- Open Access
- Total Downloads : 829
- Authors : Calistus Ayegba, Augustine Edoka Ijigah, Adakole Edwin Agbo
- Paper ID : IJERTV3IS10189
- Volume & Issue : Volume 03, Issue 01 (January 2014)
- Published (First Online): 01-01-2014
- ISSN (Online) : 2278-0181
- Publisher Name : IJERT
- License: This work is licensed under a Creative Commons Attribution 4.0 International License
Stakeholders Perspective of the Impact of Risk Factors on Cost, Time and Quality of Building Construction Projects
Calistus Ayegba1*, Augustine Edoka Ijigah 2, Adakole Edwin Agbo 3,
-
Department of Building, Federal University of Technology Minna Niger State, Nigeria
-
Department of Building, Federal University of Technology Minna Niger State, Nigeria
-
Department of Building, Federal University of Technology Minna Niger State, Nigeria
Abstract
The paper considers the stakeholders perspective of the impact of risk factors on cost, time and quality of building construction projects. In the study, stakeholders perceptive of the impact of risk factors on cost of building construction projects as well as stakeholders perceptive of the impact of risk factors on time duration of building construction projects and stakeholders perceptive of the impact of risk factors on quality of building construction projects were assessed. Data for the study was obtained Data for the study was collected via a structured questionnaire administered to respondents in Abuja, Port-Harcourt, Kaduna and Lagos state. The questionnaires are designed to assess the views of respondents on the impact of risk factors on cost, time and quality of building construction projects. Respondents were asked to rate their perceptions regarding the severity of risk factors on a five point Likert ordinal scale where 5 = Very Severe, 4 = Severe, 3 = Neutral, 2 = Less Severe and 1 = Not Severe. Data obtained from the survey were analysed using Relative Severity Index (RII) method. The Relative Severity index (RII) was calculated using the formula: RII = nW÷N (for 0RII5) Where W= the weight assigned to each strategy by the respondents, n = number of respondents, N = the total number of respondents. The limits of definition of RII were: 0 RII1 = Not Severe, 1RII2 = Less Severe, 2RII3
= Neutral, 3RII4 = Severe, 4RII5 = Very Severe. The mean relative severity index was then calculated and a rank ordering of these variables were then assigned based on the calculated relative index (RII). Findings revealed that 6% and 91% of the impact of risk factors on cost of building
construction projects were perceived to be very severe and severe respectively, 3% of these factors have neutral impact while none of the factors were seen to be of less severity or not having severe impact on the cost of building construction projects. Furthermore, on stakeholders perceptive of impact of risk factors on time duration of building construction projects, improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking with relative index of 4.290, 4.142, 4.110, 4.108 and 4.002 respectively while on stakeholders perceptive of impact of risk factors on quality of building construction projects corruption/bribery, competition from other companies in form of employing lowest bid to get the contract, poor quality of procured materials, design changes and shortage of skilful workers were ranked overall as the top 34 risk factors identified from literature review.
Keywords: Risk Management, Risk factors, Cost, Time, Quality, Construction Industry.
-
Construction industry development is a common and contemporary goal of many urban development policies in various countries [2] and [3]. Development of the construction industry also requires knowledge of risk management policies. It is a well establish fact that every stage of the construction process, from initial investment appraisal through to construction and use of the built facility, is subject to risk for all the parties involved. Indeed, compared to other industries, the Nigeria construction industry has a particularly poor record in this regard with high number of construction related risks occurring each year [12] and [20]. In recent
times, the nature, incident and impact of risk in construction have become a topic of interest because of the effects on quality, time and cost of construction projects [9], [12] and [20]. Risk is important to contractors as well as clients and consultants within the construction industry; however, the problems of risk assessment are complex and poorly understood in practice[18]. In a related development [1] pointed out that construction activities are full of risk which include those that may relate to external, commercial, design, construction and operation. However, they have to be considered for effective management in order to retain the initial objective of the project. Risk is defined as the probability that an unfavorable outcome will occur [15]. According to [6], risk is the probability that an adverse event occurs during a stated period of time. [1], [18] and [7] stated that projects have life cycles or a sequence of stages and activities from origin to completion and there is always a degree of risk associated with each stage. [11] and [23] pointed out that too often this risk is not dealt with satisfactorily which has resulted into poorly performed projects in the industry. They submit that the way out is the integration of risk management techniques into the estimation of construction projects cost and time, as this will help considerably to avoid excessive overrun.
Many approaches have been suggested for the classification of risks. However, all of them pointed to the identifying the primary source of risk central to construction activities which triggered the risk. [12] Identified physical, design, environmental, logistics, financial, legal political, construction and operational risk while [6] classified risks into natural and human risks, subdivision of each of these classifications were also listed. The classification of risk are therefore combined into physical, political, environmental, management, legal, technical and market risk. [16] Listed the following as six major processes involved in project risk management: Risk management planning, risk identification, qualitative risk analysis, quantitative risk analysis, risk response planning and risk monitoring and control. Each risk management process results in a specific deliverable which is used as the foundation for the subsequent process.
Track record of successful construction projects would have been greatly improved if more companies had included risk as an integrated part of the project control and quality system [12]. Therefore it is necessary to understand the nature or risks before any management of risk can occur as risk comes in many forms and often the nature of risk depends on the situation.
-
Statement of Problem
The Nigerian construction industry has been associated with repeated construction time overrun, construction cost overrun and low quality construction products in recent years but according to [5], [11] and [12] required attention to risk management will reduce project time overrun, cost overrun as well as improve the quality of products and cases of abandoned projects. Construction itself is prone to a variety of risks, such as financial, management, environmental and technical related risks, mainly because of the materials used, nature of design, methods of construction, locations and layout, physical structure and the use to which buildings are put [4]. Previous study by [14], [13] and [21] suggests the application of risk management model of project characteristic to manage the risks inherent in construction project but according to
[16] quantitative analytical techniques for managing risk has been rarel used due to limited understanding and experience of the stakeholders in the construction industry. Risk management of construction projects gives the most emphasis to environmental, economic and social issues. Previous researches has identified what constitute risk factors on construction projects but stakeholders perspective on the impacts of these risk factors on cost, time and quality of construction projects as not been well looked into. Based on this the study set out to analyze stakeholders perspective of the impact of risk factors to the cost, time and quality of construction projects so as to reduce construction cost and time overruns as well as improve the quality of construction products. -
Research Methodology
Data for the study was collected via a structured questionnaire designed to assess the views of respondents on the impact of risk factors on cost, time and quality of building construction projects. Respondents were asked to rate their perceptions regarding the severity of risk factors on a five point Likert ordinal scale where 5 = Very Severe, 4 = Severe, 3 = Neutral, 2 = Less Severe and 1 = Not Severe.
The study was carried out on building construction shareholders in Abuja, Port-Harcourt, and Kaduna and Lagos state. These places where selected due to the high rate of construction activities in these places. The population for the study comprised of clients/developers, contractors and consultants who are involved in construction risk management. A total of 70 questionnaires were distributed but 57 (81.43%) of the data were retrieved. Hinkel et al (1998) however believes that the minimum sample size that allows normal distribution assumptions to be
used rather than using a t-distribution is 30. Hence the sample size of 70 is justifiable.
Data obtained from the survey were analysed using Relative Severity Index (RII) method. The Relative Severity index (RII) was calculated using the formula: RII = nW÷N (for 0RII5) Where W= the weight assigned to each strategy by the respondents,
n = number of respondents, N = the total number of respondents. The limits of definition of RII were: 0 RII1 = Not Severe, 1RII2 = Less Severe, 2RII3 = Neutral, 3RII4 = Severe, 4RII5 = Very Severe. The mean relative severity index was then calculated and a rank ordering of these variables were then assigned based on the calculated mean RII.
-
Results and Interpretation
Table 1. Stakeholders perceptive of impact of risk factors on cost of building construction projects
Clients
Mean
Consultants
mean
Contractors
mean
Average
Mean
rank
Increase of labour cost
4.210
5
4.435
2
4.627
1
4.424
1
Improper planning & budgeting
3.540
19
4.377
3
4.234
3
4.050
2
Inadequate forecast about market
demand
4.345
2
3.568
9
4.021
5
3.978
3
Change of government policies
4.214
4
3.723
8
3.678
9
3.872
4
Design changes
4.022
6
4.563
1
3.490
15
3.858
5
Internal management problems
3.765
13
4.344
4
3.456
19
3.855
6
Improper project organization-
structure
3.876
9
4.203
5
3.472
18
3.850
7
Material shortage & thief
4.432
1
3.276
24
3.798
8
3.835
8
Improper verification of contract
document
4.231
3
3.387
23
3.566
14
3.728
9
Poor quality of procured materials
3.768
12
3.547
11
3.453
22
3.589
10
Rise in Fuel Prices
3.910
8
3.245
25
3.423
24
3.526
11
Increase of material cost
2.345
34
3.985
6
4.326
2
3.552
12
Bureaucracy
3.432
24
3.563
10
3.567
11
3.521
13
Poor communication
3.657
17
3.450
19
3.456
19
3.521
13
Fluctuation of Inflation Rate
3.456
23
3.442
21
3.567
11
3.488
15
Fluctuation of Interest Rate
4.002
7
2.458
30
3.985
7
3.482
16
Change of top management
3.573
18
3.210
26
3.650
11
3.478
17
Unknown site condition
3.432
24
3.457
13
3.434
23
3.441
18
Fluctuation of Exchange rate
3.789
10
2.453
31
4.000
6
3.414
19
Breach of contract by project partners
3.432
24
3.532
12
3.243
28
3.402
20
Corruption/ bribery
3.675
15
2.345
34
4.129
4
3.383
21
Change in climatic condition
3.218
28
3.423
22
2.457
31
3.327
22
Environmental Impact of the project
3.456
22
3.456
14
3.236
29
3.327
22
Law of arbitration clause in contract
agreement
2.678
32
2.678
28
3.456
19
3.271
24
Improper project feasibility studies
3.456
21
3.452
18
2.888
30
3.265
25
Change in Bank Formalities &
Regulations
2.721
31
3.456
14
3.567
12
3.248
26
Stiff environmental regulations
3.456
20
2.769
27
3.472
17
3.232
27
Dispute
3.671
16
2.345
33
3.657
10
3.224
28
Lack of enforcement of legal judgment
2.967
29
3.443
20
3.245
27
3.218
29
Absence of team work
3.772
11
3.456
14
2.345
33
3.191
30
Competition from other companies
2.453
33
3.453
17
3.423
24
3.110
31
Shortage of skilful workers
3.359
27
2.451
32
3.475
16
3.095
32
Accidents on site
2.789
30
3.983
7
2.234
34
3.002
33
Healthy working Environment for the
workers
3.675
14
2.568
29
2.456
32
2.900
34
Figure 1. Stakeholders perceptive of the impact of risk factors on cost of building construction projects
The study identified 34 major risk factors from literature to get the stakeholders perceptive of the impact of these risk factors on cost of building construction projects. The options Very Severe, Severe, Neutral, Less Severe and Not Severe were use to evaluate the responses, the result is presented in table 2 and figure 1. Figure 1 indicates that 6% and 91% of the impact of risk factors on cost of building construction projects were perceived to be very severe and severe respectively, 3% of these factors have neutral impact while none of the factors were seen to be of less severity or not having severe impact on the cost of building construction projects. As indicated in table 2, increase of labour cost, improper planning and budgeting, inadequate forecast about market demand, change of government policies and design changes were ranked overall as the top 34 risk factors with impact on cost of building construction projects. These findings is consistent with the results of other researches that has reported increase labour cost and improper planning and budgeting as a major risk factor on cost (Florence and Linda, 2006 and Windapo et al, 2010).
Table 2. Stakeholders perceptive of impact of risk factors on time of building construction projects
Clients
Mean
Designers
mean
Contractors
mean
Average
Mean
rank
Improper planning & budgeting
4.201
6
3.987
4
4.683
1
4.290
1
Inadequate forecast about
market demand
3.987
9
4.210
3
4.230
3
4.142
2
Increase of material cost
4.214
5
3.876
7
4.241
2
4.110
3
Increase of labour cost
4.219
4
4.321
1
3.786
11
4.108
4
Improper project
organization-structure
4.356
2
3.550
19
4.102
4
4.002
5
Improper project
feasibility studies
4.100
8
3.893
5
3.800
10
3.931
6
Poor communication
4.106
7
3.567
17
3.890
8
3.854
7
Design changes
3.768
12
4.321
1
3.462
21
3.850
8
Change of government
policies
3.982
10
3.890
6
3.670
15
3.847
9
Bureaucracy
4.243
3
3.245
9
3.876
3.788
10
Improper verification of
contract document
3.765
13
3.569
16
3.988
6
3.774
11
Material shortage & thief
3.678
16
3.675
13
3.897
7
3.750
12
Shortage of skilful
workers
4.400
1
3.256
29
3.567
18
3.741
13
Change in Bank
Formalities & Regulations
3.524
21
3.592
15
4.029
5
3.715
14
Change of top
management
3.567
19
3.560
18
3.672
14
3.599
15
Lack of enforcement of
legal judgment
3.287
26
3.789
8
3.670
16
3.582
16
Dispute
3.725
15
3.241
30
3.684
12
3.550
17
Corruption/ bribery
3.478
22
3.450
22
3.674
13
3.534
18
Rise in Fuel Prices
3.743
14
3.420
25
3.435
24
3.532
19
Fluctuation of Exchange
rate
3.561
20
3.651
14
3.247
29
3.486
20
Poor quality of procured
materials
3.429
24
3.367
26
3.650
17
3.482
21
Absence of team work
3.456
23
3.478
21
3.456
22
3.463
22
Fluctuation of Inflation
Rate
3.245
29/p>
3.679
12
3.456
23
3.460
23
Unknown site condition
3.679
16
2.980
31
3.468
20
3.375
24
Fluctuation of Interest
Rate
3.095
31
3.347
28
3.564
19
3.335
25
Law of arbitration clause
in contract agreement
3.783
11
2.760
33
3.426
26
3.323
26
Change in climatic
condition
3.574
18
2.876
32
3.430
25
3.293
27
Breach of contract by
project partners
3.278
27
3.768
9
2.678
34
3.241
28
Stiff environmental
regulations
3.324
25
3.432
23
2.967
32
3.241
28
Accidents on site
3.214
30
3.168
30
3.267
28
3.216
30
Environmental Impact of the project
2.984
32
3.768
11
2.870
33
3.207
31
Healthy working Environment for the
workers
2.578
33
3.423
24
3.320
27
3.107
32
Internal management
problems
3.276
28
2.659
34
3.103
31
3.012
33
Competition from other
companies
2.245
34
3.493
19
3.241
30
2.993
34
Figure 2 Stakeholders perceptive of the impact of risk factors on time duration of building construction projects.
To obtain respondents view on the impact of risk factors on time duration of building construction
projects. A range of risk factors from literature was presented to the respondents for them to decide on the impact of the risk factors on time duration of building construction projects. The rating value of 5, 4, 3, 2, and 1 were assigned to the options Very Severe, Severe, Neutral, Less Severe and Not Severe respectively. The results are ranked in table 3 in which shortage of skillful workers, design changes and improper planning and budgeting were ranked 1st by the client, consultants and contractor respectively. Improper project organization structure, increase in labour cost and increase in material cost were ranked 2nd with relative index of 4.356, 4.321 and 4.241 by the client, consultants and contractors respectively while improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking. Considering the results in table 3, the
various high relative index of these factors shows that the respondents highly agree that these risk factors has very severe and severe impacts on the time duration of building construction projects in presented in figure 2 where only 3% of these factors has neutral impact while none of the factors were
seen to be of less severity or not having severe impact on the time duration of building construction projects.
Table 3. Stakeholders perceptive of impact of risk factors on quality of building construction projects
Clients Mean
Designers mean
Contractors mean
Average Mean
Rank
Corruption/ bribery
4.201
6
3.987
6
4.683
1
4.290
1
Competition from other
companies
3.987
10
4.210
4
4.230
4
4.142
2
Poor quality of procured
materials
3.987
11
4.210
5
4.230
5
4.142
2
Design changes
4.219
5
4.321
3
3.786
13
4.109
4
Shortage of skilful
workers
4.210
7
3.435
21
4.627
2
4.091
5
Unknown site condition
3.540
23
4.377
1
4.234
3
4.050
6
Poor communication
4.356
1
3.550
14
4.102
6
4.003
7
Improper verification of
contract document
4.356
2
3.550
15
4.102
7
4.003
7
Absence of team work
3.765
15
4.344
2
3.456
25
3.855
9
Change of government
policies
4.106
8
3.567
12
3.890
11
3.854
10
Improper project
organization-structure
3.982
12
3.890
7
3.670
16
3.847
11
Improper project
feasibility studies
4.243
3
3.245
28
3.876
12
3.788
12
Internal management
problems
3.765
16
3.569
11
3.988
9
3.774
13
Dispute
4.231
4
3.387
25
3.566
23
3.728
14
Bureaucracy
3.524
24
3.592
10
4.029
8
3.715
15
Law of arbitration clause
in contract agreement
3.287
30
3.789
8
3.670
17
3.582
16
Lack of enforcement of legal judgment
3.725
18
3.241
30
3.684
14
3.550
17
Improper planning &
budgeting
3.743
17
3.420
24
3.435
28
3.533
18
Change in Bank
Formalities & Regulations
3.910
13
3.245
29
3.423
29
3.526
19
Rise in Fuel Prices
3.567
22
3.560
13
3.672
15
3.510
20
Change in climatic
condition
3.429
27
3.367
26
3.650
19
3.482
21
Fluctuation of Inflation
Rate
3.429
28
3.367
27
3.650
20
3.482
21
Fluctuation of Interest
Rate
4.002
9
2.458
33
3.985
10
3.481
23
Healthy working Environment for the
workers
3.573
21
3.210
31
3.650
21
3.478
24
Stiff environmental
regulations
3.456
25
3.478
18
3.456
26
3.463
25
Fluctuation of Exchange
rate
3.245
31
3.679
9
3.456
27
3.460
26
Increase of material cost
3.432
26
3.532
16
3.243
30
3.402
27
Increase of labour cost
3.679
19
2.980
32
3.468
24
3.376
27
Change of top
management
2.721
33
3.456
19
3.567
22
3.248
29
Accidents on site
3.324
29
3.432
22
2.967
32
3.241
30
Inadequate forecast about
market demand
3.671
20
2.345
34
3.657
18
3.224
31
Material shortage & thief
3.772
14
3.456
20
2.345
34
3.191
32
Breach of contract by
project partners
3.218
32
3.423
23
2.457
33
3.033
33
Environmental Impact of
the project
2.245
34
3.493
17
3.241
31
2.993
34
Also the rating value of 5, 4, 3, 2, and 1 were assigned to the options Very Severe, Severe, Neutral, Less Severe and Not Severe respectively in obtaining Shareholders perceptive of impact of risk factors on quality of building construction projects. Table 4 below shows the ranking of the results in which corruption/bribery, competition from other companies in form of employing lowest bid to get the contract, poor quality of procured materials, design changes and shortage of skilful workers were ranked overall as the top 34 risk factors which impacts on quality of building construction projects while accident on site, inadequate forecast about market demand, material shortage and thief, breach of contract by project partners and environmental impact of the project were ranked as the risk factors that have the least (of the 34 risk factors from literature) impact on the quality of building construction Projects. Also the results in table 4 show that there is a positive nearness responds from the consultants and contractors than that of the clients which might be as a result of the professional views in their responses.
-
Conclusion and Recommendations
The study has established that among the impact of the various risk factors on cost of building construction projects, increase of labour cost, improper planning and budgeting, inadequate forecast about market demand, change of government policies and design changes top the list while among
the impact of the various risk factors on time duration of building construction projects, improper planning and budgeting, inadequate forecast about market demand, increase of material cost, increase in labour cost and improper project organization structure were giving the overall top ranking. Also, among the impact of the various risk factors on quality of building construction projects, corruption/bribery, competition from other companies in form of employing lowest bid to get contracts, poor quality of procured materials, design changes and shortage of skilful workers top the list.
Based on the outcome of the study the following recommendations are made towards improving risk management so as to reduce cost and time overrun and improve the quality of building construction project.
-
to reduce cost overrun of building construction projects, efforts should be made to mitigate increase in labour cost through adequate planning and budgeting and adequate forecast about market demand as well as taking into consideration other risk factors such as change of government policies and design changes .
-
Proper planning and budgeting, proper project organization structure, adequate forecast about market demand, practice of bulk purchase of construction materials in case of rise in cost of the materials as well as in-house ownership and management of labour to mitigate labour cost in case of increase in labour cost should be put into consideration to reduce time overrun of building construction projects.
-
to improve the quality of building construction projects, efforts should be made to curb corruption/bribery practices which most often will result in inadequate funds left for the actual project execution, encouraging the award of contract not just based on the lowest bidder but also based on some degree of quality assurances, providing detail construction material l schedules as part of contract documents, involving all stake holders to have input during design stages of the projects and encouraging skill acquisition in construction trades and training of construction craftsmen so as to mitigate shortage of skilful workers in the construction industry.
-
References
-
Ashworth, A and Hogg, K. W.(2002). Procedure for the Quantity Surveyors, 11th edition, Blackwell Science Ltd., Oxford, 2002.
-
Berke, P.R. and Conroy, M.M. (2000). Are we planning for sustainable development? Journal of the American Planning Association, Winter 66 (1) (2000), 21-33.
-
Chan, E.H.W. and Lee, G.K.L. (2008). A sustainability evaluation of government-led urban renewal projects,
Journal of Facilities, Emerald Group Publishing Limited 26 (13) (2008), 526-541.
-
Chapman, R.J. (2001). The controlling influence on effective risk identification and assessment for construction design management. International Journal of Project Management 19 (2001), 147-160.
-
Dada J.O. and Jagboro, G.O (2007) An evaluation of the impact of risk on project cost overrun in the Nigerian construction industry, Journal of Financial Management of Property and Construction, 12 (1) (2007), 37-44.
-
Edward, P.J. and Bowen,P.A.(1998) Risk and risk management in construction: A Review and Future
Directions for Research in Engineering and Construction.
-
Florence, Y.Y.L. and Linda, H.(2006) Risks faced by Singapore firms when undertaking construction projects in India. International Journal of Project Management 24 (38) (2006), 261270.
-
Hyun-Ho, C.H.C. and Seo, J.W.(2004) Risk assessment methodology for underground construction projects. Journal of Construction
Engineering and Management (ASCE), 12 (2004),
258-272.
-
Joshua, O.D (2010). Strategies for mitigating risk in construction projects. The 40th Annual General Meeting/ Conference of the Nigeria Institute of Building (NIOB), Asaba, Delta State, July, 7th-11th (2010).
-
Odeyinka, H.A.(2000). On an evaluation of the use of insurance in managing construction risks, Construction Management and Economics, 18 (2000), 519-524.
-
Odeyinka, H.A.; Lowa, J.G.and Kaka,A. (2008). On an evaluation of risks factors impacting construction cash flow forecast, Journal of Financial Management of Property and Construction, 13 (1) (2008), 5-17.
-
Ojo, G.K. (2010). An assessment of the construction site risk-related factors. The 40th Annual General Meeting/ Conference of the Nigeria Institute of Building (NIOB), Asaba, Delta State, July, 7th-11th 2010.
-
Osama, A.J. and Salman, A. (2003). Risk assessment in construction, Journal of Construction Engineering and Management (ASCE) 129 (5) (2003), 492-500.
-
Prashant, K. and Chris, H. (2001). Exchange rate risk management in international construction ventures, Journal of Management in Engineering (ASCE), 17 (4) (2001), 186-191.
-
Project Management Institute (PIM) (1996). Project Management Body of Knowledge, PA., Pennsylvania, (1996).
-
Shen, L.Y.(1997). Project management in Hong Kong, International Journal of Project Management, 15 (2) (1997), 101-105.
-
Shen, L.Y.; Wu, G.W.C. and Ng, C.S.K. (2011) Risk assessment for construction joint ventures in China. Journal of Construction Engineering and Management (ASCE) 127 (1) (2011), 76-81.
-
Shou, Q.W.; Mohammad, F.D. and Muhammad, Y.A.(2004). Risk management framework for construction projects in developing countries, Construction Management and Economics 22 (30) (2004), 237252.
-
Tah, J.H.M. and Carr,V. (2000). A proposal for construction risk assessment using fuzzy logic.
Construction Management and Economics 18 (2000),
491-500.
-
Thomas, A.V.; Stayanarayana, N. and Kalanindi,
N. (2003). Risk perception analysis in India. Construction Management and Economics, 21 (2003), 393407.
-
Windapo, A.O.; Omeife, C.and Wahap, L.A. on stakeholders perception of key risks in oil and gas construction projects. 40th Annual General meeting/ Conference of the Nigeria institute of building (NIOB), Asaba, Delta State, July 7th 11th (2010).
-
Seung, H.H.; James, E.D.; Young, L. and Jong,
H.O. (2004) Multi criteria financial portfolio risk management for international projects. Journal of Construction Engineering and Management (ASCE) (27) (2004), 346-356.
-
Ward, S. and Chapman, C. (2003). Transforming project risk management (RM) into project uncertainty management., International Journal of Project Management, 21 (2003), 97-105.
-
Hinkel E; Wiersma, W and Jurs, S.G (1988): Applied Statistics for the Behavioural Sciences. Houghton, Mifflin, Boston.