). A proposal for construction risk assessment using fuzzy logic.

    Construction Management and Economics 18 (2000),

    491-500.

  20. Thomas, A.V.; Stayanarayana, N. and Kalanindi,

    N. (2003). Risk perception analysis in India. Construction Management and Economics, 21 (2003), 393407.

  21. Windapo, A.O.; Omeife, C.and Wahap, L.A. on stakeholders perception of key risks in oil and gas construction projects. 40th Annual General meeting/ Conference of the Nigeria institute of building (NIOB), Asaba, Delta State, July 7th 11th (2010).

  22. Seung, H.H.; James, E.D.; Young, L. and Jong,

    H.O. (2004) Multi criteria financial portfolio risk management for international projects. Journal of Construction Engineering and Management (ASCE) (27) (2004), 346-356.

  23. Ward, S. and Chapman, C. (2003). Transforming project risk management (RM) into project uncertainty management., International Journal of Project Management, 21 (2003), 97-105.

  24. Hinkel E; Wiersma, W and Jurs, S.G (1988): Applied Statistics for the Behavioural Sciences. Houghton, Mifflin, Boston.

Leave a Reply